ODOT contract 250216 bid tabulation

D08-TSG-FY2025/FY2026 (SIGNALIZATION). Let by Ohio DOT on April 24, 2025, District 8. 3 bids received; low bid $1,965,200 by Miller Cable Company, +1.8% against the engineer's estimate of $1,931,000.

Owner
Ohio DOT
Letting
24 APR 2025
Pay items
122
Data through
12 NOV 2026

2 of the 3 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Miller Cable Company$1,965,200Low+2.0%
2Complete General Construction Company$1,996,386+2.0%+3.0%
ODOT contract 250216: bids by rank

Engineer's estimate: $1,931,000.

Bid tabulation

LinePay itemUnitQuantity1. Miller Cable Company2. Complete General Construction Company
1Walk removed (202E30000)SF200$21.00$9.00
2Curb removed (202E32000)FT50$60.00$9.00
34" concrete walk (608E10000)SF200$40.00$30.00
4Curb ramp, as per plan (608E52001)SF250$190.00$35.00
54" conduit, type E (611E00400)FT50$4.00$20.00
6Bracket arm, 12' (625E18100)EACH1$1,350.00$1,600.00
7No. 10 AWG pole and bracket cable (625E23400)FT89$1.50$1.50
8Conduit, 2", 725.051 (625E25408)FT419$11.00$12.00
9Conduit, 4", 725.051 (625E25604)FT469$18.00$12.50
10Conduit, jacked or drilled, 725.052, 4" (625E25908)FT1,311$57.00$44.50
11Luminaire, conventional, solid state (LED), 120V, (625E26252)EACH1$450.00$600.00
12Trench (625E29000)FT819$12.00$18.00
13Trench in paved area (625E29400)FT100$33.00$52.50
14Pull box, 725.08, 24" (625E30706)EACH26$1,200.00$1,400.00
15Pull box removed (625E31510)EACH24$225.00$425.00
16Ground rod (625E32000)EACH34$265.00$300.00
17Underground warning marking tape (625E36010)FT819$2.00$1.70
18Ground mounted support, no. 3 post (630E03100)FT100$16.50$16.50
19Sign attachment assembly (630E75000)EACH8$875.00$875.00
20Sign hanger assembly, span wire (630E79000)EACH8$485.00$485.00
21Sign hanger assembly, mast arm (630E79100)EACH14$395.00$395.00
22Sign, flat sheet (630E80100)SF229.10$20.00$20.00
23Sign, overhead extrusheet (630E80224)SF266$25.50$25.50
24Removal of ground mounted sign and disposal (630E84900)EACH7$15.00$15.00
25Removal of ground mounted post support and disposal (630E86002)EACH6$25.00$25.00
26Removal of overhead mounted sign and disposal (630E87400)EACH4$245.00$245.00
27Removal of overhead sign support and disposal, type TC-9.10 (630E89800)EACH2$1,430.00$1,430.00
28Signing, misc.:solar-powered amish buggy warning S (630E97700)EACH1$9,500.00$34,000
29Center line, type 1 (642E00300)MI0.25$12,230$5,400.00
30Channelizing line, 12" (644E00404)FT50$6.75$1.70
31Stop line (644E00500)FT100$22.50$4.85
32Crosswalk line, 24" (644E00630)FT500$18.00$4.85
33Transverse/diagonal line (644E00700)FT100$22.50$4.85
34Island marking (644E00900)SF100$13.50$4.85
35Lane arrow (644E01300)EACH2$370.00$125.00
36Removal of pavement marking (644E30000)FT200$19.40$4.00
37Removal of pavement marking (644E30010)SF100$38.80$4.00
38Removal of pavement marking (644E30020)EACH2$535.00$100.00
39Vehicular signal head, (LED), 1-section, 12" lens, 4-way, aluminum (632E04816)EACH1$2,200.00$2,000.00
40Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH22$1,300.00$1,025.00
41Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH19$1,300.00$1,025.00
42Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064)EACH2$1,525.00$1,250.00
43Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064)EACH4$1,800.00$1,500.00
44Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086)EACH10$2,125.00$1,800.00
45Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH15$185.00$165.00
46Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH576$75.00$70.00
47Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH584$75.00$70.00
48Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH597$75.00$70.00
49Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH32$150.00$210.00
50Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH237$80.00$70.00
51Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH2$95.00$100.00
52Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH95$80.00$70.00
53Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH2$95.00$90.00
54Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH208$175.00$140.00
55Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH211$80.00$75.00
56Relamp existing signal section with LED lamp unit, as per plan (632E10101)EACH2$95.00$90.00
57Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH10$825.00$660.00
58Accessible pedestrian pushbutton (632E20750)EACH10$950.00$850.00
59Covering of vehicular signal head (632E25000)EACH59$40.00$40.00
60Covering of pedestrian signal head (632E25010)EACH10$30.00$30.00
61Disconnect switch with enclosure (632E28200)EACH2$1,000.00$2,250.00
62Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200)FT1,000$20.00$20.00
63Tether wire, with accessories (632E30600)FT1,000$20.00$24.00
64Signal cable, 5 conductor, no. 14 AWG (632E40500)FT500$3.00$3.00
65Signal cable, 7 conductor, no. 14 AWG (632E40700)FT9,555$3.20$3.50
66Strain pole foundation (632E64000)EACH8$7,100.00$10,000
67Signal support foundation (632E64010)EACH6$8,500.00$11,000
68Pedestal foundation (632E64020)EACH18$1,300.00$1,350.00
69Pedestal foundation, as per plan (632E64021)EACH1$1,750.00$3,000.00
70Test hole performed (632E64950)EACH6$350.00$2,750.00
71Loop detector lead-in cable, 2 conductor, no. 14 AWG (632E65300)FT500$2.00$2.00
72Power cable, 3 conductor, no. 6 AWG (632E68300)FT445$7.50$5.00
73Power cable, 4 conductor, no. 6 AWG (632E68400)FT200$9.50$6.00
74Service cable, 3 conductor, no. 6 AWG (632E69800)FT619$8.00$5.00
75Service cable, 3 conductor, with ground, no. 4 AWG (632E69910)FT100$12.00$10.00
76Power service, as per plan (632E70001)EACH6$1,900.00$3,500.00
77Conduit riser, 2" diameter (632E70400)EACH2$500.00$1,250.00
78Signal support, type TC-12.31 design 10 pole, with mast arms TC-81.22 design 14 and design 12 (632E71388)EACH1$30,550$31,000
79Signal support, type TC-81.22, design 13, as per plan (632E72141)EACH2$21,500$22,000
80Signal support, misc.: signal supp TC-12.31 design (632E80700)EACH1$36,900$39,000
81Signal support, misc.: signal supp TC-12.31 design (632E80700)EACH1$42,850$44,000
82Combination signal support, misc.:combination sign (632E81700)EACH1$31,850$33,000
83Strain pole, type TC-81.11, design 12, as per plan (632E86141)EACH4$13,300$12,500
84Strain pole, type TC-81.11, design 12, as per plan (632E86141)EACH4$13,050$13,000
85Wood pole, as per plan (632E89301)EACH2$1,600.00$2,500.00
86Down guy (632E89400)EACH2$435.00$1,000.00
87Pedestal, 8', transformer base (632E89900)EACH10$890.00$1,000.00
88Pedestal, 11', transformer base (632E90000)EACH2$1,675.00$1,800.00
89Pedestal, 11', transformer base, as per plan (632E90001)EACH4$1,725.00$1,800.00
90Removal of miscellaneous traffic signal item: var (632E90020)EACH5$500.00$350.00
91Removal of traffic signal installation (632E90100)EACH5$3,350.00$10,000
92Reuse of traffic control item: fiber optic termin (632E90104)EACH2$1,000.00$275.00
93Reuse of traffic control item: modem (632E90104)EACH1$700.00$1,200.00
94Reuse of traffic control item: network switch (632E90104)EACH2$900.00$1,000.00
95Reuse of traffic control item: pre-emption phase (632E90104)EACH2$175.00$250.00
96Reuse of traffic control item: pre-emption receiv (632E90104)EACH2$600.00$275.00
97Reuse of traffic control item: various signal com (632E90104)EACH5$600.00$800.00
98Signalization, misc.: spanwire adjustment (632E90400)EACH5$575.00$2,500.00
99Signalization, misc.: removal of loop detector CA (632E90500)FT7,716$1.00$0.75
100Signalization, misc.: unlash and relash messenger (632E90500)FT300$5.00$10.50
101Cabinet, type 332, as per plan (633E65521)EACH5$19,150$18,000
102Cabinet foundation (633E67100)EACH5$2,900.00$5,000.00
103Controller work pad (633E67200)EACH5$650.00$1,500.00
104Uninterruptible power supply (UPS), battery replacement (633E67500)EACH117$1,300.00$1,100.00
105Flasher controller (633E71000)EACH1$1,674.00$1,250.00
106Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH5$7,750.00$9,000.00
107Fiber optic cable, 24 fiber (804E15010)FT432$3.00$8.00
108Drop cable, 24 fiber (804E32012)EACH2$750.00$1,750.00
109Splice enclosure, butt style (804E37000)EACH2$1,500.00$2,325.00
110CCTV IP-camera system, dome-type (809E60000)EACH5$6,350.00$8,000.00
111Ethernet cable, outdoor-rated (809E64550)FT643$3.00$12.00
112Advance radar detection, as per plan (809E69001)EACH14$9,900.00$8,600.00
113Stop line radar detection, as per plan (809E69101)EACH18$9,600.00$8,200.00
114Atc controller, as per plan (809E69123)EACH5$1,100.00$625.00
115Preempt detector cable (809E69220)FT132$3.50$6.00
116Preempt confirmation light, as per plan (809E69241)EACH2$725.00$600.00
117Law enforcement officer with patrol car for assistance (614E11110)HR40$75.00$100.00
118Maintaining traffic, misc.: maintaining traffic P (614E18000)EACH6$3,000.00$3,500.00
119Maintaining traffic, misc.: maintaining traffic P (614E18000)EACH86$170.00$500.00
120Premium for contract performance bond and for payment bond (103E05000)LS1$8,500.00$9,000.00
121Construction layout stakes and surveying, as per plan (623E10001)LS1$17,700$10,000
122Mobilization (624E10000)LS1$40,000$40,000
ODOT contract 250216: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy