ODOT contract 250221 bid tabulation

MUS-US 40-08.35 (SIGNALIZATION). Let by Ohio DOT on April 24, 2025, MUS. 3 bids received; low bid $269,000 by Miller Cable Company, -8.8% against the engineer's estimate of $295,000.

Owner
Ohio DOT
Letting
24 APR 2025
Pay items
48
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Miller Cable Company$269,000Low-9.0%
2Perram Electric Inc$269,5440.0%-9.0%
3Complete General Construction Company$291,318+8.0%-1.0%
ODOT contract 250221: bids by rank

Engineer's estimate: $295,000.

Bid tabulation

LinePay itemUnitQuantity1. Miller Cable Company2. Perram Electric Inc3. Complete General Construction Company
1Preconstruction survey monument verification and report (623E50000)LS1$1,900.00$1,170.00$1,500.00
2Post construction survey monument verification and report (623E51000)LS1$1,450.00$1,380.00$1,500.00
3Erosion control (832E30000)EACH3,000$1.00$1.00$1.00
4Ground mounted support, no. 3 post, as per plan (630E03101)FT168$20.00$29.85$20.00
5Sign support assembly, pole mounted (630E79500)EACH4$240.00$160.00$240.00
6Sign, flat sheet (630E80100)SF115.20$25.00$25.55$25.00
7Removal of ground mounted sign and disposal (630E84900)EACH13$15.00$30.60$15.00
8Removal of ground mounted post support and disposal (630E86002)EACH12$20.00$33.15$20.00
9Stop line (644E00500)FT79$15.00$12.50$12.50
10Removal of pavement marking (644E30000)FT30$35.00$27.00$27.00
11Connection, fused pull apart (625E00450)EACH4$100.00$158.00$140.00
12Connection, unfused pull apart (625E00460)EACH4$100.00$153.00$135.00
13Bracket arm, 20' (625E18400)EACH1$1,150.00$1,060.00$2,500.00
14Bracket arm, 30' (625E18510)EACH3$1,600.00$1,510.00$3,000.00
15Conduit, 2", 725.04 (625E25400)FT45$21.00$22.25$20.00
16Conduit, 4", 725.051 (625E25604)FT36$18.00$11.68$15.00
17Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH4$550.00$555.00$700.00
18Trench (625E29000)FT72$24.00$13.80$17.50
19Pull box, 725.08, 18" (625E30700)EACH1$1,150.00$1,815.00$1,300.00
20Pull box, 725.08, 24" (625E30706)EACH1$1,400.00$2,015.00$1,500.00
21Ground rod (625E32000)EACH5$265.00$325.00$300.00
22Underground warning marking tape (625E36010)FT72$3.00$4.00$1.50
23Arc flash calculations and label, (controller) (625E76000)EACH1$3,500.00$1,500.00$4,000.00
24Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007)EACH10$1,200.00$885.00$1,200.00
25Covering of vehicular signal head (632E25000)EACH10$40.00$10.00$37.50
26Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200)FT347$20.00$13.55$20.00
27Tether wire, with accessories (632E30600)FT347$20.00$16.55$25.00
28Signal cable, 7 conductor, no. 14 AWG (632E40700)FT1,106$3.25$3.60$3.60
29Strain pole foundation (632E64000)EACH4$7,600.00$7,045.00$9,000.00
30Test hole performed (632E64950)EACH5$90.00$400.00$2,000.00
31Power cable, 3 conductor, no. 8 AWG (632E67300)FT754$6.50$6.35$4.50
32Service cable, 3 conductor, no. 8 AWG (632E69700)FT175$7.50$6.15$5.50
33Power service, as per plan (632E70001)EACH1$5,700.00$8,275.00$3,000.00
34Combination strain pole, type TC-81.11, design 10 (632E87130)EACH2$11,750$11,490$12,000
35Combination strain pole, type TC-81.11, design 12 (632E87140)EACH2$11,600$11,375$14,000
36Cabinet, type 332, as per plan (633E65521)EACH1$17,750$16,480$20,000
37Cabinet foundation, as per plan (633E67101)EACH1$3,100.00$3,470.00$5,000.00
38Controller work pad, as per plan (633E67201)EACH1$850.00$3,190.00$2,600.00
39Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH1$7,900.00$7,845.00$9,000.00
40Advance radar detection, as per plan (809E69001)EACH3$9,800.00$9,345.00$9,250.00
41Stop line radar detection, as per plan (809E69101)EACH2$9,500.00$8,745.00$9,000.00
42Atc controller, as per plan (809E69123)EACH1$1,000.00$350.00$1,000.00
43Law enforcement officer with patrol car for assistance (614E11110)HR50$75.00$100.00$90.00
44Portable changeable message sign, as per plan (614E18601)SNMT6$900.00$1,800.00$1,200.00
45Premium for contract performance bond and for payment bond (103E05000)LS1$2,300.00$5,270.00$1,500.00
46Maintaining traffic (614E11000)LS1$8,500.00$10,275$4,500.00
47Construction layout stakes and surveying, as per plan (623E10001)LS1$4,630.00$2,460.00$1,000.00
48Mobilization (624E10000)LS1$10,000$10,000$10,000
ODOT contract 250221: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy