ODOT contract 250221 bid tabulation
MUS-US 40-08.35 (SIGNALIZATION). Let by Ohio DOT on April 24, 2025, MUS. 3 bids received; low bid $269,000 by Miller Cable Company, -8.8% against the engineer's estimate of $295,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 48
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Miller Cable Company | $269,000 | Low | -9.0% |
| 2 | Perram Electric Inc | $269,544 | 0.0% | -9.0% |
| 3 | Complete General Construction Company | $291,318 | +8.0% | -1.0% |
Engineer's estimate: $295,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller Cable Company | 2. Perram Electric Inc | 3. Complete General Construction Company |
|---|---|---|---|---|---|---|
| 1 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,900.00 | $1,170.00 | $1,500.00 |
| 2 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,450.00 | $1,380.00 | $1,500.00 |
| 3 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 |
| 4 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 168 | $20.00 | $29.85 | $20.00 |
| 5 | Sign support assembly, pole mounted (630E79500) | EACH | 4 | $240.00 | $160.00 | $240.00 |
| 6 | Sign, flat sheet (630E80100) | SF | 115.20 | $25.00 | $25.55 | $25.00 |
| 7 | Removal of ground mounted sign and disposal (630E84900) | EACH | 13 | $15.00 | $30.60 | $15.00 |
| 8 | Removal of ground mounted post support and disposal (630E86002) | EACH | 12 | $20.00 | $33.15 | $20.00 |
| 9 | Stop line (644E00500) | FT | 79 | $15.00 | $12.50 | $12.50 |
| 10 | Removal of pavement marking (644E30000) | FT | 30 | $35.00 | $27.00 | $27.00 |
| 11 | Connection, fused pull apart (625E00450) | EACH | 4 | $100.00 | $158.00 | $140.00 |
| 12 | Connection, unfused pull apart (625E00460) | EACH | 4 | $100.00 | $153.00 | $135.00 |
| 13 | Bracket arm, 20' (625E18400) | EACH | 1 | $1,150.00 | $1,060.00 | $2,500.00 |
| 14 | Bracket arm, 30' (625E18510) | EACH | 3 | $1,600.00 | $1,510.00 | $3,000.00 |
| 15 | Conduit, 2", 725.04 (625E25400) | FT | 45 | $21.00 | $22.25 | $20.00 |
| 16 | Conduit, 4", 725.051 (625E25604) | FT | 36 | $18.00 | $11.68 | $15.00 |
| 17 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 4 | $550.00 | $555.00 | $700.00 |
| 18 | Trench (625E29000) | FT | 72 | $24.00 | $13.80 | $17.50 |
| 19 | Pull box, 725.08, 18" (625E30700) | EACH | 1 | $1,150.00 | $1,815.00 | $1,300.00 |
| 20 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,400.00 | $2,015.00 | $1,500.00 |
| 21 | Ground rod (625E32000) | EACH | 5 | $265.00 | $325.00 | $300.00 |
| 22 | Underground warning marking tape (625E36010) | FT | 72 | $3.00 | $4.00 | $1.50 |
| 23 | Arc flash calculations and label, (controller) (625E76000) | EACH | 1 | $3,500.00 | $1,500.00 | $4,000.00 |
| 24 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 10 | $1,200.00 | $885.00 | $1,200.00 |
| 25 | Covering of vehicular signal head (632E25000) | EACH | 10 | $40.00 | $10.00 | $37.50 |
| 26 | Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200) | FT | 347 | $20.00 | $13.55 | $20.00 |
| 27 | Tether wire, with accessories (632E30600) | FT | 347 | $20.00 | $16.55 | $25.00 |
| 28 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 1,106 | $3.25 | $3.60 | $3.60 |
| 29 | Strain pole foundation (632E64000) | EACH | 4 | $7,600.00 | $7,045.00 | $9,000.00 |
| 30 | Test hole performed (632E64950) | EACH | 5 | $90.00 | $400.00 | $2,000.00 |
| 31 | Power cable, 3 conductor, no. 8 AWG (632E67300) | FT | 754 | $6.50 | $6.35 | $4.50 |
| 32 | Service cable, 3 conductor, no. 8 AWG (632E69700) | FT | 175 | $7.50 | $6.15 | $5.50 |
| 33 | Power service, as per plan (632E70001) | EACH | 1 | $5,700.00 | $8,275.00 | $3,000.00 |
| 34 | Combination strain pole, type TC-81.11, design 10 (632E87130) | EACH | 2 | $11,750 | $11,490 | $12,000 |
| 35 | Combination strain pole, type TC-81.11, design 12 (632E87140) | EACH | 2 | $11,600 | $11,375 | $14,000 |
| 36 | Cabinet, type 332, as per plan (633E65521) | EACH | 1 | $17,750 | $16,480 | $20,000 |
| 37 | Cabinet foundation, as per plan (633E67101) | EACH | 1 | $3,100.00 | $3,470.00 | $5,000.00 |
| 38 | Controller work pad, as per plan (633E67201) | EACH | 1 | $850.00 | $3,190.00 | $2,600.00 |
| 39 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 1 | $7,900.00 | $7,845.00 | $9,000.00 |
| 40 | Advance radar detection, as per plan (809E69001) | EACH | 3 | $9,800.00 | $9,345.00 | $9,250.00 |
| 41 | Stop line radar detection, as per plan (809E69101) | EACH | 2 | $9,500.00 | $8,745.00 | $9,000.00 |
| 42 | Atc controller, as per plan (809E69123) | EACH | 1 | $1,000.00 | $350.00 | $1,000.00 |
| 43 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $75.00 | $100.00 | $90.00 |
| 44 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $900.00 | $1,800.00 | $1,200.00 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,300.00 | $5,270.00 | $1,500.00 |
| 46 | Maintaining traffic (614E11000) | LS | 1 | $8,500.00 | $10,275 | $4,500.00 |
| 47 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $4,630.00 | $2,460.00 | $1,000.00 |
| 48 | Mobilization (624E10000) | LS | 1 | $10,000 | $10,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.