ODOT contract 250223 bid tabulation

OTT-SR 2-17.69 Slope Stab. (SLIDE REPAIR). Let by Ohio DOT on April 24, 2025, OTT. 3 bids received; low bid $525,237 by Vernon Nagel Inc, -20% against the engineer's estimate of $653,000.

Owner
Ohio DOT
Letting
24 APR 2025
Pay items
66
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Vernon Nagel Inc$525,237Low-20%
2Great Lakes Demolition Company$555,717+6.0%-15%
3Eclipse Co LLC$663,395+26%+2.0%
ODOT contract 250223: bids by rank

Engineer's estimate: $653,000.

Bid tabulation

LinePay itemUnitQuantity1. Vernon Nagel Inc2. Great Lakes Demolition Company3. Eclipse Co LLC
1Clearing and grubbing, as per plan (201E11001)LS1$20,000$6,500.00$1,000.00
2Pavement removed (202E23000)SY60$30.00$90.00$19.50
3Concrete barrier removed, as per plan (202E30701)FT137.50$16.00$20.00$22.75
4Curb removed (202E32000)FT18$10.00$10.00$24.50
5Pipe removed, 24" and under (202E35100)FT60$5.00$25.00$27.75
6Guardrail removed (202E38000)FT325$4.00$4.00$2.50
7Guardrail removed for reuse (202E38200)FT570$4.00$4.00$3.25
8Anchor assembly removed for reuse (202E42806)EACH1$350.00$350.00$125.00
9Bridge terminal assembly removed for reuse (202E47200)EACH2$350.00$350.00$100.00
10Impact attenuator removed, as per plan (202E47801)EACH1$1,000.00$1,500.00$525.00
11Catch basin removed (202E58100)EACH1$250.00$450.00$441.00
12Removal misc.:, traffic drums (202E98000)LS1$250.00$4,500.00$210.25
13Removal misc.:, underdrain (202E98200)FT380$18.00$15.00$8.50
14Excavation (203E10000)CY3,290$18.00$6.00$17.25
15Embankment, as per plan (203E20001)CY3,290$12.00$6.00$17.25
16Granular material, type B (203E35110)CY165$55.00$50.00$68.50
17Granular material, type D (203E35130)CY438$65.00$55.00$76.50
18Borrow, as per plan (203E40001)CY402$15.00$25.00$15.75
19Subgrade compaction (204E10000)SY606$1.00$3.00$0.75
20Excavation of subgrade (204E13000)CY202$24.00$15.00$37.50
21Granular material, type C (204E30020)CY202$85.00$50.00$75.25
22Geotextile fabric (204E50000)SY606$1.75$4.00$4.50
23Guardrail, type MGS (606E15050)FT325$31.00$31.00$23.25
24Guardrail rebuilt, type MGS (606E16050)FT570$15.75$16.00$15.25
25Anchor assembly rebuilt, MGS type T (606E27910)EACH1$875.00$875.00$1,260.00
26MGS bridge terminal assembly rebuilt, type 1 (606E35012)EACH1$1,250.00$1,250.00$2,340.00
27MGS bridge terminal assembly rebuilt, type 2 (606E35112)EACH1$675.00$675.00$520.00
28Tied concrete block mat with type 2 underlayment (601E21060)SY617$60.00$61.00$99.00
29Rock channel protection, type C with geotextile fabric (601E32204)CY7$185.00$200.00$217.00
30Topsoil (659E00300)CY462$30.00$50.00$73.50
31Seeding and mulching, class 3B (659E00530)SY4,129$2.25$3.00$2.00
32Repair seeding and mulching (659E14000)SY214$1.20$1.00$1.00
33Commercial fertilizer (659E20000)TON0.61$850.00$800.00$1,113.75
34Water (659E35000)MGAL22$1.00$20.00$1.00
35Erosion control mat, type F (671E15050)SY3,650$1.90$6.00$2.00
36Erosion control (832E30000)EACH40,000$1.00$1.00$1.00
37Concrete masonry (602E20000)CY0.21$5,000.00$3,500.00$4,153.52
3812" conduit, type F (611E05200)FT65$105.00$150.00$102.75
39Catch basin, no. 6 (611E98370)EACH1$4,600.00$3,250.00$4,961.25
40Full depth pavement sawing (252E01500)FT394$2.00$4.00$2.25
41Asphalt concrete base, PG64-22, (449) (301E56000)CY70$310.00$320.00$310.00
42Aggregate base (304E20000)CY91$75.00$55.00$78.25
43Tack coat (407E10000)GAL82$5.00$4.00$5.00
44Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100)CY35$350.00$420.00$350.00
45Combination curb and gutter, type 4 (609E23000)FT846$35.00$25.00$41.00
46Combination curb and gutter, type 4, as per plan (609E23001)FT45$35.00$25.00$50.00
47Longitudinal joint adhesive (875E10000)LB193$1.00$4.00$6.00
48Edge line, 6", type 1 (642E00104)MI0.10$1,000.00$1,000.00$1,500.00
49Lane line, 6", type 1 (642E00204)MI1.07$500.00$500.00$1,500.00
50Dotted line, 6", type 1 (642E01510)FT550$0.50$0.50$1.00
51Law enforcement officer with patrol car for assistance (614E11110)HR16$80.00$150.00$75.00
52Increased barrier delineation (614E11630)FT1,938$1.00$5.00$2.75
53Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH2$2,750.00$2,750.00$1,767.25
54Replacement sign (614E12500)EACH3$192.00$192.00$149.75
55Replacement drum (614E12600)EACH6$56.00$56.00$55.25
56Barrier reflector, type 1, one-way (614E13310)EACH39$8.00$8.00$12.50
57Object marker, one way (614E13350)EACH39$18.00$18.00$19.75
58Portable changeable message sign, as per plan (614E18601)SNMT6$900.00$900.00$1,075.50
59Work zone edge line, class I, 6" (614E22010)MI1$1,000.00$1,000.00$2,500.00
60Work zone dotted line, class I (614E24000)FT2,594$0.50$0.50$0.50
61Water (616E10000)MGAL130$1.00$20.00$29.25
62Portable barrier, unanchored (622E41100)FT1,938$15.00$30.00$42.50
63Premium for contract performance bond and for payment bond (103E05000)LS1$7,500.00$7,000.00$8,620.50
64Maintaining traffic (614E11000)LS1$18,000$18,650$29,083
65Construction layout stakes and surveying (623E10000)LS1$6,000.00$8,500.00$13,589
66Mobilization (624E10000)LS1$25,000$60,000$29,500
ODOT contract 250223: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy