ODOT contract 250244 bid tabulation

D03-TSG FY2025(B) (SIGNALIZATION). Let by Ohio DOT on May 8, 2025, District 3. 3 bids received; low bid $1,247,324 by Cornerstone Electric Inc, -11% against the engineer's estimate of $1,408,000.

Owner
Ohio DOT
Letting
08 MAY 2025
Pay items
100
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Cornerstone Electric Inc$1,247,324Low-11%
2Perram Electric Inc$1,251,2220.0%-11%
3Miller Cable Company$1,326,265+6.0%-6.0%
ODOT contract 250244: bids by rank

Engineer's estimate: $1,408,000.

Bid tabulation

LinePay itemUnitQuantity1. Cornerstone Electric Inc2. Perram Electric Inc3. Miller Cable Company
1Walk removed (202E30000)SF1,126$3.50$8.75$8.75
2Curb removed (202E32000)FT257$17.50$20.00$20.00
3Embankment (203E20000)CY8$500.00$150.00$150.00
4Embankment, as per plan (203E20001)CY1$2,200.00$300.00$300.00
5Aggregate base (304E20000)CY3$800.00$200.00$200.00
6Asphalt concrete surface course, 9.5 MM, type A (4 (442E10501)CY3$4,150.00$895.00$7,000.00
7Concrete masonry (602E20000)CY1$3,150.00$3,800.00$3,800.00
84" concrete walk (608E10000)SF428$16.25$18.00$18.00
9Curb ramp (608E52000)SF1,221$19.25$18.00$18.00
10Combination curb and gutter, type 2 (609E12000)FT21$130.75$54.00$54.00
11Curb, type 6 (609E26000)FT153$42.50$49.00$49.00
12Curb, type 7 (609E28000)FT126$50.75$54.00$54.00
134" concrete traffic island (609E50000)SY67$220.50$111.00$111.00
14Preconstruction survey monument verification and report (623E50000)LS1$4,000.00$2,400.00$2,840.00
15Post construction survey monument verification and report (623E51000)LS1$4,000.00$2,400.00$2,840.00
16Erosion control (832E30000)EACH2,000$1.00$1.00$1.00
174" conduit, type E (611E00400)FT320$5.00$8.45$4.00
1812" conduit, type D (611E04900)FT16$108.00$75.00$78.00
19Connection, fused pull apart (625E00450)EACH22$150.00$165.00$110.00
20Connection, unfused pull apart (625E00460)EACH51$150.00$155.05$110.00
21Light pole, conventional, AT8B30 (625E10490)EACH1$3,000.00$2,890.00$3,000.00
22Light pole, conventional, ATON14 (post top) (625E10490)EACH1$2,000.00$1,985.00$2,100.00
23Light pole foundation, 24" X 6' deep (625E14000)EACH4$1,800.00$1,540.00$1,650.00
24Bracket arm, 10' (625E18000)EACH2$1,200.00$1,015.00$625.00
25Bracket arm, 12' (625E18100)EACH1$1,250.00$1,060.00$675.00
26Bracket arm, 15' (625E18200)EACH2$1,500.00$1,155.00$950.00
27Bracket arm, 20' (625E18400)EACH2$1,800.00$1,550.00$1,150.00
28No. 4 AWG 2400 volt distribution cable (625E23200)FT3,798$3.00$3.31$3.90
29No. 10 AWG pole and bracket cable (625E23400)FT1,335$1.50$1.23$1.50
30Luminaire, conventional, solid state (LED), ies-II (625E26252)EACH9$450.00$460.00$450.00
31Luminaire, post top, solid state (LED), as per plan (625E27403)EACH2$1,650.00$1,340.00$1,050.00
32Glare shield (625E28000)EACH1$100.00$270.00$125.00
33Light pole, decorative (625E10480)EACH1$4,200.00$3,860.00$4,050.00
34Light pole, decorative (625E10480)EACH1$3,000.00$2,875.00$3,200.00
37Sign support assembly, pole mounted (630E79500)EACH22$86.00$18.00$86.00
38Sign, flat sheet (630E80100)SF22$45.00$110.00$45.00
39Removal of ground mounted sign and reerection (630E85100)EACH1$87.00$395.00$87.00
40Stop line, type 1 (642E00500)FT34$10.65$10.65$10.65
41Crosswalk line, 12", type 1 (642E00620)FT561$4.00$4.00$4.00
42Removal of pavement marking (642E30000)FT668$4.85$4.85$4.85
43Conduit, 2", 725.04 (625E25400)FT133$15.00$19.20$18.00
44Conduit, 3", 725.04 (625E25500)FT181$20.00$34.50$28.00
45Conduit, 4", 725.04 (625E25600)FT88$50.00$50.25$48.00
46Conduit, jacked or drilled, 725.04, 2" (625E25902)FT264$50.00$42.25$37.00
47Conduit, jacked or drilled, 725.04, 3" (625E25902)FT166$60.00$54.20$48.00
48Conduit, jacked or drilled, 725.04, 4" (625E25902)FT321$75.00$91.45$70.00
49Trench (625E29000)FT391$10.00$13.65$12.00
50Pull box, 725.08, 18" (625E30700)EACH4$1,250.00$1,300.00$995.00
51Pull box, 725.08, 24" (625E30706)EACH13$1,500.00$1,500.00$1,250.00
52Ground rod (625E32000)EACH26$200.00$323.00$265.00
53Underground warning marking tape (625E36010)FT391$1.50$1.75$3.00
54Special - maintain existing lighting (625E40000)LS1$1,000.00$100.00$15,500
55Arc flash calculations and label , power service (625E76000)EACH4$500.00$1,500.00$3,450.00
56Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007)EACH32$900.00$940.00$1,375.00
57Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate, as per plan (632E05087)EACH2$1,600.00$1,760.00$2,225.00
58Pedestrian signal head (LED), type D2, countdown (632E20730)EACH22$650.00$580.00$785.00
59Accessible pedestrian pushbutton (632E20750)EACH22$800.00$821.00$875.00
60Covering of vehicular signal head (632E25000)EACH34$10.00$10.00$40.00
61Covering of pedestrian signal head (632E25010)EACH22$10.00$5.00$30.00
62Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200)FT342$15.00$15.15$20.00
63Messenger wire, misc.: unlash and relash (632E30500)FT100$6.00$9.90$4.25
64Tether wire, with accessories (632E30600)FT342$15.00$18.10$20.00
65Signal cable, 2 conductor, no. 14 AWG (632E40200)FT2,970$2.50$2.58$1.80
66Signal cable, 5 conductor, no. 14 AWG (632E40500)FT4,329$3.00$2.89$2.70
67Signal cable, 7 conductor, no. 14 AWG (632E40700)FT2,016$3.25$3.15$2.90
68Signal support foundation (632E64010)EACH11$8,000.00$7,580.00$7,050.00
69Pedestal foundation (632E64020)EACH20$1,000.00$1,395.00$950.00
70Test hole performed (632E64950)EACH2$1,000.00$395.00$300.00
71Power cable, 3 conductor, no. 6 AWG (632E68300)FT217$6.00$8.70$7.50
72Service cable, 3 conductor, no. 6 AWG (632E69800)FT194$6.00$7.60$8.00
73Power service, as per plan (632E70001)EACH4$2,500.00$3,960.00$2,850.00
74Conduit riser, 2" diameter (632E70400)EACH4$750.00$685.00$625.00
75Combination signal support, type TC-12.31 design 6 pole, with mast arms TC-81.22 design 12 and design 2 (632E78240)EACH1$19,500$19,730$19,800
76Combination signal support, type TC-12.31 design 1 (632E78360)EACH1$27,000$25,575$30,700
77Combination signal support, type TC-12.31 design 1 (632E78364)EACH2$27,500$26,135$30,250
78Combination signal support, type TC-12.31 design 1 (632E78368)EACH1$26,800$26,410$33,700
79Combination signal support, type TC-81.22, design 4 (632E79110)EACH1$11,500$11,545$11,000
80Combination signal support, type TC-81.22, design 13 (632E79140)EACH1$18,000$17,120$19,200
81Strain pole, type TC-81.11, design 10 (632E86130)EACH4$10,500$9,630.00$10,100
82Pedestal, 8', transformer base (632E89900)EACH20$900.00$1,019.00$600.00
83Removal of traffic signal installation (632E90100)EACH4$3,000.00$1,890.00$3,250.00
84Cabinet, type TS-2, as per plan (633E65511)EACH4$16,650$15,860$17,950
85Cabinet foundation (633E67100)EACH4$2,000.00$3,340.00$2,600.00
86Controller work pad (633E67200)EACH4$1,000.00$865.00$850.00
87Uninterruptible power supply (UPS), 1000 watt (633E75000)EACH4$7,500.00$7,192.00$7,075.00
88Controller item, misc.: communications (633E99000)EACH4$2,000.00$1,927.00$2,275.00
89Advance radar detection, as per plan (809E69001)EACH16$8,600.00$8,455.00$9,850.00
90Stop line radar detection, as per plan (809E69101)EACH16$8,400.00$8,420.00$9,550.00
91Atc controller, as per plan (809E69123)EACH4$500.00$550.00$995.00
92Emergency vehicle preemption (809E69200)EACH2$5,500.00$5,135.00$750.00
93Preempt receiving unit (809E69210)EACH8$1,000.00$855.00$1,300.00
94Preempt detector cable (809E69220)FT1,212$2.00$2.40$3.39
95Preempt phase selector (809E69230)EACH2$5,000.00$3,500.00$4,925.00
96Preempt confirmation light (809E69240)EACH8$600.00$930.00$585.00
97Law enforcement officer with patrol car for assistance (614E11110)HR80$70.00$85.00$75.00
98Premium for contract performance bond and for payment bond (103E05000)LS1$11,000$16,523$6,200.00
99Maintaining traffic (614E11000)LS1$20,000$17,375$14,000
100Field office, type B (619E16010)MNTH16$800.00$1,200.00$800.00
101Construction layout stakes and surveying (623E10000)LS1$12,000$8,100.00$17,000
102Mobilization (624E10000)LS1$30,000$40,000$40,000
ODOT contract 250244: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy