ODOT contract 250339 bid tabulation

BEL-SR 149-02.11 (CULVERT REPLACEMENT). Let by Ohio DOT on July 17, 2025, BEL. 7 bids received; low bid $878,695 by Axis Civil Construction LLC.

Owner
Ohio DOT
Letting
17 JUL 2025
Pay items
31
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Axis Civil Construction LLC$878,695Low
2Marucci & Gaffney Excavating Co$941,090+7.0%
3Eclipse Co LLC$1,349,050+54%
4Turn-Key Tunneling Inc$1,397,000+59%
5Stanley Miller Construction Company$1,429,345+63%
6Ohio-West Virginia Excavating Co$1,692,020+93%
7S E T Inc$1,986,263+126%
ODOT contract 250339: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Axis Civil Construction LLC2. Marucci & Gaffney Excavating Co3. Eclipse Co LLC4. Turn-Key Tunneling Inc5. Stanley Miller Construction Company6. Ohio-West Virginia Excavating Co
1Clearing and grubbing, as per plan (201E11001)LS1$25,000$40,000$19,854$43,200$15,000$37,700
2Pipe removed, 24" and under (202E35100)FT6$100.00$10.00$36.50$216.00$25.00$411.00
3Catch basin removed (202E58100)EACH2$1,000.00$10.00$250.50$3,240.00$1,000.00$1,250.00
4Special - fill and plug existing conduit (202E70000)FT24$140.00$50.00$215.00$540.00$150.00$226.00
5Special - pipe cleanout over 48" (202E70130)FT453$35.00$15.00$15.00$17.50$125.00$114.00
6Removal misc.: riprap removed (202E98300)SY107$110.00$20.00$130.00$270.00$185.00$216.00
7Excavation (203E10000)CY19$150.00$50.00$107.50$54.00$150.00$214.00
8Embankment (203E20000)CY16$150.00$50.00$125.00$108.00$200.00$132.00
9Riprap, type D (601E11000)SY110$290.00$180.00$245.00$351.00$265.00$394.00
10Soil analysis test (659E00100)EACH2$150.00$5.00$125.00$27.00$150.00$200.00
11Topsoil (659E00300)CY262$40.00$15.00$94.50$108.00$72.00$132.00
12Seeding and mulching (659E10000)SY2,361$1.50$2.00$2.00$10.80$5.00$2.00
13Repair seeding and mulching (659E14000)SY118$1.50$0.27$2.00$22.00$3.00$2.00
14Commercial fertilizer (659E20000)TON0.32$1,250.00$400.00$891.50$2,592.00$800.00$1,600.00
15Lime (659E31000)ACRE0.49$150.00$10.00$155.51$2,052.00$150.00$200.00
16Water (659E35000)MGAL13$1.00$0.01$1.00$1.08$1.00$1.00
17Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00$1.00$1.00
18Cofferdams and excavation bracing (503E11100)LS1$40,000$76,000$70,727$24,300$65,000$73,000
19Unclassified excavation (503E21300)LS1$15,000$5,000.00$1,721.00$7,020.00$6,000.00$4,100.00
2012" conduit, type C (611E04600)FT11$250.00$200.00$250.50$216.00$50.00$192.00
21Catch basin, no. 2-2B (611E98470)EACH1$4,500.00$3,000.00$5,841.00$5,184.00$5,000.00$5,000.00
25Conduit, with field paving of pipe (96" tunnel lin (611E96560)FT453$150.00$154.52$214.50$240.00$1,411.00$196.00
26Conduit, misc.: (96" tunnel liner plate structure) (611E97400)FT453$990.00$1,013.22$1,515.00$1,480.00$50.00$2,360.00
27Backfill for liner pipe (837E21000)FT453$185.00$386.45$521.50$575.00$717.00$291.00
28Special - work zone guardrail (614E12200)FT75$80.00$10.00$305.00$216.00$75.00$94.00
29Asphalt concrete for maintaining traffic (614E13000)CY10$300.00$50.00$350.00$81.00$150.00$534.00
30Premium for contract performance bond and for payment bond (103E05000)LS1$6,500.00$10,000$14,588$25,324$30,000$20,000
31Maintaining traffic (614E11000)LS1$20,000$14,500$22,555$5,400.00$25,000$16,300
32Field office, type B (619E16010)MNTH5$2,500.00$500.00$890.00$300.00$5,000.00$3,100.00
33Construction layout stakes and surveying (623E10000)LS1$7,500.00$12,000$6,563.00$3,240.00$15,000$2,000.00
34Mobilization (624E10000)LS1$40,000$20,000$56,000$55,600$90,000$29,000
ODOT contract 250339: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of July 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy