ODOT contract 250377 bid tabulation

CUY-SRTS FY2023 Warrensville Hts (SPOT SAFETY). Let by Ohio DOT on August 14, 2025, CUY. 6 bids received; low bid $625,585 by Catts Construction Inc, -15% against the engineer's estimate of $732,000.

Owner
Ohio DOT
Letting
14 AUG 2025
Pay items
84
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Catts Construction Inc$625,585Low-15%
2C A Agresta Construction Co$667,731+7.0%-9.0%
3Smith Paving & Excavating Inc$671,246+7.0%-8.0%
4Perk Company Inc$676,345+8.0%-8.0%
5Tri-Mor Corp$758,161+21%+4.0%
6Madex Construction Co$1,086,782+74%+48%
ODOT contract 250377: bids by rank

Engineer's estimate: $732,000.

Bid tabulation

LinePay itemUnitQuantity1. Catts Construction Inc2. C A Agresta Construction Co3. Smith Paving & Excavating Inc4. Perk Company Inc5. Tri-Mor Corp6. Madex Construction Co
1Pavement removed (202E23000)SY79$23.00$25.00$48.00$32.50$30.00$173.68
2Walk removed, as per plan (202E30001)SF4,252$1.50$2.00$5.30$4.45$3.00$7.11
3Curb removed, as per plan (202E32001)FT479$14.75$10.00$15.00$14.85$20.00$30.11
4Removal misc.: brick pavers removed (202E98400)SF32$12.00$10.00$30.00$16.50$10.00$57.89
5Subgrade compaction (204E10000)SY40$3.00$2.00$2.00$1.50$5.00$11.58
6Sealing of concrete surfaces, as per plan (512E10001)SY1,824$1.00$3.00$12.00$9.60$6.00$34.74
74" concrete walk, as per plan (608E10001)SF11,749$10.80$11.00$10.25$13.00$14.00$24.95
88" concrete walk, as per plan (608E15001)SF502$16.00$14.00$13.60$15.00$15.00$32.45
9Curb ramp, as per plan (608E52001)SF3,541$25.00$23.00$14.10$23.00$30.00$44.00
10Topsoil (659E00300)CY13$178.00$100.00$80.00$250.00$100.00$115.79
11Seeding and mulching, class 1 (659E00500)SY49$15.00$10.00$10.00$27.50$25.00$23.16
12Erosion control (832E30000)EACH2,500$1.00$1.00$1.00$1.00$1.00$1.00
136" unclassified pipe underdrains, as per plan (605E13301)FT448$7.00$15.00$21.50$4.00$25.00$33.58
146" conduit, type F for underdrain outlets (611E00510)FT10$15.00$20.00$21.50$4.00$25.00$57.89
15Aggregate base, as per plan (304E20001)CY7$135.00$100.00$85.00$190.00$125.00$463.16
16Non-tracking tack coat (407E20000)GAL4$9.00$20.00$50.00$5.00$35.00$70.53
17Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY4$860.00$1,000.00$500.00$1,235.00$900.00$4,052.63
18Asphalt concrete intermediate course, type 2, (449) (441E70300)CY4$850.00$1,000.00$500.00$1,070.00$850.00$4,052.63
19Reinforced concrete pavement, misc.: 8" class QC M (451E20000)SY40$120.00$140.00$130.00$135.00$150.00$468.99
20Curb, type 2-A, as per plan (609E14001)FT56$45.00$65.00$42.00$70.00$75.00$104.21
21Curb, type 2-B, as per plan (609E16001)FT30$45.00$65.00$43.00$70.00$75.00$115.79
22Curb, type 7, as per plan (609E28001)FT357$67.00$65.00$52.00$70.00$45.00$57.89
23Valve box adjusted to grade (638E10800)EACH1$125.00$500.00$500.00$1,500.00$1,000.00$1,112.63
24Water work, misc.: manhole adjusted to grade, as P (638E98000)EACH1$1,900.00$1,000.00$1,000.00$2,585.00$2,500.00$5,396.84
25Ground rod (625E32000)EACH2$367.00$265.00$265.00$350.00$400.00$402.50
26Ground mounted support, no. 2 post (630E02100)FT65.10$14.00$8.00$8.00$12.00$15.00$13.80
27Ground mounted support, no. 3 post (630E03100)FT26.20$16.00$10.00$10.00$14.00$20.00$16.10
28Ground mounted support, no. 4 post, as per plan (630E04101)FT15.50$19.00$12.00$12.00$16.00$18.00$18.40
29Street name sign support, no. 3 post (630E08520)FT12.10$18.00$12.00$12.00$15.00$20.00$17.25
30Sign support assembly, pole mounted (630E79500)EACH3$101.00$80.00$80.00$85.00$95.00$97.75
31Sign, flat sheet (630E80100)SF69.70$21.00$19.00$19.00$18.00$20.00$20.70
32Removal of ground mounted sign and disposal (630E84900)EACH9$18.00$25.00$25.00$15.00$17.00$17.25
33Removal of ground mounted sign and reerection (630E85100)EACH2$102.00$75.00$75.00$85.00$94.00$97.75
34Removal of ground mounted post support and disposal (630E86002)EACH9$24.00$25.00$25.00$20.00$23.00$23.00
35Removal of pole mounted sign and disposal (630E87500)EACH31$17.00$25.00$25.00$15.00$17.00$17.25
36Signing, misc.: radar speed sign (630E97700)EACH2$10,545$4,600.00$4,600.00$9,000.00$5,400.00$5,629.25
37Signing, misc.: rectangular rapid flashing becaon (630E97700)EACH2$8,226.00$7,400.00$7,400.00$7,020.00$9,400.00$9,775.00
38Pedestal foundation (632E64020)EACH2$1,600.00$1,350.00$1,350.00$1,300.00$1,250.00$1,265.00
39Stop line (644E00500)FT37$9.50$6.00$6.00$8.00$8.00$9.20
40Crosswalk line, 12", as per plan (644E00621)FT847$4.80$3.95$3.95$4.00$7.00$4.60
41Crosswalk line, 24", as per plan (644E00631)FT574$9.50$6.00$6.00$8.00$7.00$9.20
42Removal of pavement marking (644E30000)FT892$6.00$4.50$4.50$5.00$3.00$5.75
43Stop line (646E10400)FT255$13.00$12.00$12.00$11.00$14.00$12.65
44Crosswalk line, 12", as per plan (646E10511)FT1,583$5.00$10.00$10.00$4.50$9.00$5.18
45Crosswalk line, 24", as per plan (646E10521)FT1,045$10.00$12.50$12.50$8.50$11.00$9.78
46Lane arrow (646E20300)EACH3$198.00$185.00$185.00$165.00$200.00$189.75
47Yield line (646E20800)FT26$14.00$10.00$10.00$12.00$17.00$13.80
48Removal of pavement marking (646E50000)EACH3$240.00$100.00$100.00$200.00$710.00$230.00
49Removal of pavement marking (646E50100)FT2,133$6.00$4.50$4.50$5.00$4.00$5.75
50Conduit, 2", 725.04 (625E25400)FT225$26.00$20.00$20.00$21.15$17.00$17.25
51Conduit, 3", 725.04 (625E25500)FT27$36.00$32.00$32.00$29.60$35.00$36.80
52Conduit, 4", 725.04 (625E25600)FT32$48.00$50.00$50.00$39.70$42.00$43.70
53Conduit, jacked or drilled, 725.04, 4" (625E25902)FT93$149.00$75.00$75.00$120.65$140.00$143.75
54Trench (625E29000)FT277$11.00$15.00$15.00$9.65$14.00$13.80
55Pull box, 725.08, 18" (625E30700)EACH2$1,353.00$1,150.00$1,150.00$1,100.00$1,100.00$1,092.50
56Pull box, misc.: pull box adjusted to grade (625E31600)EACH8$430.00$250.00$250.00$350.00$450.00$977.50
57Pull box, misc.: skid resistant cover (625E31600)EACH2$1,414.00$1,100.00$1,100.00$1,150.00$720.00$460.00
58Ground rod (625E32000)EACH18$368.00$265.00$265.00$300.00$275.00$287.50
59Underground warning marking tape (625E36010)FT277$2.50$2.00$2.00$2.00$3.50$3.45
60Arc flash calculations and label, traffic signal C (625E76000)EACH1$615.00$3,450.00$3,450.00$500.00$2,000.00$2,070.00
61Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH32$647.00$825.00$825.00$555.00$680.00$707.25
62Covering of pedestrian signal head (632E25010)EACH32$48.00$40.00$40.00$39.00$56.00$57.50
63Pedestrian pushbutton, as per plan (632E26001)EACH32$293.00$265.00$265.00$250.00$440.00$454.25
64Signal cable, 3 conductor, no. 14 AWG (632E40300)FT922$2.75$3.25$3.25$2.25$2.00$1.78
65Signal cable, 5 conductor, no. 14 AWG (632E40500)FT4,700$3.00$3.80$3.80$2.55$2.50$2.59
66Signal cable, 7 conductor, no. 14 AWG (632E40700)FT540$3.75$4.00$4.00$3.00$3.25$3.39
67Pedestal foundation (632E64020)EACH16$1,537.00$1,250.00$1,250.00$1,250.00$1,220.00$1,265.00
68Loop detector lead-in cable (632E65200)FT4,571$2.50$2.50$2.50$2.00$2.00$1.73
69Power service, as per plan (632E70001)EACH1$4,736.00$3,500.00$3,500.00$3,850.00$4,200.00$4,370.00
70Conduit riser, 2" diameter (632E70400)EACH1$369.00$621.00$621.00$300.00$500.00$517.50
71Pedestal, 5', transformer base (632E89802)EACH1$700.00$650.00$650.00$600.00$665.00$690.00
72Pedestal, 8', transformer base (632E89900)EACH15$780.00$750.00$750.00$667.00$1,100.00$1,092.50
73Removal of traffic signal installation, as per plan (632E90101)EACH5$2,025.00$1,250.00$1,250.00$1,650.00$1,700.00$1,725.00
74Signalization, misc.: unlash and relash messenger (632E90500)FT105$7.30$5.00$5.00$6.00$10.00$10.35
75Cabinet, type TS-2, as per plan (633E65511)EACH1$18,636$16,600$16,600$16,000$18,600$19,349
76Cabinet foundation (633E67100)EACH1$1,783.00$2,750.00$2,750.00$1,450.00$4,500.00$4,542.50
77Controller item, misc.: controller modifications (633E99000)EACH4$1,680.00$1,250.00$1,250.00$1,366.00$3,100.00$3,220.00
78Atc controller, as per plan (809E69123)EACH1$6,799.00$5,702.00$5,702.00$5,530.00$6,800.00$7,015.00
79Law enforcement officer with patrol car for assistance (614E11110)HR50$50.00$90.00$95.00$125.00$90.00$115.79
80Premium for contract performance bond and for payment bond (103E05000)LS1$6,860.00$12,000$7,000.00$7,150.00$10,000$25,474
81Maintaining traffic (614E11000)LS1$15,000$63,000$50,000$25,160$45,000$8,646.40
82Construction layout stakes and surveying (623E10000)LS1$7,000.00$8,000.00$10,000$20,150$23,000$23,158
83Mobilization (624E10000)LS1$12,000$21,700$55,000$25,850$18,000$26,869
84Special - pre-construction video (690E98400)LS1$1,550.00$2,000.00$1,500.00$2,000.00$1,600.00$5,789.47
ODOT contract 250377: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy