ODOT contract 250377 bid tabulation
CUY-SRTS FY2023 Warrensville Hts (SPOT SAFETY). Let by Ohio DOT on August 14, 2025, CUY. 6 bids received; low bid $625,585 by Catts Construction Inc, -15% against the engineer's estimate of $732,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 84
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Catts Construction Inc | $625,585 | Low | -15% |
| 2 | C A Agresta Construction Co | $667,731 | +7.0% | -9.0% |
| 3 | Smith Paving & Excavating Inc | $671,246 | +7.0% | -8.0% |
| 4 | Perk Company Inc | $676,345 | +8.0% | -8.0% |
| 5 | Tri-Mor Corp | $758,161 | +21% | +4.0% |
| 6 | Madex Construction Co | $1,086,782 | +74% | +48% |
Engineer's estimate: $732,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Catts Construction Inc | 2. C A Agresta Construction Co | 3. Smith Paving & Excavating Inc | 4. Perk Company Inc | 5. Tri-Mor Corp | 6. Madex Construction Co |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 79 | $23.00 | $25.00 | $48.00 | $32.50 | $30.00 | $173.68 |
| 2 | Walk removed, as per plan (202E30001) | SF | 4,252 | $1.50 | $2.00 | $5.30 | $4.45 | $3.00 | $7.11 |
| 3 | Curb removed, as per plan (202E32001) | FT | 479 | $14.75 | $10.00 | $15.00 | $14.85 | $20.00 | $30.11 |
| 4 | Removal misc.: brick pavers removed (202E98400) | SF | 32 | $12.00 | $10.00 | $30.00 | $16.50 | $10.00 | $57.89 |
| 5 | Subgrade compaction (204E10000) | SY | 40 | $3.00 | $2.00 | $2.00 | $1.50 | $5.00 | $11.58 |
| 6 | Sealing of concrete surfaces, as per plan (512E10001) | SY | 1,824 | $1.00 | $3.00 | $12.00 | $9.60 | $6.00 | $34.74 |
| 7 | 4" concrete walk, as per plan (608E10001) | SF | 11,749 | $10.80 | $11.00 | $10.25 | $13.00 | $14.00 | $24.95 |
| 8 | 8" concrete walk, as per plan (608E15001) | SF | 502 | $16.00 | $14.00 | $13.60 | $15.00 | $15.00 | $32.45 |
| 9 | Curb ramp, as per plan (608E52001) | SF | 3,541 | $25.00 | $23.00 | $14.10 | $23.00 | $30.00 | $44.00 |
| 10 | Topsoil (659E00300) | CY | 13 | $178.00 | $100.00 | $80.00 | $250.00 | $100.00 | $115.79 |
| 11 | Seeding and mulching, class 1 (659E00500) | SY | 49 | $15.00 | $10.00 | $10.00 | $27.50 | $25.00 | $23.16 |
| 12 | Erosion control (832E30000) | EACH | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 448 | $7.00 | $15.00 | $21.50 | $4.00 | $25.00 | $33.58 |
| 14 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 10 | $15.00 | $20.00 | $21.50 | $4.00 | $25.00 | $57.89 |
| 15 | Aggregate base, as per plan (304E20001) | CY | 7 | $135.00 | $100.00 | $85.00 | $190.00 | $125.00 | $463.16 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 4 | $9.00 | $20.00 | $50.00 | $5.00 | $35.00 | $70.53 |
| 17 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 4 | $860.00 | $1,000.00 | $500.00 | $1,235.00 | $900.00 | $4,052.63 |
| 18 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 4 | $850.00 | $1,000.00 | $500.00 | $1,070.00 | $850.00 | $4,052.63 |
| 19 | Reinforced concrete pavement, misc.: 8" class QC M (451E20000) | SY | 40 | $120.00 | $140.00 | $130.00 | $135.00 | $150.00 | $468.99 |
| 20 | Curb, type 2-A, as per plan (609E14001) | FT | 56 | $45.00 | $65.00 | $42.00 | $70.00 | $75.00 | $104.21 |
| 21 | Curb, type 2-B, as per plan (609E16001) | FT | 30 | $45.00 | $65.00 | $43.00 | $70.00 | $75.00 | $115.79 |
| 22 | Curb, type 7, as per plan (609E28001) | FT | 357 | $67.00 | $65.00 | $52.00 | $70.00 | $45.00 | $57.89 |
| 23 | Valve box adjusted to grade (638E10800) | EACH | 1 | $125.00 | $500.00 | $500.00 | $1,500.00 | $1,000.00 | $1,112.63 |
| 24 | Water work, misc.: manhole adjusted to grade, as P (638E98000) | EACH | 1 | $1,900.00 | $1,000.00 | $1,000.00 | $2,585.00 | $2,500.00 | $5,396.84 |
| 25 | Ground rod (625E32000) | EACH | 2 | $367.00 | $265.00 | $265.00 | $350.00 | $400.00 | $402.50 |
| 26 | Ground mounted support, no. 2 post (630E02100) | FT | 65.10 | $14.00 | $8.00 | $8.00 | $12.00 | $15.00 | $13.80 |
| 27 | Ground mounted support, no. 3 post (630E03100) | FT | 26.20 | $16.00 | $10.00 | $10.00 | $14.00 | $20.00 | $16.10 |
| 28 | Ground mounted support, no. 4 post, as per plan (630E04101) | FT | 15.50 | $19.00 | $12.00 | $12.00 | $16.00 | $18.00 | $18.40 |
| 29 | Street name sign support, no. 3 post (630E08520) | FT | 12.10 | $18.00 | $12.00 | $12.00 | $15.00 | $20.00 | $17.25 |
| 30 | Sign support assembly, pole mounted (630E79500) | EACH | 3 | $101.00 | $80.00 | $80.00 | $85.00 | $95.00 | $97.75 |
| 31 | Sign, flat sheet (630E80100) | SF | 69.70 | $21.00 | $19.00 | $19.00 | $18.00 | $20.00 | $20.70 |
| 32 | Removal of ground mounted sign and disposal (630E84900) | EACH | 9 | $18.00 | $25.00 | $25.00 | $15.00 | $17.00 | $17.25 |
| 33 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $102.00 | $75.00 | $75.00 | $85.00 | $94.00 | $97.75 |
| 34 | Removal of ground mounted post support and disposal (630E86002) | EACH | 9 | $24.00 | $25.00 | $25.00 | $20.00 | $23.00 | $23.00 |
| 35 | Removal of pole mounted sign and disposal (630E87500) | EACH | 31 | $17.00 | $25.00 | $25.00 | $15.00 | $17.00 | $17.25 |
| 36 | Signing, misc.: radar speed sign (630E97700) | EACH | 2 | $10,545 | $4,600.00 | $4,600.00 | $9,000.00 | $5,400.00 | $5,629.25 |
| 37 | Signing, misc.: rectangular rapid flashing becaon (630E97700) | EACH | 2 | $8,226.00 | $7,400.00 | $7,400.00 | $7,020.00 | $9,400.00 | $9,775.00 |
| 38 | Pedestal foundation (632E64020) | EACH | 2 | $1,600.00 | $1,350.00 | $1,350.00 | $1,300.00 | $1,250.00 | $1,265.00 |
| 39 | Stop line (644E00500) | FT | 37 | $9.50 | $6.00 | $6.00 | $8.00 | $8.00 | $9.20 |
| 40 | Crosswalk line, 12", as per plan (644E00621) | FT | 847 | $4.80 | $3.95 | $3.95 | $4.00 | $7.00 | $4.60 |
| 41 | Crosswalk line, 24", as per plan (644E00631) | FT | 574 | $9.50 | $6.00 | $6.00 | $8.00 | $7.00 | $9.20 |
| 42 | Removal of pavement marking (644E30000) | FT | 892 | $6.00 | $4.50 | $4.50 | $5.00 | $3.00 | $5.75 |
| 43 | Stop line (646E10400) | FT | 255 | $13.00 | $12.00 | $12.00 | $11.00 | $14.00 | $12.65 |
| 44 | Crosswalk line, 12", as per plan (646E10511) | FT | 1,583 | $5.00 | $10.00 | $10.00 | $4.50 | $9.00 | $5.18 |
| 45 | Crosswalk line, 24", as per plan (646E10521) | FT | 1,045 | $10.00 | $12.50 | $12.50 | $8.50 | $11.00 | $9.78 |
| 46 | Lane arrow (646E20300) | EACH | 3 | $198.00 | $185.00 | $185.00 | $165.00 | $200.00 | $189.75 |
| 47 | Yield line (646E20800) | FT | 26 | $14.00 | $10.00 | $10.00 | $12.00 | $17.00 | $13.80 |
| 48 | Removal of pavement marking (646E50000) | EACH | 3 | $240.00 | $100.00 | $100.00 | $200.00 | $710.00 | $230.00 |
| 49 | Removal of pavement marking (646E50100) | FT | 2,133 | $6.00 | $4.50 | $4.50 | $5.00 | $4.00 | $5.75 |
| 50 | Conduit, 2", 725.04 (625E25400) | FT | 225 | $26.00 | $20.00 | $20.00 | $21.15 | $17.00 | $17.25 |
| 51 | Conduit, 3", 725.04 (625E25500) | FT | 27 | $36.00 | $32.00 | $32.00 | $29.60 | $35.00 | $36.80 |
| 52 | Conduit, 4", 725.04 (625E25600) | FT | 32 | $48.00 | $50.00 | $50.00 | $39.70 | $42.00 | $43.70 |
| 53 | Conduit, jacked or drilled, 725.04, 4" (625E25902) | FT | 93 | $149.00 | $75.00 | $75.00 | $120.65 | $140.00 | $143.75 |
| 54 | Trench (625E29000) | FT | 277 | $11.00 | $15.00 | $15.00 | $9.65 | $14.00 | $13.80 |
| 55 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $1,353.00 | $1,150.00 | $1,150.00 | $1,100.00 | $1,100.00 | $1,092.50 |
| 56 | Pull box, misc.: pull box adjusted to grade (625E31600) | EACH | 8 | $430.00 | $250.00 | $250.00 | $350.00 | $450.00 | $977.50 |
| 57 | Pull box, misc.: skid resistant cover (625E31600) | EACH | 2 | $1,414.00 | $1,100.00 | $1,100.00 | $1,150.00 | $720.00 | $460.00 |
| 58 | Ground rod (625E32000) | EACH | 18 | $368.00 | $265.00 | $265.00 | $300.00 | $275.00 | $287.50 |
| 59 | Underground warning marking tape (625E36010) | FT | 277 | $2.50 | $2.00 | $2.00 | $2.00 | $3.50 | $3.45 |
| 60 | Arc flash calculations and label, traffic signal C (625E76000) | EACH | 1 | $615.00 | $3,450.00 | $3,450.00 | $500.00 | $2,000.00 | $2,070.00 |
| 61 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 32 | $647.00 | $825.00 | $825.00 | $555.00 | $680.00 | $707.25 |
| 62 | Covering of pedestrian signal head (632E25010) | EACH | 32 | $48.00 | $40.00 | $40.00 | $39.00 | $56.00 | $57.50 |
| 63 | Pedestrian pushbutton, as per plan (632E26001) | EACH | 32 | $293.00 | $265.00 | $265.00 | $250.00 | $440.00 | $454.25 |
| 64 | Signal cable, 3 conductor, no. 14 AWG (632E40300) | FT | 922 | $2.75 | $3.25 | $3.25 | $2.25 | $2.00 | $1.78 |
| 65 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 4,700 | $3.00 | $3.80 | $3.80 | $2.55 | $2.50 | $2.59 |
| 66 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 540 | $3.75 | $4.00 | $4.00 | $3.00 | $3.25 | $3.39 |
| 67 | Pedestal foundation (632E64020) | EACH | 16 | $1,537.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,220.00 | $1,265.00 |
| 68 | Loop detector lead-in cable (632E65200) | FT | 4,571 | $2.50 | $2.50 | $2.50 | $2.00 | $2.00 | $1.73 |
| 69 | Power service, as per plan (632E70001) | EACH | 1 | $4,736.00 | $3,500.00 | $3,500.00 | $3,850.00 | $4,200.00 | $4,370.00 |
| 70 | Conduit riser, 2" diameter (632E70400) | EACH | 1 | $369.00 | $621.00 | $621.00 | $300.00 | $500.00 | $517.50 |
| 71 | Pedestal, 5', transformer base (632E89802) | EACH | 1 | $700.00 | $650.00 | $650.00 | $600.00 | $665.00 | $690.00 |
| 72 | Pedestal, 8', transformer base (632E89900) | EACH | 15 | $780.00 | $750.00 | $750.00 | $667.00 | $1,100.00 | $1,092.50 |
| 73 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 5 | $2,025.00 | $1,250.00 | $1,250.00 | $1,650.00 | $1,700.00 | $1,725.00 |
| 74 | Signalization, misc.: unlash and relash messenger (632E90500) | FT | 105 | $7.30 | $5.00 | $5.00 | $6.00 | $10.00 | $10.35 |
| 75 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $18,636 | $16,600 | $16,600 | $16,000 | $18,600 | $19,349 |
| 76 | Cabinet foundation (633E67100) | EACH | 1 | $1,783.00 | $2,750.00 | $2,750.00 | $1,450.00 | $4,500.00 | $4,542.50 |
| 77 | Controller item, misc.: controller modifications (633E99000) | EACH | 4 | $1,680.00 | $1,250.00 | $1,250.00 | $1,366.00 | $3,100.00 | $3,220.00 |
| 78 | Atc controller, as per plan (809E69123) | EACH | 1 | $6,799.00 | $5,702.00 | $5,702.00 | $5,530.00 | $6,800.00 | $7,015.00 |
| 79 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $50.00 | $90.00 | $95.00 | $125.00 | $90.00 | $115.79 |
| 80 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,860.00 | $12,000 | $7,000.00 | $7,150.00 | $10,000 | $25,474 |
| 81 | Maintaining traffic (614E11000) | LS | 1 | $15,000 | $63,000 | $50,000 | $25,160 | $45,000 | $8,646.40 |
| 82 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,000.00 | $8,000.00 | $10,000 | $20,150 | $23,000 | $23,158 |
| 83 | Mobilization (624E10000) | LS | 1 | $12,000 | $21,700 | $55,000 | $25,850 | $18,000 | $26,869 |
| 84 | Special - pre-construction video (690E98400) | LS | 1 | $1,550.00 | $2,000.00 | $1,500.00 | $2,000.00 | $1,600.00 | $5,789.47 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.