ODOT contract 250396 bid tabulation
ROS-SR 772-07.64 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on August 28, 2025, ROS. 8 bids received; low bid $1,649,002 by Miller Bros Const Inc, -1.0% against the engineer's estimate of $1,665,000.
- Owner
- Ohio DOT
- Letting
- 28 AUG 2025
- Pay items
- 74
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Miller Bros Const Inc | $1,649,002 | Low | -1.0% |
| 2 | Double Z Construction Company | $1,657,380 | +1.0% | 0.0% |
| 3 | D G M Inc | $1,694,124 | +3.0% | +2.0% |
| 4 | Alan Stone Co Inc | $1,738,050 | +5.0% | +4.0% |
| 5 | George J Igel & Co Inc | $1,836,632 | +11% | +10% |
| 6 | Shelly & Sands Inc | $1,882,404 | +14% | +13% |
| 7 | Complete General Construction Company | $1,905,839 | +16% | +14% |
| 8 | Ruhlin Company | $2,550,835 | +55% | +53% |
Engineer's estimate: $1,665,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller Bros Const Inc | 2. Double Z Construction Company | 3. D G M Inc | 4. Alan Stone Co Inc | 5. George J Igel & Co Inc | 6. Shelly & Sands Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,296.43 | $28,000 | $13,000 | $15,000 | $42,000 | $39,000 |
| 2 | Pavement removed (202E23000) | SY | 854 | $21.03 | $18.00 | $12.50 | $15.00 | $13.00 | $17.00 |
| 3 | Guardrail removed (202E38000) | FT | 606 | $10.00 | $10.00 | $1.00 | $8.00 | $5.50 | $3.50 |
| 4 | Excavation (203E10000) | CY | 486 | $39.30 | $10.00 | $25.00 | $45.00 | $20.50 | $36.01 |
| 5 | Embankment (203E20000) | CY | 486 | $29.87 | $30.00 | $25.00 | $20.00 | $9.75 | $18.00 |
| 6 | Subgrade compaction (204E10000) | SY | 1,105 | $3.62 | $10.00 | $5.00 | $6.00 | $5.00 | $6.50 |
| 7 | Proof rolling (204E45000) | HR | 1 | $267.25 | $150.00 | $75.00 | $280.00 | $132.00 | $225.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 175 | $33.00 | $33.00 | $37.50 | $40.00 | $33.00 | $21.50 |
| 9 | Anchor assembly, MGS type E (NCHRP 350 / MASH 2016 (606E26150) | EACH | 4 | $3,150.00 | $3,150.00 | $3,250.00 | $3,700.00 | $3,150.00 | $2,500.00 |
| 10 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,925.00 | $2,925.00 | $3,000.00 | $3,500.00 | $2,925.00 | $2,600.00 |
| 11 | Rock channel protection, type C with filter (601E32200) | CY | 144 | $128.77 | $77.00 | $100.00 | $120.00 | $118.00 | $98.00 |
| 12 | Soil analysis test (659E00100) | EACH | 2 | $25.00 | $150.00 | $50.00 | $180.00 | $25.00 | $150.00 |
| 13 | Topsoil (659E00300) | CY | 85 | $42.56 | $55.00 | $20.00 | $40.00 | $13.25 | $40.00 |
| 14 | Seeding and mulching (659E10000) | SY | 765 | $3.50 | $10.00 | $7.00 | $4.00 | $6.00 | $4.00 |
| 15 | Repair seeding and mulching (659E14000) | SY | 38 | $1.00 | $4.00 | $0.05 | $15.00 | $1.00 | $4.00 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.10 | $800.00 | $1,250.00 | $1,500.00 | $660.00 | $800.00 | $1,250.00 |
| 17 | Lime (659E31000) | ACRE | 0.16 | $100.00 | $150.00 | $300.00 | $950.00 | $100.00 | $150.00 |
| 18 | Water (659E35000) | MGAL | 4 | $30.00 | $1.00 | $1.00 | $120.00 | $30.00 | $1.00 |
| 19 | Erosion control (832E30000) | EACH | 1,445 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | Aggregate drains (605E31100) | FT | 134 | $23.91 | $18.00 | $25.00 | $34.66 | $37.00 | $20.00 |
| 21 | 6" conduit, type E (611E01400) | FT | 50 | $32.21 | $6.00 | $8.00 | $24.82 | $31.50 | $10.00 |
| 22 | 6" conduit, type F (611E01500) | FT | 50 | $37.78 | $6.00 | $8.00 | $32.45 | $31.50 | $7.50 |
| 23 | 8" conduit, type B (611E01800) | FT | 50 | $54.04 | $12.00 | $10.00 | $26.74 | $40.00 | $12.00 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 182 | $205.00 | $205.00 | $215.00 | $297.52 | $205.00 | $205.00 |
| 25 | Aggregate base (304E20000) | CY | 184 | $78.74 | $98.00 | $100.00 | $106.49 | $69.70 | $125.00 |
| 26 | Tack coat (407E10000) | GAL | 154 | $3.50 | $3.50 | $3.50 | $6.44 | $3.50 | $3.50 |
| 27 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 71 | $305.00 | $305.00 | $315.00 | $400.00 | $305.00 | $305.00 |
| 28 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 0.51 | $18,663 | $12,100 | $15,000 | $19,000 | $12,100 | $12,100 |
| 29 | RPM (621E00100) | EACH | 11 | $375.00 | $275.00 | $275.00 | $325.00 | $275.00 | $275.00 |
| 30 | Raised pavement marker removed (621E54000) | EACH | 11 | $23.97 | $6.00 | $1.00 | $20.00 | $20.00 | $10.00 |
| 31 | Barrier reflector, type 3, bidirectional (626E00112) | EACH | 10 | $13.00 | $13.00 | $15.00 | $13.00 | $13.00 | $12.00 |
| 32 | Edge line, 6", type 1 (642E00104) | MI | 0.24 | $3,550.00 | $3,550.00 | $3,750.00 | $4,000.00 | $3,550.00 | $3,550.00 |
| 33 | Center line, type 1 (642E00300) | MI | 0.18 | $4,595.00 | $4,595.00 | $4,750.00 | $4,500.00 | $4,595.00 | $4,595.00 |
| 34 | Pavement planing, asphalt concrete (1 1/4") (254E01000) | SY | 600 | $14.60 | $10.00 | $15.00 | $25.00 | $6.75 | $13.75 |
| 35 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 21 | $440.00 | $375.00 | $460.00 | $420.00 | $525.00 | $440.00 |
| 36 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 72 | $104.15 | $60.00 | $60.00 | $95.00 | $100.00 | $110.00 |
| 37 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $3,500.00 | $3,500.00 | $2,500.00 | $2,500.00 | $3,500.00 | $2,200.00 |
| 38 | Barrier reflector, type 1 (two-way) (614E13310) | EACH | 12 | $50.00 | $50.00 | $50.00 | $60.00 | $16.00 | $7.00 |
| 39 | Object marker, two way (614E13360) | EACH | 12 | $50.00 | $50.00 | $50.00 | $60.00 | $26.00 | $24.00 |
| 40 | Work zone edge line, class I, 6" (614E22010) | MI | 0.43 | $4,250.00 | $4,250.00 | $4,500.00 | $5,000.00 | $10,450 | $4,250.00 |
| 41 | Work zone stop line, class I (614E26000) | FT | 44 | $12.00 | $12.00 | $12.00 | $15.00 | $12.00 | $12.00 |
| 42 | Pavement for maintaining traffic, class A (615E20000) | SY | 372 | $153.57 | $155.00 | $110.00 | $137.00 | $135.00 | $115.00 |
| 43 | Water (616E10000) | MGAL | 3 | $99.24 | $50.00 | $1.00 | $1.00 | $45.50 | $74.00 |
| 44 | Portable barrier, unanchored (622E41100) | FT | 950 | $22.35 | $28.00 | $20.00 | $18.00 | $29.00 | $28.00 |
| 45 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $89,824 | $100,000 | $130,000 | $90,000 | $160,000 | $105,000 |
| 46 | Approach slab removed (202E22900) | SY | 212 | $59.32 | $50.00 | $35.00 | $75.00 | $45.00 | $30.00 |
| 47 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $20,211 | $33,000 | $67,500 | $8,000.00 | $16,000 | $100,000 |
| 48 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $27,337 | $25,000 | $8,000.00 | $15,000 | $40,000 | $21,000 |
| 49 | Steel piles HP10X42, furnished, as per plan (507E00101) | FT | 400 | $57.33 | $38.00 | $38.00 | $40.00 | $37.00 | $29.85 |
| 50 | Prebored holes, as per plan (507E92201) | FT | 205 | $115.00 | $250.00 | $250.00 | $125.00 | $195.00 | $350.00 |
| 51 | Epoxy coated steel reinforcement (509E10000) | LB | 47,263 | $1.68 | $1.50 | $1.40 | $1.90 | $1.70 | $1.90 |
| 52 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 131 | $1,785.87 | $1,750.00 | $1,445.00 | $1,850.00 | $1,820.00 | $1,850.00 |
| 53 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 146 | $880.67 | $910.00 | $670.00 | $800.00 | $965.00 | $980.00 |
| 54 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 324 | $26.55 | $30.00 | $35.00 | $48.00 | $30.00 | $30.00 |
| 55 | Draped strand prestressed concrete bridge I-beam members, level 3, type 3 (515E15010) | EACH | 5 | $42,370 | $46,500 | $60,000 | $55,000 | $49,900 | $53,000 |
| 56 | Intermediate diaphragms (515E20000) | EACH | 4 | $2,924.54 | $2,300.00 | $2,770.00 | $7,500.00 | $3,500.00 | $4,500.00 |
| 57 | 1/2" preformed expansion joint filler (516E13200) | SF | 79 | $5.27 | $12.00 | $12.00 | $6.00 | $8.00 | $6.00 |
| 58 | 1" preformed expansion joint filler (516E13600) | SF | 82 | $6.72 | $14.00 | $15.00 | $2.00 | $9.25 | $7.00 |
| 59 | 2" preformed expansion joint filler (516E13900) | SF | 65 | $7.83 | $18.00 | $20.00 | $2.50 | $14.00 | $10.00 |
| 60 | Integral abutment expansion joint seal (516E14014) | FT | 105 | $29.86 | $30.00 | $47.50 | $30.00 | $36.00 | $50.00 |
| 61 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 10 | $1,873.97 | $1,800.00 | $2,000.00 | $2,252.50 | $2,900.00 | $1,650.00 |
| 62 | Railing (three steel tube bridge railing) (517E70100) | FT | 182 | $449.50 | $449.50 | $465.00 | $460.00 | $456.05 | $450.00 |
| 63 | Porous backfill with geotextile fabric, as per plan (518E21201) | CY | 352 | $73.04 | $85.00 | $95.00 | $50.00 | $105.00 | $100.00 |
| 64 | 6" perforated corrugated plastic pipe (518E40000) | FT | 147 | $10.60 | $15.00 | $20.00 | $15.00 | $9.50 | $7.00 |
| 65 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 60 | $20.17 | $18.00 | $20.00 | $15.00 | $40.00 | $9.00 |
| 66 | Reinforced concrete approach slabs with QC/QA (T=1 (526E15010) | SY | 161 | $406.05 | $390.00 | $387.00 | $500.00 | $465.00 | $500.00 |
| 67 | Type A installation (526E90010) | FT | 72 | $190.34 | $275.00 | $280.00 | $325.00 | $325.00 | $245.00 |
| 68 | Structure grounding system (625E33000) | EACH | 1 | $18,500 | $10,000 | $23,000 | $18,000 | $18,500 | $21,000 |
| 69 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,016.45 | $10,700 | $41,000 | $15,000 | $9,000.00 | $10,800 |
| 70 | Maintaining traffic (614E11000) | LS | 1 | $71,855 | $70,000 | $82,500 | $77,000 | $78,000 | $51,000 |
| 71 | Field office, type A (619E16000) | MNTH | 4 | $6,781.99 | $2,000.00 | $750.00 | $1,500.00 | $1,825.00 | $5,000.00 |
| 72 | Construction layout stakes and surveying (623E10000) | LS | 1 | $11,000 | $18,000 | $7,000.00 | $25,000 | $12,000 | $12,000 |
| 73 | Mobilization (624E10000) | LS | 1 | $82,450 | $40,000 | $40,000 | $45,000 | $90,000 | $95,500 |
| 100 | Wearing course removed (202E23500) | SY | 622 | $8.22 | $18.00 | $10.00 | $5.00 | $11.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 28, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.