ODOT contract 250421 bid tabulation
CUY-US 6-14.56 Tower B (BRIDGE REPAIR). Let by Ohio DOT on September 11, 2025, CUY. 5 bids received; low bid $1,108,670 by Catts Construction Inc, +15% against the engineer's estimate of $963,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 33
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Catts Construction Inc | $1,108,670 | Low | +15% |
| 2 | Suburban Maintenance & Construction Inc | $1,329,288 | +20% | +38% |
| 3 | Ruhlin Company | $1,387,117 | +25% | +44% |
| 4 | S E T Inc | $1,404,308 | +27% | +46% |
| 5 | Perk Company Inc | $1,947,085 | +76% | +102% |
Engineer's estimate: $963,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Catts Construction Inc | 2. Suburban Maintenance & Construction Inc | 3. Ruhlin Company | 4. S E T Inc | 5. Perk Company Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,600.00 | $50,000 | $1,000.00 | $4,000.00 | $25,000 |
| 2 | Pipe removed, 24" and under (202E35100) | FT | 207 | $91.00 | $75.00 | $50.00 | $44.00 | $100.00 |
| 3 | Manhole removed (202E58000) | EACH | 1 | $800.00 | $3,000.00 | $840.00 | $1,200.00 | $910.00 |
| 4 | Fence removed (202E75000) | FT | 184 | $15.00 | $15.00 | $12.50 | $3.50 | $7.25 |
| 5 | Excavation (203E10000) | CY | 2,158 | $15.00 | $65.00 | $13.31 | $13.50 | $37.50 |
| 6 | Embankment (203E20000) | CY | 2,158 | $18.50 | $65.00 | $5.50 | $10.50 | $35.50 |
| 7 | Subgrade compaction (204E10000) | SY | 799 | $1.25 | $5.00 | $13.00 | $3.50 | $2.15 |
| 8 | Proof rolling (204E45000) | HR | 2 | $100.00 | $120.00 | $413.00 | $300.00 | $1,085.00 |
| 9 | Fence, type CLT (607E23000) | FT | 184 | $67.00 | $63.00 | $54.00 | $57.00 | $30.50 |
| 10 | Soil analysis test (659E00100) | EACH | 2 | $93.00 | $100.00 | $200.00 | $150.00 | $610.00 |
| 11 | Topsoil (659E00300) | CY | 233 | $43.50 | $75.00 | $50.00 | $75.00 | $85.00 |
| 12 | Seeding and mulching (659E10000) | SY | 2,100 | $2.50 | $5.00 | $4.00 | $3.50 | $2.50 |
| 13 | Repair seeding and mulching (659E14000) | SY | 105 | $1.25 | $5.00 | $1.50 | $4.00 | $1.25 |
| 14 | Inter-seeding (659E15000) | SY | 105 | $1.00 | $5.00 | $0.10 | $4.00 | $1.25 |
| 15 | Commercial fertilizer (659E20000) | TON | 0.29 | $1,100.00 | $1,000.00 | $650.00 | $2,000.00 | $1,200.00 |
| 16 | Lime (659E31000) | ACRE | 0.43 | $180.00 | $2,000.00 | $50.00 | $1,000.00 | $1,200.00 |
| 17 | Water (659E35000) | MGAL | 12 | $1.00 | $1.00 | $1.00 | $150.00 | $120.00 |
| 18 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | 12" conduit, type C, as per plan (611E04601) | FT | 212 | $109.00 | $150.00 | $425.00 | $340.00 | $215.00 |
| 20 | 18" conduit, type D (611E07900) | FT | 71 | $109.00 | $185.00 | $174.00 | $89.00 | $405.00 |
| 21 | Manhole, no. 3 (611E99574) | EACH | 1 | $13,010 | $5,000.00 | $6,300.00 | $6,750.00 | $13,050 |
| 22 | Compacted aggregate (617E10100) | CY | 178 | $39.00 | $75.00 | $168.00 | $176.50 | $110.00 |
| 23 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $116,000 | $245,000 | $332,500 | $170,000 | $245,000 |
| 24 | Unclassified excavation, as per plan (503E21101) | CY | 34 | $154.00 | $125.00 | $380.00 | $158.00 | $185.00 |
| 25 | Epoxy coated steel reinforcement (509E10000) | LB | 1,567 | $5.00 | $2.00 | $12.00 | $2.85 | $3.00 |
| 26 | Class QC1 concrete, footing (511E46510) | CY | 11 | $700.00 | $2,200.00 | $1,930.00 | $915.00 | $970.00 |
| 27 | Drilled shafts, 36" diameter, into bedrock (524E94704) | FT | 20 | $4,333.00 | $2,300.00 | $6,800.00 | $2,300.00 | $2,950.00 |
| 28 | Drilled shafts, 42" diameter, above bedrock (524E94802) | FT | 308 | $1,310.00 | $1,385.00 | $1,500.00 | $2,300.00 | $2,950.00 |
| 29 | Special - structures, dowel holes with epoxy adhes (530E00400) | EACH | 32 | $120.00 | $50.00 | $700.00 | $98.00 | $95.00 |
| 30 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,587 | $25,000 | $12,502 | $30,000 | $19,000 |
| 31 | Field office, type B, as per plan (619E16011) | MNTH | 6 | $3,000.00 | $1,200.00 | $3,672.00 | $2,650.00 | $2,000.00 |
| 32 | Construction layout stakes and surveying (623E10000) | LS | 1 | $21,000 | $30,000 | $28,500 | $10,000 | $28,000 |
| 33 | Mobilization (624E10000) | LS | 1 | $231,500 | $40,000 | $67,500 | $160,000 | $285,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.