ODOT contract 250572 bid tabulation
WAR-SR 73-07.20 (TWO LANE RESURFACING). Let by Ohio DOT on December 4, 2025, WAR. 3 bids received; low bid $4,722,570 by John R Jurgensen Company, +2.9% against the engineer's estimate of $4,589,000.
- Owner
- Ohio DOT
- Letting
- 04 DEC 2025
- Pay items
- 98
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $4,722,570 | Low | +3.0% |
| 2 | Fillmore Construction | $4,785,475 | +1.0% | +4.0% |
| 3 | Barrett Paving Materials Inc | $5,028,794 | +6.0% | +10% |
Engineer's estimate: $4,589,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Fillmore Construction | 3. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $19,342 | $25,000 | $8,000.00 |
| 2 | Pavement removed (202E23000) | SY | 422 | $15.66 | $20.00 | $50.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 81 | $25.69 | $20.00 | $12.00 |
| 4 | Guardrail removed (202E38000) | FT | 11,721 | $2.50 | $2.50 | $2.50 |
| 5 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 32 | $275.00 | $275.00 | $275.00 |
| 6 | Anchor assembly removed, type E (202E42010) | EACH | 19 | $50.00 | $50.00 | $50.00 |
| 7 | Anchor assembly removed, type T (202E42040) | EACH | 9 | $40.00 | $40.00 | $40.00 |
| 8 | Anchor assembly removed, type B (202E42050) | EACH | 1 | $50.00 | $50.00 | $50.00 |
| 9 | Bridge terminal assembly removed (202E47000) | EACH | 7 | $75.00 | $75.00 | $75.00 |
| 10 | Excavation (203E10000) | CY | 566 | $19.50 | $30.00 | $40.00 |
| 11 | Embankment (203E20000) | CY | 1,020 | $22.82 | $50.00 | $35.00 |
| 12 | Subgrade compaction (204E10000) | SY | 1,951 | $2.25 | $5.00 | $5.00 |
| 13 | Excavation of subgrade (204E13000) | CY | 888 | $34.88 | $30.00 | $40.00 |
| 14 | Granular material, type C (204E30020) | CY | 888 | $70.40 | $100.00 | $85.00 |
| 15 | Geotextile fabric (204E50000) | SY | 1,951 | $3.10 | $3.00 | $2.50 |
| 16 | Reshaping under guardrail (209E15000) | STA | 142 | $35.00 | $35.00 | $35.00 |
| 17 | Guardrail, type MGS with long posts (606E15100) | FT | 11,000 | $24.50 | $24.50 | $24.50 |
| 18 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 46 | $2,450.00 | $2,450.00 | $2,450.00 |
| 19 | Anchor assembly, MGS type E, softstop (606E26150) | EACH | 5 | $2,850.00 | $2,850.00 | $2,850.00 |
| 20 | Anchor assembly, MGS type T (606E26550) | EACH | 14 | $1,100.00 | $1,100.00 | $1,100.00 |
| 21 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 7 | $2,400.00 | $2,400.00 | $2,400.00 |
| 22 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $325.00 | $325.00 | $325.00 |
| 23 | Topsoil (659E00300) | CY | 313 | $44.10 | $50.00 | $62.00 |
| 24 | Seeding and mulching (659E10000) | SY | 2,818 | $1.48 | $1.45 | $1.48 |
| 25 | Commercial fertilizer (659E20000) | TON | 0.38 | $925.00 | $1,400.00 | $925.00 |
| 26 | Lime (659E31000) | ACRE | 0.58 | $100.00 | $450.00 | $100.00 |
| 27 | Water (659E35000) | MGAL | 16 | $1.00 | $100.00 | $1.00 |
| 28 | Sodding reinforced (660E20000) | SY | 77 | $17.45 | $15.00 | $17.45 |
| 29 | Slope erosion protection (670E00500) | SY | 29 | $8.00 | $2.00 | $8.00 |
| 30 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,300.00 | $3,500.00 | $2,500.00 |
| 31 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,790.00 | $5,000.00 | $7,500.00 |
| 32 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $12,116 | $10,000 | $12,120 |
| 33 | Erosion control (832E30000) | EACH | 24,405 | $1.00 | $1.00 | $1.00 |
| 34 | 6" base pipe underdrains (605E14000) | FT | 2,816 | $14.55 | $12.00 | $18.00 |
| 35 | 12" conduit, type D (611E04900) | FT | 49 | $95.75 | $100.00 | $65.00 |
| 36 | 12" conduit, type D (611E04900) | FT | 46 | $124.64 | $200.00 | $90.00 |
| 37 | Pavement repair (253E02000) | CY | 500 | $476.90 | $300.00 | $460.00 |
| 38 | Pavement planing, asphalt concrete, 1.25" (254E01000) | SY | 229,104 | $1.35 | $2.00 | $2.30 |
| 39 | Patching planed surface (254E01600) | SY | 2,298 | $4.26 | $5.00 | $5.00 |
| 40 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 458 | $217.56 | $200.00 | $225.00 |
| 41 | Aggregate base (304E20000) | CY | 510 | $76.25 | $100.00 | $90.00 |
| 42 | Tack coat (407E10000) | GAL | 9 | $5.00 | $5.00 | $4.00 |
| 43 | Non-tracking tack coat (407E20000) | GAL | 21,029 | $5.00 | $5.00 | $4.00 |
| 44 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 8,023 | $245.96 | $220.00 | $252.00 |
| 45 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 95 | $331.89 | $300.00 | $295.00 |
| 46 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 4 | $1,884.04 | $500.00 | $1,200.00 |
| 47 | Asphalt concrete intermediate course, type 1, (449), (driveways) (441E70600) | CY | 5 | $1,552.44 | $500.00 | $1,200.00 |
| 48 | Compacted aggregate (617E10100) | CY | 952 | $137.47 | $100.00 | $100.00 |
| 49 | Shoulder preparation (617E20000) | SY | 17,717 | $1.61 | $2.00 | $0.50 |
| 50 | Water (617E25000) | MGAL | 19 | $7.51 | $100.00 | $10.00 |
| 51 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 9.25 | $750.00 | $1,000.00 | $1,275.00 |
| 52 | RPM (621E00100) | EACH | 1,213 | $36.70 | $40.00 | $36.70 |
| 53 | Raised pavement marker removed (621E54000) | EACH | 1,191 | $12.00 | $10.00 | $10.00 |
| 54 | Barrier reflector, type 2, (bidirectional) (626E00110) | EACH | 152 | $12.00 | $12.00 | $12.00 |
| 55 | Ground mounted support, no. 3 post (630E03100) | FT | 39 | $16.00 | $16.00 | $16.00 |
| 56 | Sign, flat sheet (630E80100) | SF | 24.75 | $26.00 | $26.00 | $26.00 |
| 57 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $15.00 | $15.00 | $15.00 |
| 58 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $30.00 | $30.00 | $30.00 |
| 59 | Edge line, 6" (644E00104) | MI | 20.20 | $3,810.00 | $4,089.00 | $3,810.00 |
| 60 | Center line (644E00300) | MI | 11.43 | $3,875.00 | $4,508.00 | $3,875.00 |
| 61 | Channelizing line, 12" (644E00404) | FT | 4,384 | $1.50 | $1.84 | $1.50 |
| 62 | Stop line (644E00500) | FT | 300 | $7.50 | $7.16 | $7.50 |
| 63 | Transverse/diagonal line (644E00700) | FT | 2,583 | $7.50 | $7.15 | $7.50 |
| 64 | Island marking (644E00900) | SF | 350 | $6.00 | $3.35 | $6.00 |
| 65 | Lane arrow (644E01300) | EACH | 64 | $115.00 | $112.50 | $115.00 |
| 66 | Wet reflective traffic paint, edge line, 6" (807E10010) | MI | 9.61 | $2,580.00 | $3,835.00 | $2,580.00 |
| 67 | Wet reflective traffic paint, lane line, 6" (807E10110) | MI | 4.42 | $1,100.00 | $1,917.00 | $1,100.00 |
| 68 | Wet reflective traffic paint, channelizing line, 1 (807E10310) | FT | 850 | $1.30 | $1.50 | $1.30 |
| 69 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 14.03 | $1,300.00 | $2,218.00 | $1,300.00 |
| 70 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 850 | $0.30 | $1.85 | $0.30 |
| 71 | Increased barrier delineation (614E11630) | FT | 172 | $2.32 | $3.00 | $2.32 |
| 72 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 6 | $1,973.66 | $2,000.00 | $1,973.66 |
| 73 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 41 | $13.03 | $14.00 | $13.03 |
| 74 | Object marker, two way (614E13360) | EACH | 45 | $25.79 | $26.00 | $25.97 |
| 75 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 4.42 | $500.00 | $665.00 | $500.00 |
| 76 | Work zone center line, class III, 642 paint (614E21550) | MI | 11.58 | $990.00 | $2,188.00 | $990.00 |
| 77 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 30.21 | $700.00 | $1,124.00 | $700.00 |
| 78 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 4,980 | $0.85 | $0.76 | $0.85 |
| 79 | Work zone stop line, class III, 642 paint (614E26610) | FT | 300 | $2.80 | $5.15 | $2.80 |
| 80 | Pavement for maintaining traffic, class B (615E25000) | SY | 1,708 | $58.74 | $100.00 | $80.00 |
| 81 | Water (616E10000) | MGAL | 4 | $164.25 | $100.00 | $100.00 |
| 82 | Portable barrier, unanchored (622E41100) | FT | 1,823 | $30.98 | $31.00 | $30.98 |
| 83 | Portions of structure removed (202E11300) | CY | 0.03 | $81,765 | $10,000 | $80,000 |
| 84 | Epoxy coated steel reinforcement (509E10000) | LB | 76 | $37.04 | $3.00 | $15.00 |
| 85 | Class QC1 concrete, headwall (511E46610) | CY | 0.41 | $18,833 | $8,000.00 | $20,000 |
| 86 | Sealing of concrete surfaces (512E10000) | SY | 1 | $800.00 | $1,000.00 | $300.00 |
| 87 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,352 | $35,000 | $23,414 |
| 88 | Maintaining traffic (614E11000) | LS | 1 | $128,275 | $250,000 | $275,000 |
| 89 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $11,853 | $25,000 | $20,000 |
| 90 | Monument assembly removed and reset (623E40000) | EACH | 5 | $749.13 | $3,000.00 | $1,250.00 |
| 91 | Mobilization (624E10000) | LS | 1 | $225,000 | $153,000 | $100,000 |
| 100 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 6 | $280.89 | $100.00 | $125.00 |
| 101 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 41 | $54.06 | $50.00 | $32.00 |
| 102 | Precast reinforced concrete outlet (611E99710) | EACH | 3 | $655.66 | $500.00 | $250.00 |
| 103 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 200 | $131.42 | $100.00 | $85.00 |
| 104 | Work zone raised pavement marker (614E12800) | EACH | 26 | $19.42 | $7.51 | $7.51 |
| 105 | Roads for maintaining traffic (615E10000) | LS | 1 | $50,118 | $5,000.00 | $35,000 |
| 106 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 19.84 | $750.00 | $1,000.00 | $1,275.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.