ODOT contract 260078 bid tabulation

CLI-SR 133-02.11 (BRIDGE REPAIR). Let by Ohio DOT on February 19, 2026, CLI. 4 bids received; low bid $1,167,846 by Eagle Bridge Co, -17% against the engineer's estimate of $1,400,000.

Owner
Ohio DOT
Letting
19 FEB 2026
Pay items
77
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Eagle Bridge Co$1,167,846Low-17%
2Double Z Construction Company$1,305,810+12%-7.0%
3Sunesis Construction Co$1,379,862+18%-1.0%
4Complete General Construction Company$1,416,432+21%+1.0%
ODOT contract 260078: bids by rank

Engineer's estimate: $1,400,000.

Bid tabulation

LinePay itemUnitQuantity1. Eagle Bridge Co2. Double Z Construction Company3. Sunesis Construction Co4. Complete General Construction Company
1Clearing and grubbing (201E11000)LS1$10,000$10,000$3,296.03$5,000.00
2Pavement removed (202E23000)SY516$22.00$24.00$2.30$25.00
3Guardrail removed (202E38000)FT168.75$4.00$2.00$22.49$2.00
4Anchor assembly removed, type A, as per plan (202E42001)EACH4$500.00$365.00$242.80$365.00
5Embankment (203E20000)CY72$75.00$100.00$40.34$30.00
6Subgrade compaction (204E10000)SY1,005$6.00$7.00$8.10$9.00
7Excavation of subgrade (204E13000)CY335$30.00$35.00$58.20$45.00
8Granular material, type C (204E30020)CY335$75.00$56.00$125.30$90.00
9Geotextile fabric (204E50000)SY1,005$1.75$1.50$2.43$10.00
10Reshaping under guardrail (209E15050)MI0.06$2,750.00$2,750.00$28,698$2,750.00
11Guardrail, type MGS (606E15050)FT18.75$39.20$39.20$35.00$39.20
12Anchor assembly, MGS type E (MASH 2016) (606E26150)EACH3$2,550.00$2,550.00$2,600.00$2,550.00
13Anchor assembly, MGS type T (606E26550)EACH1$1,340.00$1,340.00$1,250.00$1,340.00
14MGS bridge terminal assembly, type TST-2 (606E34600)EACH4$2,630.00$2,630.00$2,600.00$2,630.00
15Inspection and compaction testing of unbound materials (878E25000)LS1$10,000$7,334.00$3,667.20$12,000
16Topsoil (659E00300)CY189$15.00$45.00$29.33$25.00
17Seeding and mulching (659E10000)SY1,700$3.00$5.00$4.21$5.20
18Repair seeding and mulching (659E14000)SY85$3.00$2.20$2.20$2.20
19Commercial fertilizer (659E20000)TON0.24$1,000.00$1,250.00$1,250.00$1,250.00
20Lime (659E31000)ACRE0.35$5.00$150.00$150.00$150.00
21Water (659E35000)MGAL9.40$10.00$1.00$1.00$1.00
22Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00
23Rock channel protection, type C with filter (601E32200)CY0.55$250.00$500.00$1,284.11$1,900.00
24Concrete masonry (602E20000)CY0.21$4,000.00$4,500.00$4,250.19$10,500
2512" conduit, type B (611E04400)FT102$110.00$125.00$126.24$250.00
26Catch basin, no. 3 (611E98150)EACH2$4,500.00$4,000.00$4,247.31$10,000
27Pavement planing, asphalt concrete(D=1.50") (254E01000)SY746$9.50$13.00$8.35$13.00
28Asphalt concrete base, PG64-22, (449) (301E56000)CY178$235.00$262.00$262.28$262.00
29Aggregate base (304E20000)CY405$55.00$90.00$118.54$95.00
30Non-tracking tack coat (407E20000)GAL257$4.00$4.10$8.91$4.10
31Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY88$300.00$284.00$386.32$284.00
32RPM (621E00100)EACH10$317.00$317.00$317.00$317.00
33Raised pavement marker removed (621E54000)EACH11$10.00$30.00$317.00$50.00
34Edge line, 6" (644E00104)MI0.04$34,375$34,375$34,375$34,375
35Center line (644E00300)MI0.02$68,750$68,750$68,750$68,750
36Edge line, 6" (646E10010)MI0.16$22,500$22,500$22,500$22,500
37Center line (646E10200)MI0.08$27,000$27,000$27,000$27,000
38Law enforcement officer with patrol car for assistance, as per plan (614E11111)HR80$60.00$60.00$68.65$90.00
39Detour signing (614E12420)LS1$12,500$15,000$8,940.00$8,940.00
40Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$57,500$120,000$105,449$95,000
41Approach slab removed (202E22900)SY140$50.00$50.00$30.91$75.00
42Cofferdams and excavation bracing, as per plan (503E11101)LS1$25,000$60,000$28,624$65,000
43Unclassified excavation (503E21300)LS1$22,500$20,000$15,556$20,000
44Pile driving equipment mobilization (505E11100)LS1$20,000$20,000$4,390.67$17,000
4514" cast-in-place reinforced concrete piles, driven with QC/QA (507E00602)FT560$8.00$60.00$47.75$45.00
4614" cast-in-place reinforced concrete piles, furnished (507E00650)FT630$115.00$45.00$80.53$75.00
47Galvanized steel reinforcement (509E26000)LB35,628$1.70$1.80$2.53$2.00
48Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001)EACH264$17.00$30.00$19.80$15.00
49Class QC2 concrete with QC/QA, superstructure (511E33312)CY142$1,650.00$1,700.00$1,765.82$1,700.00
50Class QC1 concrete with QC/QA, abutment (511E45712)CY18$2,000.00$1,600.00$3,711.41$1,900.00
51Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY127$38.00$38.00$36.50$38.00
52Type 2 waterproofing (512E33000)SY14$50.00$50.00$38.57$125.00
53Surface preparation of existing structural steel (514E00050)SF526$60.00$60.00$60.00$125.00
54Field painting of existing structural steel, prime coat (514E00056)SF541$10.00$10.00$10.00$10.00
55Field painting structural steel, finish coat (514E00066)SF449$10.00$10.00$10.00$10.00
561/2" preformed expansion joint filler (516E13200)SF172$6.00$13.00$3.62$16.00
571" preformed expansion joint filler (516E13600)SF108$8.00$15.00$6.63$18.00
58Integral abutment expansion joint seal (516E14014)FT84$50.00$40.00$52.26$75.00
59Railing (three steel tube bridge railing) (517E70100)FT126.13$470.00$475.00$492.00$505.00
60Porous backfill with geotextile fabric (518E21200)CY55$125.00$115.00$143.38$150.00
61Special - steel drip strip (518E22300)FT139$16.00$20.00$37.90$15.25
626" perforated corrugated plastic pipe (518E40000)FT124$12.00$13.00$7.82$12.00
636" non-perforated corrugated plastic pipe, including specials (518E40010)FT100$25.00$15.00$19.12$15.00
64Dynamic load testing (523E20000)EACH4$2,500.00$3,680.00$4,631.07$6,100.00
65Reinforced concrete approach slabs (T=13"), as per plan (526E15001)SY186$300.00$430.00$480.07$395.00
66Type A installation, as per plan (526E90011)FT80$250.00$250.00$185.41$400.00
67Polymer modified asphalt expansion joint system (846E00110)CF23.74$1,000.00$1,165.77$1,165.77$1,200.00
68Premium for contract performance bond and for payment bond (103E05000)LS1$25,000$9,000.00$8,034.51$9,500.00
69Maintaining traffic (614E11000)LS1$2,500.00$8,400.00$3,891.08$3,000.00
70Construction layout stakes and surveying (623E10000)LS1$15,000$14,000$13,900$15,000
71Mobilization (624E10000)LS1$55,000$60,000$84,403$71,000
100Wearing course removed (202E23500)SY140$15.00$18.00$4.13$13.50
101Proof rolling (204E45000)HR2$125.00$180.00$489.12$350.00
102Steel points or shoes (507E93300)EACH14$600.00$200.00$281.53$190.00
103Barrier reflector, type 5. (626E00116)EACH11$12.40$12.40$20.00$12.40
104Combination curb and gutter, type 2 (609E12000)FT84$65.00$70.00$85.40$95.00
105Field painting structural steel, intermediate coat (514E00060)SF449$10.00$10.00$10.00$10.00
ODOT contract 260078: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy