ODOT contract 260087 bid tabulation
JAC-SR 788-00.87 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on February 19, 2026, JAC. 8 bids received; low bid $984,962 by D G M Inc, -15% against the engineer's estimate of $1,160,000.
- Owner
- Ohio DOT
- Letting
- 19 FEB 2026
- Pay items
- 77
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $984,962 | Low | -15% |
| 2 | R C Construction Company and Son Inc | $1,065,164 | +8.0% | -8.0% |
| 3 | Double Z Construction Company | $1,067,840 | +8.0% | -8.0% |
| 4 | George J Igel & Co Inc | $1,104,864 | +12% | -5.0% |
| 5 | Axis Civil Construction LLC | $1,110,136 | +13% | -4.0% |
| 6 | Complete General Construction Company | $1,111,789 | +13% | -4.0% |
| 7 | Shelly & Sands Inc | $1,138,636 | +16% | -2.0% |
| 8 | Beaver Excavating Company | $1,268,890 | +29% | +9.0% |
Engineer's estimate: $1,160,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. R C Construction Company and Son Inc | 3. Double Z Construction Company | 4. George J Igel & Co Inc | 5. Axis Civil Construction LLC | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $12,500 | $3,500.00 | $5,000.00 | $5,600.00 | $15,000 | $5,000.00 |
| 2 | Pavement removed (202E23000) | SY | 860 | $15.00 | $25.00 | $28.00 | $18.00 | $16.00 | $30.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 110 | $25.00 | $50.00 | $8.00 | $18.00 | $28.00 | $40.00 |
| 4 | Guardrail removed (202E38000) | FT | 278 | $1.00 | $5.00 | $6.00 | $5.00 | $8.00 | $3.00 |
| 5 | Excavation (203E10000) | CY | 246 | $30.00 | $25.00 | $30.00 | $35.00 | $32.00 | $30.00 |
| 6 | Embankment (203E20000) | CY | 159 | $30.00 | $25.00 | $20.00 | $25.00 | $32.00 | $34.00 |
| 7 | Subgrade compaction (204E10000) | SY | 1,309 | $4.00 | $2.00 | $6.00 | $2.60 | $3.00 | $5.00 |
| 8 | Proof rolling (204E45000) | HR | 1 | $75.00 | $100.00 | $200.00 | $118.00 | $250.00 | $140.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 300 | $28.00 | $26.00 | $24.98 | $24.98 | $25.00 | $24.98 |
| 10 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 1 | $2,500.00 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 5 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 12 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 3 | $2,300.00 | $2,200.00 | $2,200.00 | $2,200.00 | $2,200.00 | $2,200.00 |
| 13 | MGS bridge terminal assembly, type TST-2, as per plan (606E34601) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 14 | Special - mailbox removed and reset (690E50350) | EACH | 3 | $250.00 | $250.00 | $250.00 | $275.00 | $400.00 | $300.00 |
| 15 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 83 | $120.00 | $150.00 | $115.00 | $125.00 | $128.00 | $116.00 |
| 16 | Topsoil (659E00300) | CY | 104 | $25.00 | $5.00 | $50.00 | $8.50 | $60.00 | $50.00 |
| 17 | Seeding and mulching (659E10000) | SY | 940 | $4.00 | $5.00 | $8.00 | $5.65 | $2.80 | $5.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.13 | $1,500.00 | $2,000.00 | $1,250.00 | $1,250.00 | $560.00 | $700.00 |
| 19 | Lime (659E31000) | ACRE | 0.19 | $300.00 | $2,000.00 | $150.00 | $150.00 | $320.00 | $100.00 |
| 20 | Water (659E35000) | MGAL | 5 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Erosion control (832E30000) | EACH | 9,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Aggregate drains (605E31100) | FT | 121 | $30.00 | $25.00 | $20.00 | $52.00 | $20.00 | $24.00 |
| 23 | 6" conduit, type E (611E01400) | FT | 25 | $8.00 | $5.00 | $8.00 | $44.60 | $22.00 | $35.00 |
| 24 | 6" conduit, type F (611E01500) | FT | 25 | $6.00 | $5.00 | $8.00 | $44.60 | $22.00 | $60.00 |
| 25 | 12" conduit, type D (611E04900) | FT | 76 | $100.00 | $125.00 | $80.00 | $62.00 | $65.00 | $90.00 |
| 26 | 24" conduit, type D (611E10900) | FT | 50 | $120.00 | $125.00 | $120.00 | $85.00 | $85.00 | $140.00 |
| 27 | Pavement repair (253E02000) | CY | 25 | $330.00 | $25.00 | $380.00 | $185.40 | $300.00 | $480.00 |
| 28 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 129 | $260.00 | $240.00 | $230.00 | $325.00 | $320.00 | $230.00 |
| 29 | Aggregate base (304E20000) | CY | 177 | $100.00 | $110.00 | $92.00 | $120.00 | $130.00 | $144.00 |
| 30 | Tack coat (407E10000) | GAL | 165 | $4.70 | $10.00 | $4.70 | $8.90 | $7.00 | $4.70 |
| 31 | Stabilized crushed aggregate (411E10000) | CY | 44 | $120.00 | $110.00 | $125.00 | $142.00 | $130.00 | $150.00 |
| 32 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 78 | $250.00 | $400.00 | $255.00 | $346.25 | $390.00 | $255.00 |
| 33 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $1,150.00 | $900.00 | $1,150.00 | $160.00 | $465.00 | $1,150.00 |
| 34 | Compacted aggregate (617E10100) | CY | 25 | $75.00 | $110.00 | $100.00 | $52.35 | $145.00 | $150.00 |
| 35 | RPM (621E00100) | EACH | 4 | $500.00 | $550.00 | $750.00 | $602.00 | $500.00 | $500.00 |
| 36 | Raised pavement marker removed (621E54000) | EACH | 4 | $1.00 | $100.00 | $50.00 | $30.00 | $50.00 | $55.00 |
| 37 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 10 | $15.00 | $10.00 | $20.00 | $11.00 | $11.00 | $11.00 |
| 38 | Ground mounted support, no. 2 post (630E02100) | FT | 20 | $45.00 | $20.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 39 | Sign post reflector (630E08600) | EACH | 2 | $25.00 | $100.00 | $30.00 | $30.00 | $55.00 | $30.00 |
| 40 | Sign, flat sheet (630E80100) | SF | 6 | $125.00 | $40.00 | $40.00 | $40.00 | $16.00 | $40.00 |
| 41 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $175.00 | $100.00 | $15.00 | $15.00 | $20.00 | $15.00 |
| 42 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $175.00 | $100.00 | $15.00 | $15.00 | $25.00 | $15.00 |
| 43 | Edge line, 6", type 1 (642E00104) | MI | 0.14 | $7,000.00 | $5,500.00 | $7,000.00 | $11,144 | $5,350.00 | $5,350.00 |
| 44 | Center line, type 1 (642E00300) | MI | 0.07 | $12,000 | $10,200 | $7,000.00 | $22,285 | $10,195 | $10,195 |
| 45 | Detour signing (614E12420) | LS | 1 | $4,000.00 | $20,000 | $9,000.00 | $7,135.00 | $3,950.00 | $3,950.00 |
| 46 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $160.00 | $25.00 | $140.00 | $281.70 | $250.00 | $300.00 |
| 47 | Water (616E10000) | MGAL | 3 | $1.00 | $1.00 | $50.00 | $41.30 | $1.00 | $160.00 |
| 48 | Portions of structure removed, over 20 foot span (202E11202) | LS | 1 | $42,500 | $20,000 | $60,000 | $45,000 | $36,000 | $95,000 |
| 49 | Wearing course removed (202E23500) | SY | 126 | $10.00 | $25.00 | $15.00 | $18.00 | $12.00 | $28.00 |
| 50 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $500.00 | $15,000 | $30,000 | $100.00 | $26,000 | $8,000.00 |
| 51 | Unclassified excavation (503E21100) | CY | 188 | $25.00 | $25.00 | $190.00 | $260.00 | $35.00 | $125.00 |
| 52 | Epoxy coated steel reinforcement (509E10000) | LB | 13,908 | $1.30 | $3.00 | $2.00 | $1.75 | $2.30 | $2.20 |
| 53 | Class QC2 concrete, superstructure, as per plan (511E31611) | CY | 43 | $2,150.00 | $1,200.00 | $1,570.00 | $1,705.00 | $1,650.00 | $1,500.00 |
| 54 | Class QC1 concrete, abutment including footing (511E43510) | CY | 68 | $675.00 | $950.00 | $925.00 | $930.55 | $1,200.00 | $1,100.00 |
| 55 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 70 | $40.00 | $50.00 | $40.00 | $50.00 | $50.00 | $50.00 |
| 56 | Type 2 waterproofing (512E33000) | SY | 10 | $50.00 | $35.00 | $50.00 | $52.00 | $100.00 | $60.00 |
| 57 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 10 | $16,500 | $16,000 | $15,000 | $18,225 | $17,500 | $15,000 |
| 58 | 2" preformed expansion joint filler (516E13900) | SF | 27 | $25.00 | $50.00 | $20.00 | $15.00 | $15.00 | $16.00 |
| 59 | Semi-integral abutment expansion joint seal (516E14020) | FT | 71 | $50.00 | $100.00 | $40.00 | $49.00 | $65.00 | $49.00 |
| 60 | Elastomeric bearing with internal laminates and load plate (516E44000) | EACH | 40 | $800.00 | $725.00 | $600.00 | $925.00 | $800.00 | $775.00 |
| 61 | Railing (three steel tube bridge railing) (517E70100) | FT | 131 | $425.00 | $425.00 | $421.00 | $421.00 | $421.00 | $421.00 |
| 62 | Porous backfill with geotextile fabric (518E21200) | CY | 52 | $135.00 | $110.00 | $135.00 | $160.00 | $125.00 | $140.00 |
| 63 | Special - steel drip strip (518E22300) | FT | 68 | $25.00 | $50.00 | $30.00 | $16.00 | $25.00 | $30.00 |
| 64 | 6" perforated corrugated plastic pipe (518E40000) | FT | 90 | $25.00 | $50.00 | $12.00 | $12.00 | $11.00 | $14.00 |
| 65 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 36 | $75.00 | $50.00 | $50.00 | $105.00 | $12.00 | $24.00 |
| 66 | Drilled shafts, 30" diameter, into bedrock (524E94604) | FT | 65 | $388.00 | $500.00 | $340.00 | $251.15 | $500.00 | $360.00 |
| 67 | Drilled shafts, 36" diameter, above bedrock (524E94702) | FT | 301 | $388.00 | $500.00 | $400.00 | $400.20 | $360.00 | $340.00 |
| 68 | Reinforced concrete approach slabs (T=13") (526E15000) | SY | 134 | $275.00 | $250.00 | $390.00 | $400.00 | $395.00 | $425.00 |
| 69 | Type A installation (526E90010) | FT | 60 | $250.00 | $200.00 | $220.00 | $250.00 | $390.00 | $250.00 |
| 70 | Structure grounding system (625E33000) | EACH | 1 | $20,000 | $20,000 | $13,776 | $13,776 | $17,500 | $14,000 |
| 71 | Thermal integrity profiling (tip) test (894E10000) | EACH | 2 | $4,250.00 | $4,000.00 | $4,000.00 | $5,200.00 | $3,875.00 | $7,000.00 |
| 72 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $19,000 | $35,000 | $7,600.00 | $5,600.00 | $12,000 | $8,000.00 |
| 73 | Maintaining traffic (614E11000) | LS | 1 | $14,000 | $20,000 | $5,000.00 | $1,800.00 | $15,000 | $6,000.00 |
| 74 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,000.00 | $15,000 | $10,000 | $11,000 | $10,000 | $18,000 |
| 75 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $1,500.00 | $400.00 | $3,600.00 | $800.00 | $2,200.00 |
| 76 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,000.00 | $1,500.00 | $400.00 | $3,400.00 | $800.00 | $2,200.00 |
| 77 | Mobilization (624E10000) | LS | 1 | $20,000 | $25,000 | $50,000 | $54,950 | $40,000 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.