ODOT contract 260130 bid tabulation
NOB-TR 392-00.02 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on March 12, 2026, NOB. 5 bids received; low bid $587,916 by J & J Bridge Company Inc, -6.7% against the engineer's estimate of $630,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 69
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J & J Bridge Company Inc | $587,916 | Low | -7.0% |
| 2 | Buds Inc | $617,938 | +5.0% | -2.0% |
| 3 | Shelly & Sands Inc | $637,867 | +8.0% | +1.0% |
| 4 | Complete General Construction Company | $868,911 | +48% | +38% |
| 5 | R C Construction Company and Son Inc | $946,900 | +61% | +50% |
Engineer's estimate: $630,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J & J Bridge Company Inc | 2. Buds Inc | 3. Shelly & Sands Inc | 4. Complete General Construction Company | 5. R C Construction Company and Son Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $3,500.00 | $3,420.00 | $3,000.00 | $30,000 |
| 2 | Guardrail removed (202E38000) | FT | 78 | $6.00 | $2.50 | $12.00 | $3.50 | $5.00 |
| 3 | Fence removed, as per plan (202E75001) | FT | 351 | $2.00 | $5.00 | $9.00 | $4.00 | $25.00 |
| 4 | Gate removed, as per plan (202E75251) | EACH | 3 | $100.00 | $50.00 | $350.00 | $245.00 | $1,000.00 |
| 5 | Excavation (203E10000) | CY | 103 | $35.00 | $30.00 | $40.00 | $45.00 | $25.00 |
| 6 | Embankment (203E20000) | CY | 145 | $50.00 | $62.00 | $35.00 | $20.00 | $35.00 |
| 7 | Subgrade compaction (204E10000) | SY | 445 | $5.00 | $6.00 | $5.00 | $9.00 | $2.00 |
| 8 | Excavation of subgrade (204E13000) | CY | 25 | $10.00 | $20.00 | $30.00 | $30.00 | $25.00 |
| 9 | Granular material, type B (204E30010) | CY | 25 | $40.00 | $85.00 | $120.00 | $75.00 | $175.00 |
| 10 | Proof rolling (204E45000) | HR | 1 | $300.00 | $50.00 | $250.00 | $300.00 | $100.00 |
| 11 | Geotextile fabric (204E50000) | SY | 75 | $2.00 | $1.00 | $5.00 | $10.00 | $15.00 |
| 12 | Guardrail, type MGS (606E15050) | FT | 75 | $44.00 | $30.00 | $32.00 | $32.00 | $40.00 |
| 13 | Anchor assembly, type A (606E25000) | EACH | 2 | $1,500.00 | $1,750.00 | $1,460.00 | $1,460.00 | $1,700.00 |
| 14 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,200.00 | $1,100.00 | $985.00 | $985.00 | $1,700.00 |
| 15 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 2 | $2,200.00 | $2,600.00 | $2,695.00 | $2,695.00 | $2,200.00 |
| 16 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 2 | $2,500.00 | $2,900.00 | $2,780.00 | $2,780.00 | $2,500.00 |
| 17 | Fence, misc.:high-tensile non-electric wire fence (607E98000) | FT | 227 | $30.00 | $35.00 | $33.00 | $33.00 | $35.00 |
| 18 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $250.00 | $200.00 | $250.00 | $295.00 | $350.00 |
| 19 | Topsoil (659E00300) | CY | 114 | $8.00 | $20.00 | $47.00 | $79.07 | $35.00 |
| 20 | Seeding and mulching (659E10000) | SY | 755 | $2.00 | $1.75 | $4.00 | $4.00 | $20.00 |
| 21 | Repair seeding and mulching (659E14000) | SY | 38 | $2.00 | $0.01 | $4.00 | $4.00 | $0.20 |
| 22 | Inter-seeding (659E15000) | SY | 38 | $2.00 | $0.01 | $4.00 | $4.00 | $0.20 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.14 | $2,000.00 | $800.00 | $1,250.00 | $1,250.00 | $2,900.00 |
| 24 | Lime (659E31000) | ACRE | 0.22 | $1,500.00 | $540.00 | $150.00 | $150.00 | $2,800.00 |
| 25 | Water (659E35000) | MGAL | 3 | $8.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 37 | $400.00 | $325.00 | $325.00 | $385.00 | $425.00 |
| 28 | Aggregate base (304E20000) | CY | 63 | $135.00 | $110.00 | $170.00 | $150.00 | $175.00 |
| 29 | Tack coat (407E10000) | GAL | 44 | $4.00 | $30.00 | $3.25 | $4.50 | $10.00 |
| 30 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 41 | $450.00 | $350.00 | $325.00 | $415.00 | $625.00 |
| 31 | Ground mounted support, no. 3 post (630E03100) | FT | 56 | $15.00 | $18.00 | $25.00 | $25.00 | $25.00 |
| 32 | Street name sign support, no. 3 post (630E08520) | FT | 15 | $25.00 | $20.00 | $42.00 | $32.50 | $35.00 |
| 33 | Sign, flat sheet (630E80100) | SF | 30.25 | $35.00 | $25.00 | $42.00 | $30.00 | $35.00 |
| 34 | Sign, double faced, street name (630E80500) | EACH | 2 | $250.00 | $225.00 | $325.00 | $220.00 | $250.00 |
| 35 | Removal of ground mounted sign and disposal (630E84900) | EACH | 8 | $10.00 | $25.00 | $60.00 | $15.00 | $100.00 |
| 36 | Removal of ground mounted post support and disposal (630E86002) | EACH | 7 | $10.00 | $25.00 | $60.00 | $20.00 | $100.00 |
| 37 | Stop line (644E00500) | FT | 28 | $15.00 | $15.00 | $15.00 | $15.00 | $100.00 |
| 38 | Center line (646E10200) | MI | 0.02 | $63,000 | $63,000 | $63,000 | $63,000 | $95,000 |
| 39 | Structure for maintaining traffic, as per plan (502E11101) | LS | 1 | $78,000 | $50,000 | $42,000 | $40,000 | $65,000 |
| 40 | Roads for maintaining traffic, as per plan (615E10001) | LS | 1 | $35,000 | $50,000 | $26,775 | $235,000 | $65,000 |
| 41 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $19,300 | $20,000 | $46,700 | $20,000 | $30,000 |
| 42 | Wearing course removed (202E23500) | SY | 42 | $10.00 | $32.00 | $41.00 | $175.00 | $45.00 |
| 43 | Unclassified excavation (503E21300) | LS | 1 | $15,000 | $7,500.00 | $4,850.00 | $19,000 | $12,500 |
| 44 | Pile driving equipment mobilization (505E11100) | LS | 1 | $12,000 | $25,000 | $19,420 | $12,000 | $45,000 |
| 45 | Steel piles HP10X42, furnished (507E00100) | FT | 400 | $40.00 | $42.00 | $36.00 | $36.00 | $85.00 |
| 46 | Steel piles HP10X42, driven (507E00150) | FT | 350 | $60.00 | $3.50 | $52.00 | $25.00 | $30.00 |
| 47 | Steel points or shoes (507E93300) | EACH | 10 | $175.00 | $150.00 | $145.00 | $145.00 | $250.00 |
| 48 | Epoxy coated steel reinforcement (509E10000) | LB | 5,676 | $3.00 | $2.00 | $3.00 | $2.50 | $3.50 |
| 49 | Class QC2 concrete, superstructure, as per plan (511E31611) | CY | 5 | $3,000.00 | $1,500.00 | $3,725.00 | $3,900.00 | $2,500.00 |
| 50 | Class QC1 concrete, abutment including footing (511E43510) | CY | 60 | $700.00 | $1,000.00 | $1,365.00 | $1,125.00 | $1,200.00 |
| 51 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 51 | $40.00 | $25.00 | $60.00 | $60.00 | $75.00 |
| 52 | Type 3 waterproofing (512E33010) | SY | 122 | $35.00 | $35.00 | $43.50 | $43.50 | $40.00 |
| 53 | Prestressed concrete non-composite box beam bridge members, level 1, B21-48, as per plan (515E10051) | EACH | 6 | $11,500 | $21,850 | $13,615 | $20,000 | $21,000 |
| 54 | 2" preformed expansion joint filler (516E13900) | SF | 27 | $12.00 | $15.00 | $12.00 | $30.00 | $50.00 |
| 55 | Integral abutment expansion joint seal (516E14014) | FT | 64 | $45.00 | $42.00 | $46.50 | $45.00 | $100.00 |
| 56 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 24 | $35.00 | $75.00 | $32.00 | $71.00 | $50.00 |
| 57 | Elastomeric bearing with internal laminates only (neoprene) (516E43100) | EACH | 24 | $105.00 | $215.00 | $160.00 | $125.00 | $400.00 |
| 58 | Railing (twin steel tube) (517E70000) | FT | 91 | $250.00 | $232.00 | $222.00 | $270.00 | $235.00 |
| 59 | Porous backfill with geotextile fabric (518E21200) | CY | 15 | $250.00 | $165.00 | $265.00 | $250.00 | $175.00 |
| 60 | Special - steel drip strip (518E22300) | FT | 112 | $14.00 | $17.00 | $15.00 | $15.00 | $50.00 |
| 61 | 6" perforated corrugated plastic pipe (518E40000) | FT | 79 | $8.00 | $15.00 | $7.00 | $20.00 | $25.00 |
| 62 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 24 | $9.20 | $20.00 | $14.00 | $20.00 | $25.00 |
| 63 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 70 | $160.00 | $115.00 | $80.00 | $95.00 | $175.00 |
| 64 | Low strength mortar backfill (613E41200) | CY | 116 | $135.00 | $118.00 | $200.00 | $375.00 | $225.00 |
| 65 | Structure grounding system (625E33000) | EACH | 1 | $7,500.00 | $5,000.00 | $21,000 | $10,000 | $22,000 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $9,000.00 | $3,621.00 | $6,000.00 | $40,000 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $2,000.00 | $5,000.00 | $2,000.00 | $4,500.00 | $35,000 |
| 68 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,711.00 | $4,000.00 | $16,787 | $8,000.00 | $20,000 |
| 69 | Mobilization (624E10000) | LS | 1 | $24,599 | $40,000 | $31,895 | $43,000 | $55,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.