ODOT contract 260134 bid tabulation
SCI-SR 125-06.26 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on March 12, 2026, SCI. 7 bids received; low bid $1,965,728 by Complete General Construction Company, +12% against the engineer's estimate of $1,760,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 84
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $1,965,728 | Low | +12% |
| 2 | R C Construction Company and Son Inc | $1,979,273 | +1.0% | +12% |
| 3 | George J Igel & Co Inc | $2,024,403 | +3.0% | +15% |
| 4 | Double Z Construction Company | $2,033,755 | +3.0% | +16% |
| 5 | Sunesis Construction Co | $2,097,336 | +7.0% | +19% |
| 6 | Axis Civil Construction LLC | $2,128,388 | +8.0% | +21% |
| 7 | D G M Inc | $2,217,459 | +13% | +26% |
Engineer's estimate: $1,760,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. R C Construction Company and Son Inc | 3. George J Igel & Co Inc | 4. Double Z Construction Company | 5. Sunesis Construction Co | 6. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $27,000 | $20,000 | $33,750 | $8,000.00 | $15,000 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 781 | $28.00 | $25.00 | $18.00 | $25.00 | $11.95 | $14.00 |
| 3 | Guardrail removed (202E38000) | FT | 374 | $3.00 | $5.00 | $7.00 | $6.00 | $1.65 | $6.00 |
| 4 | Excavation (203E10000) | CY | 106 | $35.00 | $25.00 | $27.00 | $50.00 | $7.56 | $32.00 |
| 5 | Embankment (203E20000) | CY | 812 | $37.00 | $35.00 | $47.00 | $35.00 | $16.82 | $42.00 |
| 6 | Subgrade compaction (204E10000) | SY | 1,002 | $4.00 | $2.00 | $5.25 | $8.00 | $3.02 | $3.50 |
| 7 | Proof rolling (204E45000) | HR | 1 | $130.00 | $100.00 | $112.00 | $200.00 | $386.18 | $250.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 87.50 | $43.00 | $45.00 | $32.00 | $42.80 | $42.80 | $42.80 |
| 9 | Guardrail, type MGS with long posts (606E15100) | FT | 62.50 | $46.00 | $48.00 | $35.00 | $45.98 | $45.98 | $46.00 |
| 10 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 3 | $2,380.00 | $2,450.00 | $2,700.00 | $2,380.00 | $2,380.00 | $2,380.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,100.00 | $1,300.00 | $1,400.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 12 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,340.00 | $2,500.00 | $2,800.00 | $2,340.00 | $2,340.00 | $2,340.00 |
| 13 | Primary project control monument, type B (623E12010) | EACH | 3 | $1,500.00 | $1,000.00 | $2,000.00 | $450.00 | $1,240.38 | $1,500.00 |
| 14 | Monument assembly, type C (623E38500) | EACH | 2 | $1,800.00 | $1,000.00 | $1,100.00 | $1,200.00 | $2,537.19 | $2,800.00 |
| 15 | Right-of-way monument, type B (623E40520) | EACH | 14 | $250.00 | $600.00 | $320.00 | $350.00 | $1,240.38 | $350.00 |
| 16 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 199 | $115.00 | $100.00 | $90.00 | $100.00 | $121.05 | $140.00 |
| 17 | Seeding and mulching (659E10000) | SY | 1,670 | $1.93 | $10.00 | $4.15 | $6.00 | $4.17 | $2.00 |
| 18 | Repair seeding and mulching (659E14000) | SY | 84 | $1.93 | $0.20 | $1.93 | $1.93 | $7.60 | $2.00 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.23 | $1,250.00 | $2,900.00 | $1,250.00 | $1,250.00 | $500.00 | $1,250.00 |
| 20 | Lime (659E31000) | ACRE | 0.35 | $150.00 | $2,200.00 | $150.00 | $150.00 | $100.00 | $150.00 |
| 21 | Water (659E35000) | MGAL | 9 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Erosion control (832E30000) | EACH | 6,365 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Aggregate drains (605E31100) | FT | 61 | $29.00 | $25.00 | $60.00 | $25.00 | $33.78 | $24.00 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 97 | $365.00 | $370.00 | $365.00 | $545.00 | $545.00 | $390.00 |
| 25 | Aggregate base (304E20000) | CY | 162 | $135.00 | $150.00 | $110.00 | $100.00 | $112.59 | $135.00 |
| 26 | Non-tracking tack coat (407E20000) | GAL | 76 | $4.10 | $10.00 | $4.10 | $4.50 | $4.50 | $7.00 |
| 27 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 24 | $580.00 | $590.00 | $580.00 | $695.00 | $695.00 | $450.00 |
| 28 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 33 | $380.00 | $385.00 | $380.00 | $625.00 | $625.00 | $420.00 |
| 29 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 10 | $10.00 | $10.00 | $14.00 | $10.00 | $13.98 | $10.00 |
| 30 | Ground mounted support, no. 3 post (630E03100) | FT | 51 | $12.00 | $30.00 | $18.00 | $12.00 | $12.00 | $12.00 |
| 31 | Sign post reflector (630E08600) | EACH | 1 | $26.00 | $250.00 | $75.00 | $26.00 | $26.00 | $26.00 |
| 32 | Sign, flat sheet (630E80100) | SF | 6.30 | $35.00 | $45.00 | $20.00 | $35.00 | $35.00 | $35.00 |
| 33 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $10.00 | $100.00 | $40.00 | $10.00 | $10.00 | $10.00 |
| 34 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $60.00 | $250.00 | $75.00 | $60.00 | $60.00 | $60.00 |
| 35 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $15.00 | $100.00 | $45.00 | $15.00 | $15.00 | $15.00 |
| 36 | Edge line, 6", type 1 (642E00104) | MI | 0.23 | $4,500.00 | $10,000 | $9,900.00 | $4,500.00 | $9,900.00 | $9,900.00 |
| 37 | Center line, type 1 (642E00300) | MI | 0.11 | $4,500.00 | $18,500 | $13,200 | $4,500.00 | $13,200 | $13,200 |
| 38 | Stop line, type 1 (642E00500) | FT | 20 | $8.00 | $20.00 | $7.50 | $8.00 | $7.50 | $7.50 |
| 39 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 7 | $2,000.00 | $3,000.00 | $2,200.00 | $1,988.53 | $2,200.00 | $2,450.00 |
| 40 | Barrier reflector, type 1(BI-directional) (614E13310) | EACH | 21 | $40.00 | $20.00 | $17.00 | $20.00 | $13.39 | $16.00 |
| 41 | Barrier reflector, type 3 (BI-directional) (614E13314) | EACH | 3 | $40.00 | $20.00 | $21.00 | $20.00 | $13.39 | $40.00 |
| 42 | Object marker, two way (614E13360) | EACH | 23 | $20.00 | $50.00 | $20.00 | $20.00 | $19.88 | $35.00 |
| 43 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.56 | $3,500.00 | $10,000 | $9,385.00 | $3,500.00 | $9,385.00 | $9,385.00 |
| 44 | Work zone stop line, class III, 642 paint (614E26610) | FT | 44 | $8.00 | $100.00 | $20.00 | $8.00 | $20.00 | $20.00 |
| 45 | Roads for maintaining traffic (615E10000) | LS | 1 | $35,000 | $25,000 | $17,500 | $25,000 | $11,999 | $8,500.00 |
| 46 | Pavement for maintaining traffic, class B (615E25000) | SY | 211 | $141.50 | $150.00 | $90.00 | $120.00 | $93.47 | $100.00 |
| 47 | Water (616E10000) | MGAL | 7 | $160.00 | $1.00 | $52.05 | $40.00 | $23.77 | $1.00 |
| 48 | Portable barrier, unanchored (622E41100) | FT | 740 | $33.60 | $35.00 | $50.50 | $28.00 | $40.84 | $28.00 |
| 49 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $145,000 | $30,000 | $140,000 | $95,000 | $72,400 | $140,000 |
| 50 | Approach slab removed (202E22900) | SY | 107 | $60.00 | $25.00 | $65.00 | $58.00 | $56.08 | $120.00 |
| 51 | Wearing course removed (202E23500) | SY | 364 | $35.00 | $30.00 | $15.00 | $15.00 | $7.61 | $11.00 |
| 52 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $40,000 | $100,000 | $50,000 | $140,000 | $89,295 | $90,000 |
| 53 | Unclassified excavation, including rock (503E21320) | LS | 1 | $60,000 | $25,000 | $56,250 | $73,000 | $92,981 | $28,000 |
| 54 | Steel piles HP14X73, furnished, as per plan (507E00301) | FT | 880 | $110.00 | $110.00 | $73.00 | $70.00 | $80.77 | $74.00 |
| 55 | Prebored holes, as per plan (507E92201) | FT | 484 | $80.00 | $300.00 | $310.00 | $260.00 | $428.59 | $390.00 |
| 56 | Epoxy coated steel reinforcement (509E10000) | LB | 34,641 | $1.88 | $3.00 | $1.75 | $1.75 | $2.02 | $2.65 |
| 57 | Class QC2 concrete with QC/QA, superstructure, as per plan (511E31613) | CY | 66 | $1,650.00 | $1,750.00 | $1,600.00 | $1,600.00 | $1,777.55 | $1,650.00 |
| 58 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 155 | $1,250.00 | $1,000.00 | $795.00 | $995.00 | $1,033.78 | $930.00 |
| 59 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 169 | $600.00 | $1,000.00 | $655.00 | $525.00 | $638.81 | $780.00 |
| 60 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 176 | $36.00 | $50.00 | $36.00 | $37.00 | $40.49 | $36.00 |
| 61 | Type 2 waterproofing (512E33000) | SY | 31 | $50.00 | $35.00 | $33.00 | $40.00 | $131.33 | $45.00 |
| 62 | Prestressed concrete composite box beam bridge members, level 1, CB27-48 (515E12070) | EACH | 9 | $25,500 | $24,000 | $28,350 | $30,700 | $26,220 | $25,500 |
| 63 | 1" preformed expansion joint filler (516E13600) | SF | 122 | $12.00 | $25.00 | $10.05 | $20.00 | $6.04 | $5.00 |
| 64 | 2" preformed expansion joint filler (516E13900) | SF | 34 | $14.00 | $35.00 | $11.00 | $22.00 | $8.00 | $12.00 |
| 65 | Semi-integral abutment expansion joint seal (516E14020) | FT | 92 | $46.00 | $100.00 | $45.00 | $40.00 | $50.34 | $46.00 |
| 66 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 18 | $90.00 | $25.00 | $120.00 | $50.00 | $105.78 | $80.00 |
| 67 | Elastomeric bearing with internal laminates and load plate (516E44100) | EACH | 36 | $1,075.00 | $1,100.00 | $700.00 | $800.00 | $793.53 | $1,360.00 |
| 68 | Railing (three steel tube bridge railing) (517E70100) | FT | 148 | $426.00 | $435.00 | $445.00 | $426.00 | $426.00 | $426.00 |
| 69 | Prefabricated geocomposite drain (518E20000) | SY | 42 | $42.00 | $20.00 | $35.00 | $60.00 | $32.11 | $45.00 |
| 70 | Porous backfill with geotextile fabric (518E21200) | CY | 93 | $135.00 | $150.00 | $150.00 | $140.00 | $110.68 | $120.00 |
| 71 | Special - steel drip strip (518E22300) | FT | 126 | $28.00 | $50.00 | $22.00 | $25.00 | $16.96 | $31.00 |
| 72 | 6" perforated corrugated plastic pipe (518E40000) | FT | 190 | $10.00 | $25.00 | $9.00 | $10.00 | $4.32 | $15.00 |
| 73 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 60 | $28.00 | $25.00 | $35.00 | $20.00 | $21.21 | $15.00 |
| 74 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 240 | $480.00 | $275.00 | $500.00 | $475.00 | $485.52 | $540.00 |
| 75 | Type A installation (526E90010) | FT | 77 | $260.00 | $200.00 | $260.00 | $230.00 | $240.88 | $450.00 |
| 76 | Low strength mortar backfill (type 2) (613E41300) | CY | 110 | $175.00 | $175.00 | $248.00 | $190.00 | $233.02 | $220.00 |
| 77 | Structure grounding system (625E33000) | EACH | 1 | $17,000 | $20,000 | $9,852.00 | $9,852.00 | $8,536.00 | $21,000 |
| 78 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,000 | $47,000 | $10,000 | $12,000 | $11,671 | $18,000 |
| 79 | Maintaining traffic (614E11000) | LS | 1 | $60,000 | $45,000 | $92,000 | $64,000 | $72,448 | $75,000 |
| 80 | Field office, type A (619E16000) | MNTH | 6 | $2,600.00 | $100.00 | $1,605.00 | $2,000.00 | $1,585.00 | $3,200.00 |
| 81 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $12,000 | $17,000 | $19,500 | $59,900 | $20,000 |
| 82 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,200.00 | $1,500.00 | $3,600.00 | $500.00 | $1,000.00 | $800.00 |
| 83 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,200.00 | $1,500.00 | $5,600.00 | $500.00 | $1,000.00 | $800.00 |
| 84 | Mobilization (624E10000) | LS | 1 | $90,000 | $55,000 | $100,000 | $100,000 | $81,067 | $95,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way