ODOT contract 260180 bid tabulation

MOT-CR 74-08.40 (SIGNALIZATION). Let by Ohio DOT on April 9, 2026, MOT. 4 bids received; low bid $818,666 by Capital Electric Line Builders Inc, +38% against the engineer's estimate of $594,000.

Owner
Ohio DOT
Letting
09 APR 2026
Pay items
107
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Capital Electric Line Builders Inc$818,666Low+38%
2Complete General Construction Company$840,307+3.0%+41%
3Bansal Construction Inc$868,996+6.0%+46%
4Perram Electric Inc$928,788+13%+56%
ODOT contract 260180: bids by rank

Engineer's estimate: $594,000.

Bid tabulation

LinePay itemUnitQuantity1. Capital Electric Line Builders Inc2. Complete General Construction Company3. Bansal Construction Inc4. Perram Electric Inc
1Clearing and grubbing (201E11000)LS1$115.00$2,600.00$2,030.00$2,435.00
2Pavement removed (202E23000)SY91$143.75$65.00$125.00$116.75
3Walk removed (202E30000)SF614$5.75$9.00$6.25$7.50
4Concrete median removed (202E30600)SY23$62.10$88.00$42.00$50.60
5Curb removed (202E32000)FT116$23.00$25.00$25.00$30.00
6Excavation (203E10000)CY63$57.50$230.00$65.00$78.00
7Embankment (203E20000)CY12$57.50$38.00$90.00$108.00
8Subgrade compaction (204E10000)SY86$11.50$7.00$10.00$12.00
94" concrete walk (608E10000)SF1,100$14.38$19.00$8.50$10.20
108" concrete walk (608E15000)SF143$23.00$22.00$15.00$18.00
11Curb ramp (608E52000)SF1,071$25.30$22.00$37.00$44.40
12Detectable warning (608E53020)SF100$51.75$75.00$35.00$42.00
13Soil analysis test (659E00100)EACH2$115.00$350.00$200.00$300.00
14Topsoil (659E00300)CY52$74.75$120.00$115.00$138.00
15Seeding and mulching, class 1 (659E00500)SY468$3.45$8.50$5.00$7.20
16Commercial fertilizer (659E20000)TON0.07$1,150.00$850.00$1,500.00$910.00
17Lime (659E31000)ACRE0.10$1,150.00$45.00$200.00$1,320.00
18Water (659E35000)MGAL3$11.50$1.00$1.00$120.00
19Manhole adjusted to grade (611E99654)EACH1$3,450.00$1,600.00$1,100.00$1,320.00
20Pavement planing, asphalt concrete, 1.5" (254E01000)SY1,718$23.00$20.00$20.00$24.00
21Asphalt concrete base, PG64-22, (449) (301E56000)CY12$1,667.50$1,450.00$1,450.00$1,740.00
22Aggregate base (304E20000)CY12$724.50$175.21$630.00$755.00
23Non-tracking tack coat (407E20000)GAL145$5.75$5.00$5.00$6.00
24Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY77$954.50$830.00$830.00$996.00
258" non-reinforced concrete pavement, class QC 1P (452E12010)SY30$207.00$125.00$230.00$162.00
266" concrete traffic island (609E54000)SY1$1,035.00$1,375.00$1,150.00$1,380.00
27Valve box adjusted to grade (638E10800)EACH2$2,070.00$475.00$230.00$275.00
28Ground mounted support, no. 3 post (630E03100)FT84.50$18.65$20.00$16.22$27.60
29Sign hanger assembly, mast arm, as per plan (630E79101)EACH24$464.65$625.00$404.04$166.00
30Sign, flat sheet (630E80100)SF151$21.85$30.00$18.93$35.60
31Sign, street name, as per plan (630E80511)EACH8$364.69$740.00$317.12$517.00
32Removal of ground mounted sign and storage (630E85000)EACH5$19.58$45.00$17.03$130.00
33Removal of ground mounted sign and reerection (630E85100)EACH2$78.97$70.00$68.67$440.00
34Removal of ground mounted post support and storage (630E86006)EACH4$26.11$55.00$22.70$130.00
35Edge line, 6" (644E00104)MI0.06$5,865.00$5,100.00$5,100.00$6,120.00
36Lane line, 6" (644E00204)MI0.02$4,600.00$4,000.00$4,000.00$4,800.00
37Center line (644E00300)MI0.05$8,050.00$7,000.00$7,000.00$8,400.00
38Channelizing line, 12" (644E00404)FT488$2.88$2.50$2.50$3.00
39Stop line (644E00500)FT154$9.20$8.00$8.00$9.60
40Crosswalk line, 24" (644E00630)FT220$9.20$8.00$8.00$9.60
41Chevron marking (644E00720)FT177$9.20$8.00$8.00$9.60
42Lane arrow (644E01300)EACH5$161.00$140.00$140.00$168.00
43Removal of pavement marking (644E30000)FT250$2.30$2.00$2.00$2.40
44Stop line (646E10400)FT15$11.50$10.00$10.00$12.00
45Crosswalk line, 24" (646E10520)FT45$23.00$20.00$20.00$24.00
46Connection, fused pull apart (625E00450)EACH4$120.18$160.00$125.00$210.00
47Connection, unfused pull apart (625E00460)EACH4$120.18$140.00$125.00$200.00
48Bracket arm, 20', as per plan (625E18401)EACH3$1,599.65$2,850.00$1,775.00$1,745.00
49Bracket arm, 25', as per plan (625E18501)EACH1$1,892.90$2,850.00$2,125.00$2,050.00
50No. 8 AWG 600 volt distribution cable (625E23304)FT1,250$3.57$3.00$2.50$2.62
51No. 10 AWG pole and bracket cable (625E23400)FT750$2.55$2.50$2.20$1.68
52Conduit, 2", 725.04 (625E25400)FT115$37.32$31.00$18.50$32.25
53Conduit, 3", 725.04 (625E25500)FT45$56.25$40.00$35.00$52.60
54Conduit, jacked or drilled, 725.051, 4" (625E25906)FT266$70.31$55.00$85.00$86.95
55Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH4$488.75$375.00$330.00$500.00
56Trench (625E29000)FT149$60.44$12.00$16.25$20.95
57Pull box, 725.08, 18" (625E30700)EACH3$1,660.60$1,650.00$1,055.00$2,100.00
58Pull box, 725.08, 24" (625E30706)EACH1$1,775.60$1,900.00$1,310.00$2,415.00
59Ground rod (625E32000)EACH10$365.70$350.00$490.00$415.00
60Underground warning marking tape (625E36010)FT149$1.93$1.00$1.75$1.60
61Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH12$1,214.40$1,100.00$1,360.00$1,287.00
62Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064)EACH6$1,541.00$1,400.00$1,690.00$1,545.00
63Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH8$793.50$900.00$725.00$730.00
64Accessible pedestrian pushbutton, as per plan (632E20751)EACH12$1,706.60$1,600.00$1,435.00$1,730.00
65Accessible pedestrian pushbutton, as per plan (632E20751)EACH4$1,273.05$1,200.00$1,000.00$1,275.00
66Covering of vehicular signal head (632E25000)EACH24$39.68$40.00$85.00$12.00
67Covering of pedestrian signal head (632E25010)EACH16$39.68$35.00$85.00$6.00
68Signal cable, 5 conductor, no. 14 AWG (632E40500)FT1,250$3.63$3.25$2.40$5.05
69Signal cable, 7 conductor, no. 14 AWG (632E40700)FT4,180$4.04$4.00$2.65$5.76
70Signal support foundation (632E64010)EACH4$9,248.30$10,100$7,980.00$8,010.00
71Pedestal foundation (632E64020)EACH5$1,647.72$1,925.00$1,980.00$1,317.00
72Power cable, 2 conductor, no. 6 AWG (632E68200)FT50$6.74$5.00$5.75$8.20
73Service cable, 3 conductor, no. 8 AWG (632E69700)FT50$7.14$6.25$7.40$6.40
74Power service, as per plan (632E70001)EACH1$3,551.20$3,600.00$6,250.00$3,720.00
75Signal support, type TC-81.22, design 14, as per plan (632E72151)EACH1$29,247$25,800$25,265$28,730
76Combination signal support, type TC-81.22, design 4, as per plan (632E79111)EACH1$17,402$20,000$15,850$16,430
77Combination signal support, type TC-81.22, design 12, as per plan (632E79131)EACH2$20,737$25,000$19,375$19,840
78Pedestal, 10', transformer base, as per plan (632E89905)EACH5$1,100.55$1,850.00$1,285.00$1,810.00
79Removal of miscellaneous traffic signal item: vari (632E90020)EACH12$67.85$500.00$750.00$175.00
80Reuse of traffic control item: advance radar detec (632E90104)EACH1$3,960.60$950.00$5,000.00$4,040.00
81Reuse of traffic control item: pull box (632E90104)EACH1$565.80$500.00$500.00$580.00
82Reuse of vehicular signal head (632E90200)EACH6$744.05$500.00$500.00$550.00
83Reuse of pedestrian signal head (632E90202)EACH8$647.45$400.00$500.00$290.00
84Reuse of controller, as per plan (632E90213)EACH1$3,251.05$2,500.00$3,750.00$3,920.00
85Signalization, misc.: removal of signal cable (632E90400)EACH1$1,085.60$3,925.00$5,255.00$1,040.00
86Cabinet, type TS-2, as per plan (633E65511)EACH1$22,149$22,000$21,650$22,515
87Cabinet foundation, as per plan (633E67101)EACH1$3,831.80$4,500.00$2,000.00$3,325.00
88Uninterruptible power supply (UPS), as per plan (633E74001)EACH1$10,704$10,000$10,890$11,785
89Atc controller, as per plan (809E69123)EACH1$5,912.15$5,850.00$5,650.00$5,790.00
90Spread spectrum radio, as per plan (815E30001)EACH2$4,535.60$4,500.00$3,950.00$4,640.00
93Advance radar detection, as per plan (809E69001)EACH4$10,840$9,500.00$8,550.00$12,000
94Stop line radar detection, as per plan (809E69101)EACH4$10,495$9,175.00$8,250.00$11,660
95Traffic compacted surface, type A or B (410E12000)CY12$230.00$200.00$200.00$180.00
96Traffic compacted surface, type C (410E13000)CY12$258.75$180.00$200.00$198.00
97Asphalt concrete for maintaining traffic (614E13000)CY12$920.00$350.00$425.00$510.00
98Work zone lane line, class I, 6" (614E20010)MI0.02$28,750$25,000$25,000$30,000
99Work zone center line, class I (614E21000)MI0.02$28,750$25,000$25,000$30,000
100Work zone edge line, class I, 6" (614E22010)MI0.04$28,750$25,000$25,000$30,000
101Work zone channelizing line, class I, 12" (614E23010)FT357$1.15$1.00$1.00$1.20
102Work zone stop line, class I (614E26000)FT292$8.05$7.00$7.00$8.40
103Work zone crosswalk line, class I, 12" (614E27010)FT207$9.20$8.00$8.00$9.60
104Work zone arrow, class I (614E30000)EACH2$115.00$100.00$100.00$120.00
105Premium for contract performance bond and for payment bond (103E05000)LS1$5,635.00$5,800.00$6,085.80$20,501
106Maintaining traffic (614E11000)LS1$51,198$70,000$100,000$114,270
107Construction layout stakes and surveying, as per plan (623E10001)LS1$7,346.20$9,900.00$28,500$10,320
108Mobilization (624E10000)LS1$16,928$40,000$60,000$20,000
200Erosion control (832E30000)EACH4,000$1.00$1.00$1.00$1.00
ODOT contract 260180: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way