ODOT contract 260180 bid tabulation
MOT-CR 74-08.40 (SIGNALIZATION). Let by Ohio DOT on April 9, 2026, MOT. 4 bids received; low bid $818,666 by Capital Electric Line Builders Inc, +38% against the engineer's estimate of $594,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 107
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Capital Electric Line Builders Inc | $818,666 | Low | +38% |
| 2 | Complete General Construction Company | $840,307 | +3.0% | +41% |
| 3 | Bansal Construction Inc | $868,996 | +6.0% | +46% |
| 4 | Perram Electric Inc | $928,788 | +13% | +56% |
Engineer's estimate: $594,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital Electric Line Builders Inc | 2. Complete General Construction Company | 3. Bansal Construction Inc | 4. Perram Electric Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $115.00 | $2,600.00 | $2,030.00 | $2,435.00 |
| 2 | Pavement removed (202E23000) | SY | 91 | $143.75 | $65.00 | $125.00 | $116.75 |
| 3 | Walk removed (202E30000) | SF | 614 | $5.75 | $9.00 | $6.25 | $7.50 |
| 4 | Concrete median removed (202E30600) | SY | 23 | $62.10 | $88.00 | $42.00 | $50.60 |
| 5 | Curb removed (202E32000) | FT | 116 | $23.00 | $25.00 | $25.00 | $30.00 |
| 6 | Excavation (203E10000) | CY | 63 | $57.50 | $230.00 | $65.00 | $78.00 |
| 7 | Embankment (203E20000) | CY | 12 | $57.50 | $38.00 | $90.00 | $108.00 |
| 8 | Subgrade compaction (204E10000) | SY | 86 | $11.50 | $7.00 | $10.00 | $12.00 |
| 9 | 4" concrete walk (608E10000) | SF | 1,100 | $14.38 | $19.00 | $8.50 | $10.20 |
| 10 | 8" concrete walk (608E15000) | SF | 143 | $23.00 | $22.00 | $15.00 | $18.00 |
| 11 | Curb ramp (608E52000) | SF | 1,071 | $25.30 | $22.00 | $37.00 | $44.40 |
| 12 | Detectable warning (608E53020) | SF | 100 | $51.75 | $75.00 | $35.00 | $42.00 |
| 13 | Soil analysis test (659E00100) | EACH | 2 | $115.00 | $350.00 | $200.00 | $300.00 |
| 14 | Topsoil (659E00300) | CY | 52 | $74.75 | $120.00 | $115.00 | $138.00 |
| 15 | Seeding and mulching, class 1 (659E00500) | SY | 468 | $3.45 | $8.50 | $5.00 | $7.20 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.07 | $1,150.00 | $850.00 | $1,500.00 | $910.00 |
| 17 | Lime (659E31000) | ACRE | 0.10 | $1,150.00 | $45.00 | $200.00 | $1,320.00 |
| 18 | Water (659E35000) | MGAL | 3 | $11.50 | $1.00 | $1.00 | $120.00 |
| 19 | Manhole adjusted to grade (611E99654) | EACH | 1 | $3,450.00 | $1,600.00 | $1,100.00 | $1,320.00 |
| 20 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 1,718 | $23.00 | $20.00 | $20.00 | $24.00 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 12 | $1,667.50 | $1,450.00 | $1,450.00 | $1,740.00 |
| 22 | Aggregate base (304E20000) | CY | 12 | $724.50 | $175.21 | $630.00 | $755.00 |
| 23 | Non-tracking tack coat (407E20000) | GAL | 145 | $5.75 | $5.00 | $5.00 | $6.00 |
| 24 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 77 | $954.50 | $830.00 | $830.00 | $996.00 |
| 25 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 30 | $207.00 | $125.00 | $230.00 | $162.00 |
| 26 | 6" concrete traffic island (609E54000) | SY | 1 | $1,035.00 | $1,375.00 | $1,150.00 | $1,380.00 |
| 27 | Valve box adjusted to grade (638E10800) | EACH | 2 | $2,070.00 | $475.00 | $230.00 | $275.00 |
| 28 | Ground mounted support, no. 3 post (630E03100) | FT | 84.50 | $18.65 | $20.00 | $16.22 | $27.60 |
| 29 | Sign hanger assembly, mast arm, as per plan (630E79101) | EACH | 24 | $464.65 | $625.00 | $404.04 | $166.00 |
| 30 | Sign, flat sheet (630E80100) | SF | 151 | $21.85 | $30.00 | $18.93 | $35.60 |
| 31 | Sign, street name, as per plan (630E80511) | EACH | 8 | $364.69 | $740.00 | $317.12 | $517.00 |
| 32 | Removal of ground mounted sign and storage (630E85000) | EACH | 5 | $19.58 | $45.00 | $17.03 | $130.00 |
| 33 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $78.97 | $70.00 | $68.67 | $440.00 |
| 34 | Removal of ground mounted post support and storage (630E86006) | EACH | 4 | $26.11 | $55.00 | $22.70 | $130.00 |
| 35 | Edge line, 6" (644E00104) | MI | 0.06 | $5,865.00 | $5,100.00 | $5,100.00 | $6,120.00 |
| 36 | Lane line, 6" (644E00204) | MI | 0.02 | $4,600.00 | $4,000.00 | $4,000.00 | $4,800.00 |
| 37 | Center line (644E00300) | MI | 0.05 | $8,050.00 | $7,000.00 | $7,000.00 | $8,400.00 |
| 38 | Channelizing line, 12" (644E00404) | FT | 488 | $2.88 | $2.50 | $2.50 | $3.00 |
| 39 | Stop line (644E00500) | FT | 154 | $9.20 | $8.00 | $8.00 | $9.60 |
| 40 | Crosswalk line, 24" (644E00630) | FT | 220 | $9.20 | $8.00 | $8.00 | $9.60 |
| 41 | Chevron marking (644E00720) | FT | 177 | $9.20 | $8.00 | $8.00 | $9.60 |
| 42 | Lane arrow (644E01300) | EACH | 5 | $161.00 | $140.00 | $140.00 | $168.00 |
| 43 | Removal of pavement marking (644E30000) | FT | 250 | $2.30 | $2.00 | $2.00 | $2.40 |
| 44 | Stop line (646E10400) | FT | 15 | $11.50 | $10.00 | $10.00 | $12.00 |
| 45 | Crosswalk line, 24" (646E10520) | FT | 45 | $23.00 | $20.00 | $20.00 | $24.00 |
| 46 | Connection, fused pull apart (625E00450) | EACH | 4 | $120.18 | $160.00 | $125.00 | $210.00 |
| 47 | Connection, unfused pull apart (625E00460) | EACH | 4 | $120.18 | $140.00 | $125.00 | $200.00 |
| 48 | Bracket arm, 20', as per plan (625E18401) | EACH | 3 | $1,599.65 | $2,850.00 | $1,775.00 | $1,745.00 |
| 49 | Bracket arm, 25', as per plan (625E18501) | EACH | 1 | $1,892.90 | $2,850.00 | $2,125.00 | $2,050.00 |
| 50 | No. 8 AWG 600 volt distribution cable (625E23304) | FT | 1,250 | $3.57 | $3.00 | $2.50 | $2.62 |
| 51 | No. 10 AWG pole and bracket cable (625E23400) | FT | 750 | $2.55 | $2.50 | $2.20 | $1.68 |
| 52 | Conduit, 2", 725.04 (625E25400) | FT | 115 | $37.32 | $31.00 | $18.50 | $32.25 |
| 53 | Conduit, 3", 725.04 (625E25500) | FT | 45 | $56.25 | $40.00 | $35.00 | $52.60 |
| 54 | Conduit, jacked or drilled, 725.051, 4" (625E25906) | FT | 266 | $70.31 | $55.00 | $85.00 | $86.95 |
| 55 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 4 | $488.75 | $375.00 | $330.00 | $500.00 |
| 56 | Trench (625E29000) | FT | 149 | $60.44 | $12.00 | $16.25 | $20.95 |
| 57 | Pull box, 725.08, 18" (625E30700) | EACH | 3 | $1,660.60 | $1,650.00 | $1,055.00 | $2,100.00 |
| 58 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,775.60 | $1,900.00 | $1,310.00 | $2,415.00 |
| 59 | Ground rod (625E32000) | EACH | 10 | $365.70 | $350.00 | $490.00 | $415.00 |
| 60 | Underground warning marking tape (625E36010) | FT | 149 | $1.93 | $1.00 | $1.75 | $1.60 |
| 61 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 12 | $1,214.40 | $1,100.00 | $1,360.00 | $1,287.00 |
| 62 | Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064) | EACH | 6 | $1,541.00 | $1,400.00 | $1,690.00 | $1,545.00 |
| 63 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 8 | $793.50 | $900.00 | $725.00 | $730.00 |
| 64 | Accessible pedestrian pushbutton, as per plan (632E20751) | EACH | 12 | $1,706.60 | $1,600.00 | $1,435.00 | $1,730.00 |
| 65 | Accessible pedestrian pushbutton, as per plan (632E20751) | EACH | 4 | $1,273.05 | $1,200.00 | $1,000.00 | $1,275.00 |
| 66 | Covering of vehicular signal head (632E25000) | EACH | 24 | $39.68 | $40.00 | $85.00 | $12.00 |
| 67 | Covering of pedestrian signal head (632E25010) | EACH | 16 | $39.68 | $35.00 | $85.00 | $6.00 |
| 68 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,250 | $3.63 | $3.25 | $2.40 | $5.05 |
| 69 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 4,180 | $4.04 | $4.00 | $2.65 | $5.76 |
| 70 | Signal support foundation (632E64010) | EACH | 4 | $9,248.30 | $10,100 | $7,980.00 | $8,010.00 |
| 71 | Pedestal foundation (632E64020) | EACH | 5 | $1,647.72 | $1,925.00 | $1,980.00 | $1,317.00 |
| 72 | Power cable, 2 conductor, no. 6 AWG (632E68200) | FT | 50 | $6.74 | $5.00 | $5.75 | $8.20 |
| 73 | Service cable, 3 conductor, no. 8 AWG (632E69700) | FT | 50 | $7.14 | $6.25 | $7.40 | $6.40 |
| 74 | Power service, as per plan (632E70001) | EACH | 1 | $3,551.20 | $3,600.00 | $6,250.00 | $3,720.00 |
| 75 | Signal support, type TC-81.22, design 14, as per plan (632E72151) | EACH | 1 | $29,247 | $25,800 | $25,265 | $28,730 |
| 76 | Combination signal support, type TC-81.22, design 4, as per plan (632E79111) | EACH | 1 | $17,402 | $20,000 | $15,850 | $16,430 |
| 77 | Combination signal support, type TC-81.22, design 12, as per plan (632E79131) | EACH | 2 | $20,737 | $25,000 | $19,375 | $19,840 |
| 78 | Pedestal, 10', transformer base, as per plan (632E89905) | EACH | 5 | $1,100.55 | $1,850.00 | $1,285.00 | $1,810.00 |
| 79 | Removal of miscellaneous traffic signal item: vari (632E90020) | EACH | 12 | $67.85 | $500.00 | $750.00 | $175.00 |
| 80 | Reuse of traffic control item: advance radar detec (632E90104) | EACH | 1 | $3,960.60 | $950.00 | $5,000.00 | $4,040.00 |
| 81 | Reuse of traffic control item: pull box (632E90104) | EACH | 1 | $565.80 | $500.00 | $500.00 | $580.00 |
| 82 | Reuse of vehicular signal head (632E90200) | EACH | 6 | $744.05 | $500.00 | $500.00 | $550.00 |
| 83 | Reuse of pedestrian signal head (632E90202) | EACH | 8 | $647.45 | $400.00 | $500.00 | $290.00 |
| 84 | Reuse of controller, as per plan (632E90213) | EACH | 1 | $3,251.05 | $2,500.00 | $3,750.00 | $3,920.00 |
| 85 | Signalization, misc.: removal of signal cable (632E90400) | EACH | 1 | $1,085.60 | $3,925.00 | $5,255.00 | $1,040.00 |
| 86 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $22,149 | $22,000 | $21,650 | $22,515 |
| 87 | Cabinet foundation, as per plan (633E67101) | EACH | 1 | $3,831.80 | $4,500.00 | $2,000.00 | $3,325.00 |
| 88 | Uninterruptible power supply (UPS), as per plan (633E74001) | EACH | 1 | $10,704 | $10,000 | $10,890 | $11,785 |
| 89 | Atc controller, as per plan (809E69123) | EACH | 1 | $5,912.15 | $5,850.00 | $5,650.00 | $5,790.00 |
| 90 | Spread spectrum radio, as per plan (815E30001) | EACH | 2 | $4,535.60 | $4,500.00 | $3,950.00 | $4,640.00 |
| 93 | Advance radar detection, as per plan (809E69001) | EACH | 4 | $10,840 | $9,500.00 | $8,550.00 | $12,000 |
| 94 | Stop line radar detection, as per plan (809E69101) | EACH | 4 | $10,495 | $9,175.00 | $8,250.00 | $11,660 |
| 95 | Traffic compacted surface, type A or B (410E12000) | CY | 12 | $230.00 | $200.00 | $200.00 | $180.00 |
| 96 | Traffic compacted surface, type C (410E13000) | CY | 12 | $258.75 | $180.00 | $200.00 | $198.00 |
| 97 | Asphalt concrete for maintaining traffic (614E13000) | CY | 12 | $920.00 | $350.00 | $425.00 | $510.00 |
| 98 | Work zone lane line, class I, 6" (614E20010) | MI | 0.02 | $28,750 | $25,000 | $25,000 | $30,000 |
| 99 | Work zone center line, class I (614E21000) | MI | 0.02 | $28,750 | $25,000 | $25,000 | $30,000 |
| 100 | Work zone edge line, class I, 6" (614E22010) | MI | 0.04 | $28,750 | $25,000 | $25,000 | $30,000 |
| 101 | Work zone channelizing line, class I, 12" (614E23010) | FT | 357 | $1.15 | $1.00 | $1.00 | $1.20 |
| 102 | Work zone stop line, class I (614E26000) | FT | 292 | $8.05 | $7.00 | $7.00 | $8.40 |
| 103 | Work zone crosswalk line, class I, 12" (614E27010) | FT | 207 | $9.20 | $8.00 | $8.00 | $9.60 |
| 104 | Work zone arrow, class I (614E30000) | EACH | 2 | $115.00 | $100.00 | $100.00 | $120.00 |
| 105 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,635.00 | $5,800.00 | $6,085.80 | $20,501 |
| 106 | Maintaining traffic (614E11000) | LS | 1 | $51,198 | $70,000 | $100,000 | $114,270 |
| 107 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $7,346.20 | $9,900.00 | $28,500 | $10,320 |
| 108 | Mobilization (624E10000) | LS | 1 | $16,928 | $40,000 | $60,000 | $20,000 |
| 200 | Erosion control (832E30000) | EACH | 4,000 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.