ODOT contract 260213 bid tabulation
ROS-SR 180-02.11 (CULVERT REPLACEMENT). Let by Ohio DOT on April 23, 2026, ROS. 6 bids received; low bid $1,188,876 by Fillmore Construction, -13% against the engineer's estimate of $1,360,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 58
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $1,188,876 | Low | -13% |
| 2 | R C Construction Company and Son Inc | $1,242,899 | +5.0% | -9.0% |
| 3 | Axis Civil Construction LLC | $1,244,036 | +5.0% | -9.0% |
| 4 | DJX Construction Company LLC | $1,245,129 | +5.0% | -8.0% |
| 5 | D G M Inc | $1,401,066 | +18% | +3.0% |
| 6 | Complete General Construction Company | $1,518,393 | +28% | +12% |
Engineer's estimate: $1,360,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. R C Construction Company and Son Inc | 3. Axis Civil Construction LLC | 4. DJX Construction Company LLC | 5. D G M Inc | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $15,000 | $15,000 | $7,074.15 | $50,000 | $35,000 |
| 2 | Pavement removed (202E23000) | SY | 1,808 | $10.00 | $20.00 | $10.00 | $19.23 | $12.00 | $20.00 |
| 3 | Guardrail removed (202E38000) | FT | 300 | $10.00 | $5.00 | $8.50 | $7.21 | $1.00 | $4.60 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 4 | $500.00 | $500.00 | $500.00 | $541.09 | $400.00 | $458.00 |
| 5 | Excavation (203E10000) | CY | 406 | $30.00 | $10.00 | $23.00 | $21.14 | $30.00 | $36.00 |
| 6 | Embankment (203E20000) | CY | 10,985 | $34.00 | $28.00 | $24.00 | $26.94 | $27.00 | $34.00 |
| 7 | Subgrade compaction (204E10000) | SY | 4,040 | $5.00 | $2.00 | $2.50 | $2.15 | $2.50 | $3.50 |
| 8 | Excavation of subgrade (204E13000) | CY | 669 | $30.00 | $10.00 | $36.00 | $32.26 | $25.00 | $38.00 |
| 9 | Granular material, type B (204E30010) | CY | 649 | $68.00 | $90.00 | $96.00 | $102.73 | $100.00 | $136.00 |
| 10 | Granular material, type C (204E30020) | CY | 104 | $66.00 | $90.00 | $86.00 | $101.68 | $120.00 | $88.00 |
| 11 | Proof rolling (204E45000) | HR | 1 | $150.00 | $100.00 | $2,000.00 | $534.95 | $100.00 | $350.00 |
| 12 | Geotextile fabric (204E50000) | SY | 1,371 | $2.00 | $10.00 | $1.80 | $2.74 | $2.50 | $2.50 |
| 13 | Full depth pavement sawing (252E01500) | FT | 47 | $20.00 | $50.00 | $4.00 | $22.00 | $20.00 | $2.00 |
| 14 | Reference monument, type A (623E40500) | EACH | 6 | $1,500.00 | $850.00 | $850.00 | $983.13 | $600.00 | $1,500.00 |
| 15 | Special - mailbox removed and reset (690E50350) | EACH | 3 | $400.00 | $200.00 | $220.00 | $226.91 | $250.00 | $360.00 |
| 16 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $25,000 | $20,000 | $54,000 | $49,350 | $20,000 | $3,000.00 |
| 17 | Topsoil (659E00300) | CY | 125 | $60.00 | $35.00 | $120.00 | $68.24 | $25.00 | $80.00 |
| 18 | Seeding and mulching (659E10000) | SY | 5,231 | $1.45 | $5.00 | $0.80 | $2.40 | $2.00 | $0.80 |
| 19 | Repair seeding and mulching (659E14000) | SY | 262 | $2.00 | $0.20 | $0.80 | $1.00 | $0.05 | $0.80 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.71 | $1,400.00 | $2,000.00 | $1,250.00 | $1,500.00 | $1,500.00 | $1,250.00 |
| 21 | Lime (659E31000) | ACRE | 1.08 | $450.00 | $1,800.00 | $150.00 | $200.00 | $300.00 | $150.00 |
| 22 | Water (659E35000) | MGAL | 28.20 | $10.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Slope erosion protection (670E00500) | SY | 1,122 | $2.00 | $10.00 | $2.50 | $2.35 | $3.00 | $2.50 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $12,500 | $1,500.00 | $7,500.00 | $2,000.00 | $1,500.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,500.00 | $20,000 | $4,800.00 | $5,300.00 | $8,000.00 | $4,800.00 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,000 | $20,000 | $10,000 | $16,030 | $8,000.00 | $7,695.09 |
| 27 | Erosion control (832E30000) | EACH | 24,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | Aggregate drains (605E31100) | FT | 363 | $15.00 | $25.00 | $20.00 | $9.91 | $35.00 | $35.00 |
| 29 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 322 | $10.00 | $30.00 | $8.50 | $14.96 | $9.00 | $7.50 |
| 30 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 344 | $194.00 | $215.00 | $210.00 | $215.00 | $220.00 | $210.00 |
| 31 | Aggregate base (304E20000) | CY | 318 | $64.00 | $140.00 | $99.00 | $95.32 | $110.00 | $105.00 |
| 32 | Tack coat (407E10000) | GAL | 271 | $3.00 | $5.00 | $4.25 | $4.25 | $4.25 | $3.50 |
| 33 | Stabilized crushed aggregate (411E10000) | CY | 190 | $224.00 | $140.00 | $180.00 | $125.06 | $125.00 | $150.00 |
| 34 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 187 | $216.00 | $275.00 | $250.00 | $250.00 | $250.00 | $275.00 |
| 35 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 5 | $270.00 | $600.00 | $365.00 | $365.00 | $375.00 | $600.00 |
| 36 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $280.00 | $600.00 | $500.00 | $500.00 | $525.00 | $650.00 |
| 37 | RPM (621E00100) | EACH | 10 | $382.50 | $450.00 | $295.00 | $290.00 | $300.00 | $290.00 |
| 38 | Raised pavement marker removed (621E54000) | EACH | 10 | $20.00 | $100.00 | $35.00 | $2.71 | $1.00 | $45.00 |
| 39 | Edge line, 6", type 1 (642E00104) | MI | 0.30 | $6,358.00 | $4,500.00 | $2,850.00 | $2,200.00 | $3,500.00 | $2,100.00 |
| 40 | Center line, type 1 (642E00300) | MI | 0.15 | $12,717 | $4,500.00 | $5,325.00 | $2,200.00 | $6,000.00 | $3,800.00 |
| 41 | Pavement repair (253E02000) | CY | 30 | $400.00 | $25.00 | $430.00 | $500.00 | $250.00 | $750.00 |
| 42 | Detour signing (614E12420) | LS | 1 | $6,985.00 | $35,000 | $7,000.00 | $6,716.11 | $6,000.00 | $16,000 |
| 43 | Asphalt concrete for maintaining traffic (614E13000) | CY | 30 | $300.00 | $25.00 | $405.00 | $500.00 | $150.00 | $450.00 |
| 44 | Water (616E10000) | MGAL | 34 | $10.00 | $1.00 | $1.00 | $32.12 | $1.00 | $550.00 |
| 45 | Structure removed (202E11000) | LS | 1 | $10,000 | $15,000 | $20,000 | $17,614 | $45,000 | $60,000 |
| 46 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,000 | $12,500 | $13,500 | $1,228.55 | $21,500 | $15,000 |
| 47 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $25,000 | $15,000 | $15,000 | $7.41 | $24,000 | $35,000 |
| 48 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 20 | $50.00 | $100.00 | $48.00 | $31.60 | $60.00 | $50.00 |
| 49 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 102 | $120.00 | $175.00 | $130.00 | $151.36 | $135.00 | $120.00 |
| 50 | Concrete masonry (602E20000) | CY | 17.90 | $2,000.00 | $2,000.00 | $2,200.00 | $1,648.55 | $1,400.00 | $2,000.00 |
| 51 | 120" conduit, type A, as per plan (see sheet P.26 (611E34001) | FT | 154 | $1,200.00 | $1,000.00 | $1,830.00 | $1,601.69 | $2,225.00 | $1,600.00 |
| 52 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $34,000 | $12,500 | $16,432 | $25,000 | $11,500 |
| 53 | Maintaining traffic (614E11000) | LS | 1 | $25,500 | $25,000 | $15,000 | $2,500.00 | $43,500 | $12,000 |
| 54 | Field office, type A (619E16000) | MNTH | 3 | $1,000.00 | $500.00 | $2,000.00 | $4,000.00 | $750.00 | $5,150.00 |
| 55 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $25,000 | $14,000 | $10,200 | $15,000 | $34,000 |
| 56 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,000.00 | $1,200.00 | $1,200.00 | $1,250.00 | $1,000.00 | $5,000.00 |
| 57 | Post construction survey monument verification and report (623E51000) | LS | 1 | $5,000.00 | $1,200.00 | $1,200.00 | $1,250.00 | $1,000.00 | $5,000.00 |
| 58 | Mobilization (624E10000) | LS | 1 | $25,000 | $25,000 | $30,000 | $63,427 | $40,000 | $75,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.