ODOT contract 260224 bid tabulation
VIN-Tar Hollow Culvert (CULVERT REPLACEMENT). Let by Ohio DOT on April 23, 2026, VIN. 6 bids received; low bid $399,890 by D G M Inc, -12% against the engineer's estimate of $455,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $399,890 | Low | -12% |
| 2 | Axis Civil Construction LLC | $443,526 | +11% | -3.0% |
| 3 | Double Z Construction Company | $454,623 | +14% | 0.0% |
| 4 | Parker Corporation | $456,083 | +14% | 0.0% |
| 5 | R C Construction Company and Son Inc | $470,052 | +18% | +3.0% |
| 6 | Fillmore Construction | $488,980 | +22% | +7.0% |
Engineer's estimate: $455,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. Axis Civil Construction LLC | 3. Double Z Construction Company | 4. Parker Corporation | 5. R C Construction Company and Son Inc | 6. Fillmore Construction |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $12,000 | $12,500 | $3,000.00 | $19,000 | $5,500.00 | $2,500.00 |
| 2 | Pavement removed (202E23000) | SY | 378 | $6.00 | $11.50 | $16.00 | $10.00 | $20.00 | $10.00 |
| 3 | Excavation (203E10000) | CY | 2 | $100.00 | $98.00 | $75.00 | $20.00 | $25.00 | $80.00 |
| 4 | Embankment (203E20000) | CY | 178 | $35.00 | $39.00 | $75.00 | $20.00 | $50.00 | $100.00 |
| 5 | Subgrade compaction (204E10000) | SY | 504 | $6.00 | $1.50 | $7.00 | $0.50 | $2.00 | $5.00 |
| 6 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $150.00 | $100.00 | $50.00 | $25.00 | $150.00 |
| 7 | Topsoil (659E00300) | CY | 81 | $20.00 | $60.00 | $40.00 | $20.00 | $20.00 | $60.00 |
| 8 | Seeding and mulching, class 5B (659E00580) | SY | 728 | $8.00 | $4.00 | $9.00 | $1.00 | $10.00 | $8.00 |
| 9 | Repair seeding and mulching (659E14000) | SY | 36 | $0.05 | $4.00 | $3.00 | $0.25 | $0.20 | $12.00 |
| 10 | Inter-seeding (659E15000) | SY | 36 | $0.05 | $4.00 | $3.00 | $0.25 | $0.20 | $12.00 |
| 11 | Commercial fertilizer (659E20000) | TON | 0.10 | $1,500.00 | $1,250.00 | $1,500.00 | $2,500.00 | $2,000.00 | $1,400.00 |
| 12 | Lime (659E31000) | ACRE | 0.15 | $300.00 | $150.00 | $200.00 | $1,667.00 | $1,800.00 | $450.00 |
| 13 | Water (659E35000) | MGAL | 4 | $1.00 | $1.00 | $1.00 | $0.05 | $1.00 | $10.00 |
| 14 | Erosion control (832E30000) | EACH | 996 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | Aggregate drains (605E31100) | FT | 64 | $40.00 | $20.00 | $25.00 | $10.00 | $50.00 | $30.00 |
| 16 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 56 | $345.00 | $342.00 | $450.00 | $400.00 | $375.00 | $320.00 |
| 17 | Aggregate base (304E20000) | CY | 84 | $110.00 | $167.00 | $120.00 | $65.00 | $175.00 | $100.00 |
| 18 | Tack coat (407E10000) | GAL | 30 | $4.25 | $7.50 | $4.10 | $10.00 | $10.00 | $5.00 |
| 19 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 17 | $500.00 | $451.00 | $700.00 | $500.00 | $425.00 | $500.00 |
| 20 | Structure removed, as per plan (202E11001) | LS | 1 | $12,000 | $4,200.00 | $12,000 | $23,000 | $15,000 | $2,500.00 |
| 21 | Headwall removed (202E20010) | EACH | 2 | $500.00 | $1,250.00 | $5,000.00 | $1,000.00 | $1,000.00 | $3,500.00 |
| 22 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $3,000.00 | $12,000 | $6,500.00 | $100.00 | $5,000.00 | $3,500.00 |
| 23 | Unclassified excavation (503E21100) | CY | 42 | $35.00 | $140.00 | $280.00 | $25.00 | $100.00 | $200.00 |
| 24 | Epoxy coated steel reinforcement (509E10000) | LB | 5,922 | $2.00 | $2.65 | $3.00 | $1.25 | $2.50 | $4.00 |
| 25 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 31 | $950.00 | $1,250.00 | $1,200.00 | $1,296.00 | $850.00 | $1,500.00 |
| 26 | Class QC1 concrete, footing (511E46510) | CY | 66 | $650.00 | $700.00 | $470.00 | $854.00 | $850.00 | $1,000.00 |
| 27 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $2,000.00 | $1,600.00 | $2,000.00 | $650.00 | $850.00 | $3,000.00 |
| 28 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 90 | $45.00 | $30.00 | $35.00 | $12.00 | $50.00 | $50.00 |
| 29 | Type 2 waterproofing (512E33000) | SY | 155 | $18.00 | $19.00 | $25.00 | $14.00 | $35.00 | $30.00 |
| 30 | Type 3 waterproofing (512E33010) | SY | 127 | $30.00 | $59.00 | $45.00 | $18.00 | $50.00 | $50.00 |
| 31 | 1" preformed expansion joint filler (516E13600) | SF | 38 | $20.00 | $8.00 | $15.00 | $5.00 | $40.00 | $20.00 |
| 32 | Porous backfill with geotextile fabric (518E21200) | CY | 125 | $65.00 | $125.00 | $130.00 | $10.00 | $175.00 | $80.00 |
| 33 | Riprap, type D (601E11000) | SY | 28 | $303.00 | $240.00 | $275.00 | $65.00 | $350.00 | $180.00 |
| 34 | Rock channel protection, type B with filter (601E32100) | CY | 56 | $120.00 | $140.00 | $100.00 | $65.00 | $175.00 | $200.00 |
| 35 | 12' X 7' conduit, type A, 706.05 (611E95900) | FT | 71 | $2,025.00 | $2,225.00 | $2,150.00 | $2,310.00 | $2,100.00 | $2,650.00 |
| 36 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $22,000 | $3,500.00 | $4,000.00 | $21,000 | $15,000 | $3,500.00 |
| 37 | Maintaining traffic (614E11000) | LS | 1 | $9,500.00 | $7,500.00 | $4,000.00 | $20,000 | $15,000 | $5,000.00 |
| 38 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,000.00 | $7,500.00 | $6,500.00 | $20,000 | $12,500 | $5,000.00 |
| 39 | Mobilization (624E10000) | LS | 1 | $8,000.00 | $20,000 | $30,000 | $20,000 | $15,000 | $7,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.