ODOT contract 260240 bid tabulation
HUR-CR 11-02.96 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on May 7, 2026, HUR. 3 bids received; low bid $3,170,138 by Rietschlin Construction Inc, -4.7% against the engineer's estimate of $3,325,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 132
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rietschlin Construction Inc | $3,170,138 | Low | -5.0% |
| 2 | Great Lakes Demolition Company | $3,743,850 | +18% | +13% |
| 3 | Ruhlin Company | $4,537,833 | +43% | +36% |
Engineer's estimate: $3,325,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rietschlin Construction Inc | 2. Great Lakes Demolition Company | 3. Ruhlin Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,000 | $500.00 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 2,105 | $10.00 | $12.00 | $40.00 |
| 3 | Walk removed (202E30000) | SF | 4,457 | $1.25 | $3.00 | $4.00 |
| 4 | Curb removed (202E32000) | FT | 602 | $3.25 | $5.00 | $2.50 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 259 | $35.00 | $15.00 | $100.00 |
| 6 | Catch basin removed (202E58100) | EACH | 2 | $775.00 | $450.00 | $900.00 |
| 7 | Special - pipe cleanout, 24" and under (202E70110) | FT | 50 | $22.00 | $100.00 | $130.00 |
| 8 | Excavation (203E10000) | CY | 1,185 | $35.00 | $50.00 | $45.00 |
| 9 | Embankment (203E20000) | CY | 803 | $25.00 | $35.00 | $65.00 |
| 10 | Subgrade compaction (204E10000) | SY | 2,541 | $2.00 | $1.00 | $5.00 |
| 11 | Excavation of subgrade (204E13000) | CY | 500 | $32.25 | $25.00 | $45.00 |
| 12 | Granular material, type B (204E30010) | CY | 500 | $77.00 | $65.00 | $70.00 |
| 13 | Proof rolling (204E45000) | HR | 1 | $490.00 | $150.00 | $1,000.00 |
| 14 | Geotextile fabric (204E50000) | SY | 100 | $9.00 | $5.00 | $2.00 |
| 15 | 4" concrete walk (608E10000) | SF | 3,414 | $7.00 | $6.00 | $11.00 |
| 16 | 6" concrete walk, as per plan (608E13001) | SF | 78 | $126.00 | $116.00 | $150.00 |
| 17 | Curb ramp (608E52000) | SF | 688 | $16.50 | $15.00 | $20.00 |
| 18 | Walkway, misc.:concrete wheel chair ramp (608E98000) | SF | 134 | $22.00 | $25.00 | $75.00 |
| 19 | Curb, type 6 (609E26000) | FT | 953 | $23.00 | $20.00 | $40.00 |
| 20 | Monument assembly, type C (623E38500) | EACH | 3 | $2,100.00 | $1,450.00 | $1,000.00 |
| 21 | Crushed aggregate slope protection (601E20010) | CY | 55 | $190.00 | $110.00 | $125.00 |
| 22 | Soil analysis test (659E00100) | EACH | 2 | $165.00 | $100.00 | $400.00 |
| 23 | Topsoil (659E00300) | CY | 112 | $58.00 | $65.00 | $75.00 |
| 24 | Seeding and mulching (659E10000) | SY | 1,007 | $5.00 | $4.00 | $1.30 |
| 25 | Repair seeding and mulching (659E14000) | SY | 51 | $3.00 | $1.50 | $3.00 |
| 26 | Commercial fertilizer (659E20000) | TON | 0.14 | $1,300.00 | $800.00 | $1,500.00 |
| 27 | Lime (659E31000) | ACRE | 0.21 | $200.00 | $60.00 | $5.00 |
| 28 | Water (659E35000) | MGAL | 6 | $11.00 | $1.00 | $0.50 |
| 29 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,200.00 | $2,500.00 | $2,900.00 |
| 30 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $9,900.00 | $12,000 | $13,200 |
| 31 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $14,080 | $17,000 | $15,000 |
| 32 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 |
| 33 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 117 | $22.00 | $12.00 | $40.00 |
| 34 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 420 | $19.00 | $12.00 | $35.00 |
| 35 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 200 | $28.00 | $20.00 | $25.00 |
| 36 | 6" conduit, type B (611E00900) | FT | 250 | $80.00 | $40.00 | $95.00 |
| 37 | 8" conduit, type B (611E01800) | FT | 50 | $106.00 | $35.00 | $85.00 |
| 38 | 8" conduit, type B (611E01800) | FT | 25 | $190.00 | $45.00 | $135.00 |
| 39 | 8" conduit, type C (611E02000) | FT | 42 | $92.00 | $30.00 | $105.00 |
| 40 | 8" conduit, type C (611E02000) | FT | 25 | $81.00 | $40.00 | $140.00 |
| 41 | 10" conduit, type B (611E03100) | FT | 25 | $105.00 | $50.00 | $90.00 |
| 42 | 12" conduit, type B (611E04400) | FT | 264 | $92.00 | $60.00 | $150.00 |
| 43 | 12" conduit, type C (611E04600) | FT | 469 | $87.00 | $55.00 | $95.00 |
| 44 | 15" conduit, type B (611E05900) | FT | 50 | $143.00 | $70.00 | $120.00 |
| 45 | 18" conduit, type B (611E07400) | FT | 50 | $163.00 | $95.00 | $185.00 |
| 46 | Catch basin, no. 3A (611E98180) | EACH | 7 | $3,700.00 | $3,200.00 | $5,800.00 |
| 47 | Catch basin, no. 5 with B grate (611E98310) | EACH | 1 | $8,500.00 | $4,500.00 | $7,000.00 |
| 48 | Catch basin, no. 6 (611E98370) | EACH | 2 | $3,800.00 | $4,200.00 | $6,500.00 |
| 49 | Catch basin, no. 2-2B (611E98470) | EACH | 6 | $2,300.00 | $2,500.00 | $3,500.00 |
| 50 | Inlet, side ditch (611E98700) | EACH | 2 | $1,725.00 | $3,500.00 | $4,100.00 |
| 51 | Manhole, no. 3 (611E99574) | EACH | 4 | $5,300.00 | $4,400.00 | $4,500.00 |
| 52 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $2,900.00 | $2,500.00 | $2,500.00 |
| 53 | Special - miscellaneous metal (611E99820) | LB | 1,000 | $3.50 | $8.50 | $4.00 |
| 54 | Pavement planing, asphalt concrete (1-1/4") (254E01000) | SY | 207 | $44.00 | $50.00 | $35.70 |
| 55 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 444 | $216.00 | $400.00 | $241.00 |
| 56 | Aggregate base (304E20000) | CY | 466 | $102.00 | $75.00 | $110.00 |
| 57 | Tack coat (407E10000) | GAL | 261 | $3.00 | $4.00 | $2.75 |
| 58 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 80 | $324.00 | $600.00 | $409.00 |
| 59 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 100 | $292.00 | $400.00 | $335.00 |
| 60 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 13 | $117.00 | $70.00 | $295.00 |
| 61 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 31 | $103.00 | $80.00 | $150.00 |
| 64 | Fire hydrant extended and adjusted to grade (638E10300) | EACH | 2 | $4,150.00 | $3,250.00 | $3,000.00 |
| 65 | Valve box adjusted to grade (638E10800) | EACH | 6 | $700.00 | $1,250.00 | $1,000.00 |
| 67 | Ground mounted support, no. 2 post (630E02100) | FT | 66 | $24.00 | $14.00 | $23.25 |
| 68 | Ground mounted support, no. 3 post (630E03100) | FT | 70.50 | $26.00 | $14.00 | $24.75 |
| 69 | Sign post reflector (630E08600) | EACH | 3 | $50.00 | $45.00 | $59.27 |
| 70 | Sign, flat sheet (630E80100) | SF | 66.10 | $30.00 | $25.00 | $26.25 |
| 71 | Sign, street name (630E80510) | EACH | 4 | $220.00 | $150.00 | $234.64 |
| 72 | Removal of ground mounted sign and disposal (630E84900) | EACH | 18 | $11.00 | $25.00 | $17.14 |
| 73 | Removal of ground mounted post support and disposal (630E86002) | EACH | 13 | $17.00 | $25.00 | $22.85 |
| 74 | Center line (644E00300) | MI | 0.13 | $5,500.00 | $11,000 | $5,000.00 |
| 75 | Stop line (644E00500) | FT | 39 | $10.00 | $11.00 | $9.00 |
| 76 | Crosswalk line, 12" (644E00620) | FT | 293 | $8.00 | $4.00 | $7.00 |
| 77 | Crosswalk line, 24" (644E00630) | FT | 204 | $10.00 | $11.00 | $9.00 |
| 78 | Parking lot stall marking (644E01200) | FT | 332 | $3.00 | $3.00 | $2.50 |
| 79 | Handicap symbol marking (644E01600) | EACH | 3 | $110.00 | $300.00 | $100.00 |
| 80 | Traffic compacted surface, type A or B (410E12000) | CY | 10 | $78.00 | $80.00 | $100.00 |
| 81 | Detour signing (614E12420) | LS | 1 | $6,200.00 | $8,500.00 | $5,569.57 |
| 82 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $215.00 | $300.00 | $500.00 |
| 83 | Water (616E10000) | MGAL | 9 | $11.00 | $1.00 | $140.00 |
| 84 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 162 | $32.00 | $40.00 | $42.00 |
| 85 | 1" preformed expansion joint filler (516E13600) | SF | 69 | $13.00 | $25.00 | $25.00 |
| 86 | Mechanically stabilized earth wall (840E20000) | SF | 3,678 | $62.25 | $185.00 | $70.00 |
| 87 | Wall excavation (840E21000) | CY | 1,310 | $42.25 | $40.00 | $225.00 |
| 88 | Foundation preparation (840E22000) | SY | 424 | $53.00 | $60.00 | $50.00 |
| 89 | Select granular backfill (840E23000) | CY | 1,271 | $109.00 | $85.00 | $90.00 |
| 90 | 6" drainage pipe, perforated (840E25010) | FT | 315 | $15.00 | $12.00 | $20.00 |
| 91 | 6" drainage pipe, non-perforated (840E25020) | FT | 84 | $29.00 | $12.00 | $24.00 |
| 92 | Concrete coping (840E26000) | FT | 364 | $215.00 | $100.00 | $185.00 |
| 93 | On-site assistance (840E27000) | DAY | 5 | $550.00 | $3,500.00 | $500.00 |
| 94 | SGB inspection and compaction testing (840E28000) | LS | 1 | $13,000 | $15,000 | $25,000 |
| 95 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $70,000 | $125,000 | $70,000 |
| 96 | Wearing course removed (202E23500) | SY | 235 | $25.00 | $35.00 | $35.00 |
| 97 | Granular material, type B (203E35110) | CY | 174 | $91.00 | $75.00 | $95.00 |
| 98 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $59,000 | $2,500.00 | $260,000 |
| 99 | Unclassified excavation (503E21300) | LS | 1 | $25,000 | $12,000 | $75,000 |
| 100 | Steel sheet piling left in place, as per plan (504E11101) | SF | 1,800 | $35.00 | $100.00 | $55.00 |
| 101 | Pile driving equipment mobilization (505E11100) | LS | 1 | $42,000 | $25,000 | $45,000 |
| 102 | Steel piles HP10X42, furnished (507E00100) | FT | 3,840 | $46.00 | $50.00 | $60.00 |
| 103 | Steel piles HP10X42, driven (507E00150) | FT | 3,600 | $17.00 | $5.00 | $17.50 |
| 104 | Galvanized steel reinforcement (509E26000) | LB | 80,611 | $2.10 | $2.60 | $2.49 |
| 105 | Class QC2 concrete with QC/QA, superstructure (511E32212) | CY | 175 | $1,170.00 | $1,100.00 | $1,500.00 |
| 106 | Class QC1 concrete with QC/QA, pier above footings (511E40512) | CY | 173 | $700.00 | $900.00 | $1,250.00 |
| 107 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 83 | $640.00 | $800.00 | $700.00 |
| 108 | Class QC1 concrete, footing (511E46510) | CY | 59 | $560.00 | $850.00 | $700.00 |
| 109 | Class QC2 concrete, sidewalk, as per plan (511E51511) | CY | 53 | $810.00 | $400.00 | $775.00 |
| 110 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,010 | $32.00 | $20.00 | $42.00 |
| 111 | 1" preformed expansion joint filler (516E13600) | SF | 25 | $11.00 | $20.00 | $16.00 |
| 112 | 2" preformed expansion joint filler (516E13900) | SF | 359 | $9.00 | $25.00 | $16.00 |
| 113 | Semi-integral abutment expansion joint seal (516E14020) | FT | 93 | $40.00 | $40.00 | $40.00 |
| 114 | Elastomeric bearing with internal laminates only (neoprene) (516E43200) | EACH | 18 | $430.00 | $225.00 | $300.00 |
| 115 | Railing (concrete parapet with twin steel tube railing) (517E75120) | FT | 355 | $345.00 | $150.00 | $350.00 |
| 116 | Porous backfill with geotextile fabric (518E21200) | CY | 27 | $140.00 | $90.00 | $150.00 |
| 117 | 6" perforated corrugated plastic pipe (518E40000) | FT | 97 | $16.00 | $15.00 | $22.00 |
| 118 | Reinforced concrete approach slabs (T=17"), as per plan (526E30001) | SY | 284 | $445.00 | $150.00 | $525.00 |
| 119 | Type A installation (526E90010) | FT | 79 | $195.00 | $350.00 | $200.00 |
| 120 | Special - structural survey and monitoring of vibration (530E14000) | LS | 1 | $11,000 | $15,000 | $25,000 |
| 121 | Structure grounding system (625E33000) | EACH | 1 | $22,000 | $5,000.00 | $3,500.00 |
| 122 | Polymer modified asphalt expansion joint system (846E00110) | CF | 27 | $740.00 | $650.00 | $550.00 |
| 123 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $15,000 | $9,000.00 | $10,000 |
| 124 | Premium for contract performance bond, payment bond and maintenance bond (103E06000) | LS | 1 | $25,000 | $35,000 | $20,000 |
| 125 | Maintaining traffic (614E11000) | LS | 1 | $3,000.00 | $25,000 | $25,000 |
| 126 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $45,000 | $60,000 |
| 127 | Mobilization (624E10000) | LS | 1 | $95,000 | $214,303 | $228,000 |
| 200 | 12" conduit, type B, as per plan (611E04401) | FT | 32 | $210.00 | $65.00 | $210.00 |
| 201 | 6" water main ductile iron pipe ansi class 53, push-on joints and fittings (638E00604) | FT | 15 | $154.00 | $135.00 | $355.00 |
| 202 | 8" water main ductile iron pipe ansi class 53, push-on joints and fittings (638E01204) | FT | 233 | $210.00 | $150.00 | $370.00 |
| 203 | 1" copper service branch (638E04900) | FT | 60 | $100.00 | $90.00 | $220.00 |
| 204 | 2" copper service branch (638E05100) | FT | 80 | $155.00 | $100.00 | $200.00 |
| 205 | 20" steel pipe encasement, bored or jacked (638E07304) | FT | 25 | $2,950.00 | $3,850.00 | $4,500.00 |
| 206 | 8" gate valve and valve box (638E07900) | EACH | 1 | $4,700.00 | $850.00 | $4,000.00 |
| 207 | Meter and chamber removed and reset, as per plan (638E11101) | EACH | 5 | $1,100.00 | $1,850.00 | $390.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.