DEF-SR 66-04.24 (SLIDE REPAIR). Let by Ohio DOT on May 21, 2026, DEF. 6 bids received; low bid $1,558,998 by Kokosing Construction Company Inc, +6.6% against the engineer's estimate of $1,463,000.
- Owner
- Ohio DOT
- Letting
- 21 MAY 2026
- Pay items
- 53
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $1,558,998 | Low | +7.0% |
| 2 | Geddis Paving & Excavating Inc | $1,501,500 | -4.0% | +3.0% |
| 3 | Advanced Excavating & Demolition LLC | $1,597,339 | +2.0% | +9.0% |
| 4 | Alan Stone Co Inc | $1,699,606 | +9.0% | +16% |
| 5 | Miller Contracting Group Inc | $1,753,227 | +12% | +20% |
| 6 | Beaver Excavating Company | $2,014,588 | +29% | +38% |
Engineer's estimate: $1,463,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. Geddis Paving & Excavating Inc | 3. Advanced Excavating & Demolition LLC | 4. Alan Stone Co Inc | 5. Miller Contracting Group Inc | 6. Beaver Excavating Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $1,750.00 | $15,000 | $8,000.00 | $2,500.00 | $8,000.00 |
| 2 | Pavement removed (202E23000) | SY | 295 | $20.00 | $40.00 | $30.00 | $20.00 | $20.00 | $40.00 |
| 3 | Curb removed (202E32000) | FT | 772 | $5.25 | $3.00 | $7.50 | $9.00 | $3.00 | $4.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 109 | $15.00 | $25.00 | $25.00 | $15.00 | $19.00 | $45.00 |
| 5 | Guardrail removed (202E38000) | FT | 782 | $2.50 | $5.00 | $2.50 | $3.00 | $3.00 | $2.00 |
| 6 | Manhole removed (202E58000) | EACH | 2 | $600.00 | $250.00 | $1,350.00 | $480.00 | $850.00 | $650.00 |
| 7 | Catch basin removed (202E58100) | EACH | 2 | $600.00 | $250.00 | $1,000.00 | $480.00 | $600.00 | $650.00 |
| 8 | Excavation (203E10000) | CY | 92 | $20.00 | $12.00 | $31.00 | $30.00 | $9.50 | $40.00 |
| 9 | Embankment (203E20000) | CY | 84 | $55.00 | $12.00 | $32.00 | $35.00 | $52.50 | $40.00 |
| 10 | Subgrade compaction (204E10000) | SY | 397 | $2.50 | $1.00 | $3.00 | $8.00 | $2.75 | $4.00 |
| 11 | Reshaping under guardrail (209E15000) | STA | 2 | $65.00 | $300.00 | $150.00 | $1,000.00 | $145.00 | $80.00 |
| 12 | Guardrail, type MGS, as per plan (606E15051) | FT | 725 | $24.75 | $27.00 | $26.00 | $30.00 | $30.00 | $26.00 |
| 13 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $1,450.00 | $1,450.00 | $1,500.00 | $1,800.00 | $3,400.00 | $2,925.00 |
| 14 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $500.00 | $3,480.00 | $3,300.00 | $3,300.00 | $3,000.00 | $1,800.00 |
| 15 | Post construction survey monument verification and report (623E51000) | LS | 1 | $500.00 | $3,480.00 | $3,300.00 | $3,300.00 | $3,000.00 | $1,800.00 |
| 16 | Rock channel protection, type C with filter (601E32200) | CY | 21 | $220.00 | $180.00 | $220.00 | $240.00 | $173.00 | $240.00 |
| 17 | Rock channel protection, with grout, type C (601E34400) | CY | 192 | $140.00 | $260.00 | $265.00 | $270.00 | $147.00 | $290.00 |
| 18 | Topsoil (659E00300) | CY | 81 | $80.00 | $140.00 | $85.00 | $100.00 | $54.00 | $100.00 |
| 19 | Seeding and mulching (659E10000) | SY | 727 | $2.60 | $3.00 | $2.60 | $3.00 | $3.00 | $2.60 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.10 | $800.00 | $870.00 | $800.00 | $870.00 | $912.00 | $800.00 |
| 21 | Lime (659E31000) | ACRE | 0.15 | $1.00 | $20.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Water (659E35000) | MGAL | 4 | $0.50 | $10.00 | $2.00 | $0.60 | $1.00 | $0.50 |
| 23 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Concrete masonry (602E20000) | CY | 0.20 | $5,500.00 | $7,400.00 | $4,500.00 | $7,400.00 | $13,893 | $6,000.00 |
| 25 | 4" base pipe underdrains with geotextile fabric (605E06020) | FT | 361 | $20.00 | $35.00 | $25.00 | $10.00 | $18.25 | $25.00 |
| 26 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 20 | $42.00 | $35.00 | $80.00 | $25.00 | $26.00 | $30.00 |
| 27 | 12" conduit, type C (611E04600) | FT | 16 | $75.00 | $64.00 | $95.00 | $55.00 | $83.00 | $95.00 |
| 28 | 12" conduit, type F (611E05200) | FT | 36 | $110.00 | $64.00 | $150.00 | $90.00 | $48.00 | $130.00 |
| 29 | Catch basin, no. 3A (611E98180) | EACH | 2 | $4,650.00 | $2,850.00 | $4,000.00 | $5,300.00 | $3,611.00 | $5,000.00 |
| 30 | Pavement planing, asphalt concrete, 1.5" depth (254E01000) | SY | 428 | $10.00 | $18.00 | $7.00 | $7.50 | $8.00 | $7.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 64 | $400.00 | $285.00 | $300.00 | $320.00 | $335.00 | $295.00 |
| 32 | Aggregate base (304E20000) | CY | 77 | $100.00 | $100.00 | $95.00 | $80.00 | $85.00 | $125.00 |
| 33 | Non-tracking tack coat (407E20000) | GAL | 85 | $1.00 | $3.00 | $3.00 | $3.00 | $2.75 | $2.65 |
| 34 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 42 | $450.00 | $305.00 | $450.00 | $490.00 | $450.00 | $445.00 |
| 35 | Curb, type 4-C (609E24510) | FT | 650 | $26.50 | $28.00 | $30.00 | $55.00 | $30.00 | $24.00 |
| 36 | Delineator, post ground mounted (620E00500) | EACH | 1 | $250.00 | $255.00 | $400.00 | $440.00 | $456.00 | $235.00 |
| 37 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 9 | $13.00 | $14.00 | $13.00 | $15.00 | $69.00 | $14.00 |
| 38 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $150.00 | $2,600.00 | $500.00 | $550.00 | $570.00 | $95.00 |
| 39 | Removal of ground mounted post support and reerection (630E86010) | EACH | 1 | $150.00 | $215.00 | $500.00 | $550.00 | $570.00 | $195.00 |
| 40 | Edge line, 6", type 1 (642E00104) | MI | 0.12 | $8,300.00 | $33,800 | $20,000 | $22,000 | $22,778 | $8,300.00 |
| 41 | Pavement repair (253E02000) | CY | 20 | $740.00 | $905.00 | $865.00 | $590.00 | $700.00 | $575.00 |
| 42 | Non-tracking tack coat (407E20000) | GAL | 20 | $1.00 | $3.50 | $3.00 | $3.00 | $2.75 | $2.65 |
| 43 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $700.00 | $564.00 | $875.00 | $960.00 | $875.00 | $875.00 |
| 44 | Compacted aggregate (617E10100) | CY | 50 | $140.00 | $100.00 | $105.00 | $140.00 | $110.00 | $95.00 |
| 45 | Steel piles, misc.: W24X55 steel beam, furnished, (507E00400) | FT | 4,715 | $78.00 | $58.00 | $55.00 | $70.00 | $66.00 | $81.00 |
| 46 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 3,946 | $143.50 | $145.00 | $152.00 | $135.00 | $140.00 | $165.00 |
| 47 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 810 | $150.00 | $195.00 | $192.00 | $380.00 | $200.00 | $400.00 |
| 48 | Drilled shafts, misc.: plug pile, 36" diameter, UN (524E95000) | FT | 1,600 | $100.00 | $105.00 | $120.00 | $80.00 | $105.00 | $145.00 |
| 49 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,200.00 | $13,000 | $40,000 | $15,000 | $17,600 | $12,000 |
| 50 | Maintaining traffic (614E11000) | LS | 1 | $4,262.80 | $11,100 | $30,000 | $17,000 | $13,500 | $9,000.00 |
| 51 | Field office, type B (619E16010) | MNTH | 3 | $6,750.00 | $1,750.00 | $1,650.00 | $1,500.00 | $2,500.00 | $3,400.00 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $11,000 | $7,300.00 | $15,500 | $12,000 | $5,000.00 | $34,000 |
| 53 | Mobilization (624E10000) | LS | 1 | $77,000 | $43,500 | $30,000 | $75,000 | $295,178 | $100,729 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.