ODOT contract 268019 bid tabulation
NOB-SR 821-02.98 (SLIDE REPAIR). Let by Ohio DOT on October 1, 2026, NOB. 4 bids received; low bid $1,815,599 by Shelly & Sands Inc, -12% against the engineer's estimate of $2,063,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 49
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,815,599 | Low | -12% |
| 2 | Alan Stone Co Inc | $1,867,203 | +3.0% | -9.0% |
| 3 | Ohio-West Virginia Excavating Co | $2,054,052 | +13% | 0.0% |
| 4 | Complete General Construction Company | $2,090,840 | +15% | +1.0% |
Engineer's estimate: $2,063,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Alan Stone Co Inc | 3. Ohio-West Virginia Excavating Co | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $15,000 | $11,000 | $9,000.00 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $600.00 | $950.00 | $2,250.00 | $2,000.00 |
| 3 | Pavement removed (202E23000) | SY | 743 | $25.00 | $15.00 | $22.00 | $55.00 |
| 4 | Guardrail removed (202E38000) | FT | 1,125 | $4.06 | $4.00 | $4.00 | $2.20 |
| 5 | Special - fill and plug existing conduit (202E70000) | FT | 130 | $60.00 | $55.00 | $110.00 | $60.00 |
| 6 | Excavation (203E10000) | CY | 315 | $19.00 | $35.00 | $42.00 | $75.00 |
| 7 | Embankment (203E20000) | CY | 315 | $10.00 | $20.00 | $80.00 | $110.00 |
| 8 | Subgrade compaction (204E10000) | SY | 838 | $5.00 | $4.50 | $2.00 | $7.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 1,025 | $23.50 | $20.00 | $23.00 | $22.80 |
| 10 | Anchor assembly, MGS type E (606E26150) | EACH | 2 | $2,700.00 | $2,500.00 | $2,500.00 | $2,765.00 |
| 11 | Seeding and mulching (659E10000) | SY | 2,361 | $3.00 | $1.50 | $4.00 | $2.00 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.21 | $940.00 | $610.00 | $1,000.00 | $700.00 |
| 13 | Lime (659E31000) | ACRE | 0.49 | $165.00 | $880.00 | $200.00 | $0.51 |
| 14 | Water (659E35000) | MGAL | 12.70 | $1.00 | $110.00 | $1.50 | $10.00 |
| 15 | Erosion control (832E30000) | EACH | 7,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $1,500.00 | $100.00 | $7,500.00 | $24,000 |
| 17 | Rock channel protection, type C with filter (601E32200) | CY | 34 | $190.00 | $140.00 | $190.00 | $175.00 |
| 18 | Concrete masonry, as per plan (602E20001) | CY | 1 | $3,700.00 | $3,400.00 | $3,500.00 | $9,000.00 |
| 19 | 6" deep pipe underdrains (605E12200) | FT | 527 | $42.00 | $30.00 | $35.00 | $40.00 |
| 20 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 30 | $45.00 | $35.00 | $45.00 | $40.00 |
| 21 | 36" conduit, type B (611E16400) | FT | 60 | $500.00 | $270.00 | $285.00 | $700.00 |
| 22 | Catch basin, no. 2-4 (611E98540) | EACH | 1 | $5,700.00 | $6,300.00 | $4,500.00 | $5,000.00 |
| 23 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $400.00 | $650.00 | $900.00 | $500.00 |
| 24 | Low strength mortar backfill (613E41200) | CY | 84 | $115.00 | $110.00 | $155.00 | $195.00 |
| 25 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 129 | $350.00 | $270.00 | $330.00 | $350.00 |
| 26 | Aggregate base (304E20000) | CY | 201 | $130.00 | $130.00 | $150.00 | $150.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 188 | $4.00 | $6.00 | $12.00 | $4.00 |
| 28 | Prime coat (408E10000) | GAL | 76 | $5.00 | $25.00 | $20.00 | $20.00 |
| 29 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 157 | $375.00 | $260.00 | $365.00 | $375.00 |
| 30 | Compacted aggregate (617E10100) | CY | 8 | $200.00 | $330.00 | $350.00 | $395.00 |
| 31 | RPM (621E00100) | EACH | 22 | $150.00 | $160.00 | $175.00 | $150.00 |
| 32 | Raised pavement marker removed (621E54000) | EACH | 22 | $12.00 | $15.00 | $45.00 | $50.00 |
| 33 | Edge line, 6", type 1 (642E00104) | MI | 0.32 | $2,750.00 | $3,000.00 | $3,200.00 | $2,750.00 |
| 34 | Center line, type 1 (642E00300) | MI | 0.16 | $4,750.00 | $5,200.00 | $5,500.00 | $4,750.00 |
| 35 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,250.00 | $2,900.00 | $3,000.00 | $2,920.00 |
| 36 | Work zone lighting system (614E12740) | EACH | 1 | $80,000 | $4,200.00 | $12,500 | $18,200 |
| 37 | Barrier reflector, type 1, bidirectional (614E13310) | EACH | 20 | $12.50 | $35.00 | $39.00 | $34.00 |
| 38 | Object marker, two way (614E13360) | EACH | 20 | $15.00 | $40.00 | $43.00 | $38.00 |
| 39 | Work zone edge line, class I, 6" (614E22010) | MI | 0.26 | $4,950.00 | $5,400.00 | $12,500 | $4,950.00 |
| 40 | Work zone stop line, class I (614E26000) | FT | 24 | $14.00 | $15.00 | $16.00 | $14.00 |
| 41 | Portable barrier, unanchored (622E41100) | FT | 1,000 | $24.00 | $15.00 | $25.00 | $22.00 |
| 42 | Epoxy coated steel reinforcement (509E10000) | LB | 400,375 | $1.50 | $2.00 | $1.44 | $1.50 |
| 43 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 2,200 | $93.00 | $85.00 | $138.00 | $95.00 |
| 44 | Drilled shafts, 42" diameter, above bedrock, as per plan (524E94803) | FT | 2,200 | $117.00 | $130.00 | $192.00 | $125.00 |
| 45 | Drilled shafts, 42" diameter, into bedrock, as per plan (524E94805) | FT | 1,760 | $132.00 | $120.00 | $152.00 | $190.00 |
| 46 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,920 | $15,000 | $22,000 | $13,000 |
| 47 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $40,000 | $30,800 | $50,000 |
| 48 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $6,600.00 | $950.00 | $10,000 |
| 49 | Mobilization (624E10000) | LS | 1 | $50,000 | $17,000 | $24,100 | $105,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.