ODOT letting results, August 8, 2024
13 contracts let by Ohio DOT on August 8, 2024, $17,331,927 in low bids, a median of 4 bidders per contract. On the 13 with an engineer's estimate, the low bid came in under it 10 times; median low bid -9.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 13
- Low bids, total
- $17,331,927
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240392 | LAK-US 6-04.61 Super (BRIDGE REPAIR) | LAK | 5 | Ruhlin Company | $4,082,078 | $4,598,750 | +13% | -6.0% | ODOT |
| 240395 | TRU-SR 11-09.97 (FOUR LANE RESURFACING) | TRU | 3 | Shelly & Sands Inc | $2,726,195 | $3,325,000 | +22% | -12% | ODOT |
| 240398 | LAW-SR 7-02.17 Tree Clearing (PRUNING/OR TREE/BRUSH REMOVAL) | LAW | 3 | Allard Excavation LLC | $2,187,709 | $3,398,667 | +55% | -3.0% | ODOT |
| 240389 | D08-/D07 GR FY2025 (GUARDRAIL REBUILDING) | District 8 | 1 | Lake Erie Construction Company | $2,012,850 | +2.0% | ODOT | ||
| 240393 | SCI-SR 335-10.31 (BRIDGE REPLACEMENT (1 BRIDGE)) | SCI | 7 | Sunesis Construction Co | $1,947,785 | $2,058,130 | +6.0% | -4.0% | ODOT |
| 248010 | VAN-US 30-14.02/22.07 Bridge Hit (BRIDGE REPAIR) | VAN | 2 | Ruhlin Company | $1,084,375 | $1,838,911 | +70% | -10% | ODOT |
| 240399 | MOE-Sign Flatsheet FY2025 (SIGNING) | MOE | 4 | M P Dory Co | $997,591 | $1,156,764 | +16% | -9.0% | ODOT |
| 248009 | LOR-SR 2-(00.97) (07.42) (BRIDGE REPAIR) | LOR | 5 | Ohio Concrete Maintenance LLC | $698,349 | $893,341 | +28% | -25% | ODOT |
| 244018 | TUS-SR 212-07.84 (CULVERT REPLACEMENT) | TUS | 4 | R C Construction Company and Son Inc | $504,311 | $518,809 | +3.0% | +7.0% | ODOT |
| 240396 | D03-CRSEAL FY2025 (CRACK SEALING) | District 3 | 4 | Scodeller Construction Inc | $438,957 | $471,121 | +7.0% | -17% | ODOT |
| 240397 | D04-FEN FY2025-26 (FENCING) | District 4 | 1 | Lake Erie Construction Company | $427,420 | -9.0% | ODOT | ||
| 240391 | HOL-SR 39-14.32 (CULVERT REPLACEMENT) | HOL | 6 | Ohio Concrete Maintenance LLC | $124,662 | $135,960 | +9.0% | -34% | ODOT |
| 240400 | RIC-US 30-08.79 Bridge Hit (BRIDGE REPAIR) | RIC | 4 | Ruhlin Company | $99,645 | $101,727 | +2.0% | +7.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.