TDOT contract CNZ214 bid tabulation
The rockfall mitigation on i-26 near m.m. 1.7. Let by Tennessee DOT on August 15, 2025, Sullivan County. 3 bids received; low bid $1,748,789 by Rock Supremacy, LLC.
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 38
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Supremacy, LLC | $1,748,789 | Low |
| 2 | Tim's Tree Service, Incorporated | $2,107,373 | +21% |
| 3 | Baker's Construction Services, Inc. | $3,053,654 | +75% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Supremacy, LLC | 2. Tim's Tree Service, Incorporated | 3. Baker's Construction Services, Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $15,000 | $22,162 | $100,119 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $64,000 | $326,040 | $375,370 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 645 | $70.00 | $127.00 | $249.90 |
| 4 | 15" temporary slope drain (209-02.06) | LF | 430 | $70.00 | $96.00 | $85.00 |
| 5 | Sediment removal (209-05) | CY | 27 | $40.00 | $95.00 | $50.37 |
| 6 | Rock check dam (209-08.07) | EACH | 2 | $3,000.00 | $2,200.00 | $606.63 |
| 7 | Enhanced rock check dam (209-08.08) | EACH | 1 | $4,000.00 | $2,500.00 | $1,072.45 |
| 8 | Sandbags (209-09.01) | BAG | 100 | $30.00 | $15.00 | $50.18 |
| 9 | Rock anchor, type II (707-02.44) | LF | 7,400 | $94.50 | $65.50 | $97.00 |
| 10 | Stock fence (707-03.01) | LF | 531 | $45.00 | $9.75 | $17.63 |
| 11 | End, braced line, corner post assembly(stock fence) (707-03.02) | EACH | 4 | $900.00 | $320.00 | $3,500.00 |
| 12 | Removal of fence (sta. 158+98.90 to sta. 163+57.93) (707-06.01) | LF | 450 | $50.00 | $12.00 | $8.00 |
| 13 | Rockfall drape (type II) (707-10.06) | SY | 2,425 | $99.00 | $195.00 | $289.00 |
| 14 | Pedestrian construction barrier fence (707-11.01) | LF | 730 | $45.00 | $28.50 | $21.00 |
| 15 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 4 | $1,000.00 | $825.00 | $2,500.00 |
| 16 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $65.00 | $95.00 | $175.65 |
| 17 | Machined rip-rap (class A-1) (709-05.06) | TON | 12 | $65.00 | $95.00 | $175.34 |
| 18 | Traffic control (712-01) | LS | 1 | $182,000 | $69,881 | $149,918 |
| 19 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 790 | $120.00 | $45.00 | $125.68 |
| 20 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $7,000.00 | $8,000.00 | $9,549.44 |
| 21 | Flexible drums (channelizing) (712-04.01) | EACH | 100 | $40.00 | $41.00 | $85.00 |
| 22 | Barrier rail delineator (712-04.50) | EACH | 37 | $15.00 | $15.25 | $26.93 |
| 23 | Warning lights (type A) (712-05.01) | EACH | 50 | $25.00 | $24.00 | $50.03 |
| 24 | Signs (construction) (712-06) | SF | 228 | $8.00 | $9.95 | $14.04 |
| 25 | Signs (construction)(reduced speed warning) (712-06.16) | EACH | 2 | $700.00 | $705.00 | $849.44 |
| 26 | Speed feedback sign assembly (712-08.08) | EACH | 1 | $4,800.00 | $4,600.00 | $6,519.20 |
| 27 | Digital speed limit sign assembly (712-08.09) | EACH | 1 | $4,200.00 | $4,350.00 | $6,497.92 |
| 28 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 6,585 | $9.00 | $3.50 | $7.16 |
| 29 | Removable black-out tape (8IN) (712-09.31) | LF | 6,600 | $9.00 | $4.25 | $7.97 |
| 30 | Changeable message sign unit (713-16.01) | EACH | 1 | $7,000.00 | $7,500.00 | $7,963.20 |
| 31 | Mobilization (717-01) | LS | 1 | $89,000 | $198,345 | $350,000 |
| 32 | Portable smart work zone system (725-21.07) | DAY | 365 | $1.00 | $590.00 | $250.00 |
| 33 | Geotextile (type III)(erosion control) (740-10.03) | SY | 172 | $10.00 | $7.25 | $20.44 |
| 34 | Seeding (with mulch) (801-01) | UNIT | 31 | $100.00 | $62.00 | $215.30 |
| 35 | Temporary seeding (with mulch) (801-01.07) | UNIT | 24 | $100.00 | $48.00 | $100.13 |
| 36 | Seeding (without mulch) (801-02) | UNIT | 12 | $250.00 | $27.25 | $95.27 |
| 37 | Water (seeding & sodding) (801-03) | MG | 4 | $250.00 | $85.00 | $78.82 |
| 38 | Erosion control blanket (type II) (805-12.02) | SY | 1,320 | $9.00 | $2.75 | $15.11 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.