TDOT contract CNZ261 bid tabulation
The repair of the bridge on s.r. 62 over little clear creek (l.m. 13.77). Let by Tennessee DOT on October 3, 2025, Morgan County. 4 bids received; low bid $1,673,335 by Jamison Construction, LLC.
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 38
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jamison Construction, LLC | $1,673,335 | Low |
| 2 | Mid-State Construction Company, Inc. | $1,818,806 | +9.0% |
| 3 | Southern Constructors, Inc. | $2,260,852 | +35% |
| 4 | Jones Bros. Contractors, LLC | $2,495,758 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jamison Construction, LLC | 2. Mid-State Construction Company, Inc. | 3. Southern Constructors, Inc. | 4. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $14,500 | $14,959 | $50,000 | $25,000 |
| 2 | Removal and disposal of brush & trees (201-07.01) | LS | 1 | $15,000 | $4,833.15 | $50,000 | $25,000 |
| 3 | Removal of structures (bridge no.65-SR062-13.77) (202-04.01) | LS | 1 | $280,000 | $319,718 | $325,000 | $700,000 |
| 4 | Dry excavation (bridges) (204-02.01) | CY | 407 | $70.00 | $73.85 | $75.00 | $60.00 |
| 5 | Granular backfill (bridges) (303-01.02) | TON | 37 | $75.00 | $61.86 | $100.00 | $150.00 |
| 6 | Mineral aggregate (size **) (303-10.04) | TON | 675 | $78.00 | $62.71 | $90.00 | $100.00 |
| 7 | Bituminous material for tack coat (TC) (403-01) | TON | 1 | $1,200.00 | $1,190.25 | $1,250.00 | $1,035.00 |
| 8 | Acs mix(PG64-22) grading D (411-01.10) | TON | 30 | $700.00 | $718.75 | $800.00 | $625.00 |
| 9 | Cold planing bituminous pavement (415-01.02) | SY | 444 | $35.00 | $36.80 | $70.00 | $32.00 |
| 10 | Epoxy coated reinforcing steel (604-02.03) | LB | 100,118 | $2.10 | $2.31 | $2.75 | $2.25 |
| 11 | Pavement @ bridge ends (604-03.04) | SY | 213 | $510.00 | $542.95 | $500.00 | $600.00 |
| 12 | Class D concrete (bridge deck) (604-03.09) | CY | 266 | $1,275.00 | $1,538.77 | $1,600.00 | $1,800.00 |
| 13 | Applied texture finish (new structures) (604-04.01) | SY | 916 | $15.00 | $14.38 | $22.00 | $18.00 |
| 14 | Applied texture finish (existing structures) (604-04.02) | SY | 21 | $15.00 | $74.75 | $22.00 | $18.00 |
| 15 | Bridge deck grooving (mechanical) (604-05.31) | SY | 1,171 | $8.75 | $10.24 | $15.00 | $5.45 |
| 16 | Concrete repairs (604-10.54) | SF | 1 | $600.00 | $1,980.80 | $1,000.00 | $2,500.00 |
| 17 | Concrete (foundation repairs) (604-10.55) | CY | 6 | $2,400.00 | $2,485.20 | $5,000.00 | $5,000.00 |
| 18 | Epoxy injection (injection) (604-10.58) | GAL | 5 | $225.00 | $80.50 | $200.00 | $250.00 |
| 19 | Epoxy injection repair (complete and in place) (604-10.62) | LF | 88 | $140.00 | $110.55 | $150.00 | $260.00 |
| 20 | Conc parapet single slope (STD-1-1SS) (620-05.01) | LF | 498 | $170.00 | $188.09 | $250.00 | $225.00 |
| 21 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 4 | $3,225.00 | $3,105.00 | $4,000.00 | $2,700.00 |
| 22 | Machined rip-rap (class A-1) (709-05.06) | TON | 40 | $80.00 | $98.90 | $275.00 | $150.00 |
| 23 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 104 | $60.00 | $53.63 | $70.00 | $50.00 |
| 24 | 6" pipe underdrain (710-09.02) | LF | 28 | $30.00 | $36.81 | $70.00 | $10.00 |
| 25 | Traffic control (712-01) | LS | 1 | $78,000 | $91,580 | $100,000 | $35,000 |
| 26 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 540 | $55.00 | $84.76 | $150.00 | $90.00 |
| 27 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $8,800.00 | $5,175.00 | $12,000 | $10,000 |
| 28 | Flexible drums (channelizing) (712-04.01) | EACH | 47 | $44.00 | $46.00 | $50.00 | $40.00 |
| 29 | Barrier rail delineator (712-04.50) | EACH | 27 | $20.00 | $14.95 | $50.00 | $13.00 |
| 30 | Signs (construction) (712-06) | SF | 620 | $10.00 | $8.80 | $15.00 | $7.65 |
| 31 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 3,834 | $4.15 | $4.20 | $5.00 | $3.65 |
| 32 | Removable pavement marking (stop line) (712-09.04) | LF | 50 | $25.00 | $28.75 | $30.00 | $20.00 |
| 33 | Removable black-out tape (8IN) (712-09.31) | LF | 1,853 | $4.50 | $4.54 | $5.00 | $3.95 |
| 34 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.30 | $13,500 | $13,800 | $22,000 | $12,000 |
| 35 | Mobilization (717-01) | LS | 1 | $137,000 | $142,222 | $220,000 | $255,000 |
| 36 | Temporary traffic signal system (730-40) | EACH | 1 | $105,000 | $91,736 | $125,000 | $160,000 |
| 37 | Geogrid reinforcement type 2 (740-07.04) | SY | 2,348 | $6.50 | $6.76 | $12.00 | $6.00 |
| 38 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 441 | $6.00 | $7.35 | $12.00 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.