TxDOT contract A00121423 bid tabulation
Preventive Maintenance, IH 10 (Pecos County line to 15.9 miles E of Pecos County line). Let by Texas DOT on February 6, 2025, Crockett, San Angelo District. 6 bids received; low bid $24,564,337 by Kiewit Infrastructure South Co., -27% against the engineer's estimate of $33,606,433.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 59
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kiewit Infrastructure South Co. | $24,564,337 | Low | -27% |
| 2 | CK Newberry, LLC | $25,755,743 | +5.0% | -23% |
| 3 | RK Hall, LLC | $26,437,779 | +8.0% | -21% |
| 4 | Reece Albert, Inc. | $28,182,975 | +15% | -16% |
| 5 | FNF Construction, Inc. | $30,265,623 | +23% | -10% |
| 6 | Allen Keller Company | $31,365,593 | +28% | -7.0% |
Engineer's estimate: $33,606,433.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Kiewit Infrastructure South Co. | 2. CK Newberry, LLC | 3. RK Hall, LLC | 4. Reece Albert, Inc. | 5. FNF Construction, Inc. | 6. Allen Keller Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (roadway) (110-7001) | CY | 270 | $82.00 | $544.91 | $100.00 | $300.00 | $93.97 | $400.00 | $74.18 |
| 2 | Embankment (final)(OC)(type A) (132-7001) | CY | 4,652 | $201.00 | $45.47 | $35.00 | $72.72 | $41.65 | $150.00 | $105.82 |
| 3 | Backfill (type A or B) (134-7004) | STA | 1,658 | $146.00 | $312.27 | $150.00 | $152.59 | $168.05 | $200.00 | $184.57 |
| 4 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 32,259 | $11.06 | $5.19 | $4.00 | $5.35 | $4.58 | $6.50 | $7.17 |
| 5 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 338,374 | $4.25 | $4.59 | $3.75 | $4.11 | $4.99 | $4.50 | $4.26 |
| 6 | Aggregate (type-PB, GR-3)(sac-B) (316-7208) | CY | 6,836 | $175.00 | $140.81 | $120.00 | $159.58 | $155.75 | $200.00 | $162.60 |
| 7 | Tack coat (342-7015) | GAL | 45,117 | $6.50 | $3.21 | $4.00 | $4.58 | $2.55 | $5.00 | $4.74 |
| 8 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 36,856 | $150.00 | $85.00 | $122.00 | $120.00 | $143.54 | $123.00 | $142.58 |
| 9 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 84,997 | $173.94 | $103.00 | $125.00 | $142.00 | $145.24 | $100.00 | $152.54 |
| 10 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 24,182 | $1.05 | $2.40 | $3.00 | $3.61 | $3.67 | $3.00 | $3.24 |
| 11 | Planing asphalt concrete pavement(2") (354-7051) | SY | 61,887 | $2.00 | $2.57 | $2.00 | $3.50 | $3.23 | $3.50 | $3.04 |
| 12 | Planing asphalt concrete pavement(4") (354-7053) | SY | 161,295 | $5.00 | $2.76 | $3.75 | $4.29 | $4.16 | $4.25 | $3.57 |
| 13 | Cem stabil BKFL (400-7010) | CY | 540 | $229.99 | $420.76 | $300.00 | $226.89 | $345.43 | $800.00 | $274.01 |
| 14 | Temporary special shoring (403-7001) | SF | 1,920 | $50.00 | $1.00 | $60.00 | $34.34 | $7.16 | $242.00 | $86.52 |
| 15 | Riprap (mow strip)(4 in) (432-7013) | CY | 1,730 | $719.03 | $728.21 | $650.00 | $656.25 | $743.74 | $1,187.90 | $636.39 |
| 16 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 1,760 | $48.00 | $45.44 | $55.00 | $53.03 | $60.09 | $70.00 | $51.42 |
| 17 | Mobilization (500-7001) | LS | 1 | $3,055,130 | $2,448,230 | $2,500,000 | $996,866 | $1,324,072 | $2,992,000 | $3,000,000 |
| 18 | Barricades, signs and traffic handling (502-7001) | MO | 20 | $8,000.00 | $50,000 | $15,000 | $10,869 | $6,096.73 | $95,167 | $57,888 |
| 19 | Portable changeable message sign (503-7001) | DAY | 44 | $100.00 | $102.96 | $125.00 | $136.84 | $35.70 | $45.00 | $203.28 |
| 20 | TMA (stationary) (505-7001) | DAY | 336 | $150.00 | $502.62 | $400.00 | $286.14 | $49.57 | $250.00 | $234.59 |
| 21 | TMA (mobile operation) (505-7003) | DAY | 44 | $200.00 | $991.03 | $200.00 | $518.21 | $480.13 | $600.00 | $1,064.42 |
| 22 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 196 | $6.39 | $13.23 | $11.00 | $18.69 | $13.16 | $4.00 | $23.43 |
| 23 | Biodegradable erosion control logs (remove) (506-7046) | LF | 196 | $2.54 | $3.69 | $4.00 | $3.31 | $7.21 | $1.50 | $16.66 |
| 24 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 1,680 | $70.00 | $100.45 | $60.00 | $29.26 | $35.02 | $45.00 | $125.09 |
| 25 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 1,680 | $15.00 | $4.01 | $15.00 | $11.64 | $1.73 | $7.50 | $10.70 |
| 26 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 1,680 | $24.00 | $28.64 | $50.00 | $25.02 | $28.51 | $25.00 | $17.08 |
| 27 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 672,818 | $0.15 | $0.08 | $0.06 | $0.01 | $0.07 | $0.08 | $0.15 |
| 28 | Fill milled asphalt rumble strips (shoulder) (533-7005) | LF | 230,983 | $0.10 | $1.62 | $1.00 | $1.24 | $1.25 | $4.00 | $0.53 |
| 29 | Metal W-beam guard fence (steel post) (540-7002) | LF | 33,282 | $34.20 | $32.92 | $30.00 | $29.66 | $33.62 | $40.00 | $28.77 |
| 30 | Downstream anchor terminal section (540-7015) | EACH | 64 | $2,700.00 | $1,433.12 | $1,300.00 | $1,291.50 | $1,463.68 | $1,800.00 | $1,252.43 |
| 31 | Metal thrie-beam guard fence (steel post) (540-7020) | EACH | 16 | $29.44 | $3,145.88 | $2,200.00 | $2,835.00 | $3,212.96 | $3,000.00 | $4,581.29 |
| 32 | Remove metal beam guard fence (542-7001) | LF | 33,282 | $4.49 | $3.50 | $2.50 | $3.15 | $3.57 | $3.50 | $3.05 |
| 33 | Remove terminal anchor section (542-7002) | EACH | 64 | $200.00 | $349.54 | $250.00 | $315.00 | $357.00 | $350.00 | $305.47 |
| 34 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 16 | $286.54 | $349.54 | $250.00 | $315.00 | $357.00 | $350.00 | $305.47 |
| 35 | Guardrail end treatment (install) (544-7001) | EACH | 64 | $3,572.44 | $3,728.45 | $2,950.00 | $3,360.00 | $3,807.95 | $4,000.00 | $3,258.35 |
| 36 | Guardrail end treatment (remove) (544-7003) | EACH | 64 | $280.00 | $349.54 | $250.00 | $315.00 | $357.00 | $350.00 | $305.47 |
| 37 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 3 | $3,000.00 | $1,306.51 | $1,150.00 | $2,945.18 | $1,232.98 | $1,200.00 | $2,770.45 |
| 38 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $2,000.00 | $941.50 | $1,700.00 | $6,270.61 | $1,232.79 | $2,200.00 | $4,972.42 |
| 39 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 1 | $7,000.00 | $18,404 | $10,000 | $10,841 | $8,967.69 | $15,000 | $12,202 |
| 40 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 397 | $27.50 | $34.95 | $25.00 | $31.50 | $35.70 | $30.00 | $30.55 |
| 41 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 236,226 | $1.00 | $0.35 | $0.35 | $0.23 | $0.36 | $0.25 | $0.30 |
| 42 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 64 | $1.00 | $0.58 | $0.55 | $3.15 | $0.60 | $3.10 | $0.51 |
| 43 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 236,226 | $1.00 | $0.35 | $0.35 | $0.23 | $0.36 | $0.25 | $0.30 |
| 44 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 5,720 | $1.00 | $1.22 | $1.05 | $0.89 | $1.25 | $0.90 | $1.07 |
| 45 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 1,121 | $2.00 | $8.74 | $7.50 | $2.63 | $8.92 | $2.60 | $7.63 |
| 46 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 100 | $11.72 | $23.30 | $20.00 | $6.30 | $23.80 | $6.20 | $20.37 |
| 47 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 16,520 | $0.22 | $0.29 | $0.25 | $0.20 | $0.30 | $0.20 | $0.25 |
| 48 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 190,416 | $0.22 | $0.29 | $0.25 | $0.20 | $0.30 | $0.20 | $0.25 |
| 49 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 183,901 | $0.22 | $0.29 | $0.25 | $0.20 | $0.30 | $0.20 | $0.25 |
| 50 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 42,210 | $0.75 | $0.87 | $0.75 | $0.79 | $0.89 | $0.80 | $0.76 |
| 51 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 168,197 | $0.45 | $0.82 | $0.70 | $0.71 | $0.83 | $0.75 | $0.72 |
| 52 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 168,197 | $0.45 | $0.82 | $0.70 | $0.71 | $0.83 | $0.75 | $0.72 |
| 53 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 22,219 | $2.33 | $0.79 | $0.70 | $0.72 | $0.81 | $0.80 | $0.69 |
| 54 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 15,704 | $2.14 | $0.79 | $0.70 | $0.79 | $0.81 | $0.80 | $0.69 |
| 55 | Prefabricated PM type C (W)(number) (668-7102) | EACH | 4 | $220.00 | $407.80 | $350.00 | $472.50 | $416.50 | $470.00 | $356.38 |
| 56 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 21 | $6.00 | $11.65 | $10.00 | $10.50 | $11.90 | $10.50 | $10.18 |
| 57 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,228 | $3.25 | $5.24 | $4.50 | $4.20 | $5.35 | $4.50 | $4.58 |
| 58 | Full - width mowing (730-7019) | CYC | 4 | $12,000 | $16,478 | $5,000.00 | $32,725 | $29,750 | $25,000 | $20,592 |
| 59 | Litter removal (734-7002) | CYC | 4 | $18,000 | $5,264.68 | $2,500.00 | $23,620 | $13,387 | $5,000.00 | $11,758 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.