TxDOT contract A00131128 bid tabulation
Install/Upgrade Drainage Structure(S), FM 1097 (At Atkins Creek to .). Let by Texas DOT on April 4, 2025, Montgomery, Houston District. 8 bids received; low bid $3,494,495 by Roman Emperors Road, LLC, -13% against the engineer's estimate of $4,016,607.
- Owner
- Texas DOT
- Letting
- 04 APR 2025
- Pay items
- 81
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Roman Emperors Road, LLC | $3,494,495 | Low | -13% |
| 2 | Ser Construction Partners, LLC | $3,650,762 | +4.0% | -9.0% |
| 3 | Brice Highway LLC | $3,694,692 | +6.0% | -8.0% |
| 4 | Texas Materials Group, Inc. | $3,833,096 | +10% | -5.0% |
| 5 | MB Western Industrial Contracting Co. | $3,892,240 | +11% | -3.0% |
| 6 | Forde Construction Company, Inc. | $4,659,352 | +33% | +16% |
| 7 | R Construction Civil, LLC | $5,026,343 | +44% | +25% |
| 8 | Grey Sky Construction LLC | $5,569,074 | +59% | +39% |
Engineer's estimate: $4,016,607.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Roman Emperors Road, LLC | 2. Ser Construction Partners, LLC | 3. Brice Highway LLC | 4. Texas Materials Group, Inc. | 5. MB Western Industrial Contracting Co. | 6. Forde Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 12 | $8,000.00 | $10,000 | $1,285.30 | $14,300 | $10,000 | $1,525.00 | $14,000 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 413 | $16.00 | $20.00 | $15.80 | $10.15 | $23.00 | $12.00 | $26.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 1,066 | $35.00 | $30.00 | $8.30 | $9.60 | $15.00 | $15.00 | $7.00 |
| 4 | Removing concrete (miscellaneous) (104-7046) | SY | 49 | $82.00 | $30.00 | $13.40 | $52.67 | $27.00 | $27.00 | $58.00 |
| 5 | Remove (13") TRT/untrt base & asphalt pavement (105-7033) | SY | 346 | $23.00 | $12.00 | $111.40 | $36.06 | $26.00 | $6.50 | $32.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 565 | $45.00 | $30.00 | $80.50 | $40.51 | $45.00 | $18.00 | $55.00 |
| 7 | Excavation (channel) (110-7002) | CY | 2,398 | $30.00 | $35.00 | $36.20 | $25.24 | $21.00 | $23.00 | $30.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,761 | $51.00 | $35.00 | $4.30 | $46.02 | $12.00 | $31.00 | $30.00 |
| 9 | Block sodding (162-7002) | SY | 6,741 | $10.00 | $10.00 | $6.10 | $5.50 | $7.00 | $6.20 | $6.00 |
| 10 | Drill seed (temporary_warm_cool) (164-7015) | SY | 5,449 | $1.45 | $1.00 | $0.40 | $0.25 | $1.50 | $0.50 | $0.50 |
| 11 | Fertilizer (166-7001) | ACRE | 2.25 | $1,535.00 | $2,000.00 | $989.40 | $1,500.00 | $1,300.00 | $1,000.00 | $950.00 |
| 12 | Vegetative watering (168-7001) | TGL | 270 | $90.00 | $190.00 | $39.60 | $52.25 | $30.00 | $45.00 | $65.00 |
| 13 | Asphalt TRT base (GR 2)(PG 64) (292-7006) | TON | 458 | $156.00 | $160.00 | $197.90 | $138.00 | $134.00 | $163.00 | $230.00 |
| 14 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 1,422 | $165.00 | $160.00 | $185.00 | $148.00 | $155.00 | $175.00 | $164.00 |
| 15 | D-GR HMA type D sac-A PG76-22 (341-7057) | TON | 355 | $210.00 | $200.00 | $215.30 | $165.00 | $173.00 | $195.00 | $190.00 |
| 16 | Tack coat (341-7082) | GAL | 515 | $4.50 | $5.00 | $13.40 | $4.50 | $4.00 | $5.40 | $4.00 |
| 17 | Planing asphalt concrete pavement (1.5") (354-7074) | SY | 4,274 | $2.00 | $2.00 | $7.10 | $4.09 | $2.00 | $2.50 | $5.00 |
| 18 | Cut & restore asphalt paving (400-7008) | SY | 140 | $225.00 | $230.00 | $308.50 | $227.60 | $250.00 | $237.00 | $325.00 |
| 19 | Cem stabil BKFL (400-7010) | CY | 345 | $95.00 | $230.00 | $67.50 | $83.79 | $130.00 | $260.00 | $100.00 |
| 20 | Cement stab backfill (inlet or MH) (400-7011) | CY | 42 | $75.00 | $150.00 | $67.50 | $83.79 | $130.00 | $260.00 | $95.00 |
| 21 | Trench excavation protection (402-7001) | LF | 109 | $6.00 | $15.00 | $1.20 | $2.59 | $50.00 | $12.00 | $10.00 |
| 22 | Temporary special shoring (403-7001) | SF | 10,428 | $50.00 | $20.00 | $31.30 | $15.74 | $47.00 | $24.00 | $60.00 |
| 23 | CL E concrete (seal slab)(non-reinforced) (420-7070) | CY | 23 | $1,960.00 | $600.00 | $605.20 | $489.91 | $600.00 | $600.00 | $650.00 |
| 24 | Class A concrete (channel lining) (420-7150) | CY | 349 | $245.00 | $500.00 | $736.00 | $618.24 | $850.00 | $600.00 | $950.00 |
| 25 | Riprap (concrete)(4 in) (432-7001) | CY | 140 | $1,024.00 | $650.00 | $552.10 | $677.47 | $700.00 | $635.00 | $716.00 |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 69 | $1,000.00 | $650.00 | $539.50 | $710.42 | $850.00 | $640.00 | $982.00 |
| 27 | Riprap (stone protection)(18 in) (432-7043) | CY | 100 | $245.00 | $200.00 | $365.10 | $314.58 | $215.00 | $275.00 | $270.00 |
| 28 | Riprap (stone protection)(24 in) (432-7045) | CY | 420 | $270.00 | $200.00 | $365.80 | $313.88 | $195.00 | $225.00 | $270.00 |
| 29 | Riprap (stone protection)(30 in) (432-7047) | CY | 75 | $313.00 | $200.00 | $426.70 | $332.10 | $250.00 | $250.00 | $300.00 |
| 30 | Concrete box culvert (10 FT X 7 FT) (462-7035) | LF | 200 | $1,100.00 | $1,600.00 | $1,492.60 | $2,132.67 | $2,500.00 | $2,500.00 | $2,140.00 |
| 31 | RC pipe (CL III)(18 in) (464-7003) | LF | 40 | $140.00 | $120.00 | $95.40 | $117.89 | $120.00 | $120.00 | $150.00 |
| 32 | RC pipe (CL III)(24 in) (464-7005) | LF | 393 | $140.00 | $150.00 | $109.40 | $139.09 | $130.00 | $150.00 | $130.00 |
| 33 | Manh (complete)(PRM)(72IN) (465-7004) | EACH | 2 | $10,715 | $6,600.00 | $8,367.20 | $14,874 | $6,200.00 | $18,000 | $15,000 |
| 34 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 1 | $4,300.00 | $6,500.00 | $4,282.10 | $9,976.66 | $5,600.00 | $9,000.00 | $4,200.00 |
| 35 | Inlet (complete)(pod)(FG)(3FTX3FT) (465-7048) | EACH | 1 | $8,000.00 | $5,000.00 | $5,474.80 | $12,867 | $7,700.00 | $9,000.00 | $6,400.00 |
| 36 | Inl(CMP)(pazd-CZ)(FG)(3FTX3FT-3FTX3FT) (465-7163) | EACH | 3 | $6,430.00 | $6,000.00 | $5,499.20 | $13,500 | $6,300.00 | $9,000.00 | $6,400.00 |
| 37 | Wingwall (PW - 2) (HW=10 FT) (466-7194) | EACH | 1 | $68,600 | $50,000 | $60,480 | $55,851 | $70,000 | $50,000 | $75,000 |
| 38 | Wingwall (SW - 0) (HW=13 FT) (466-7211) | EACH | 1 | $26,000 | $60,000 | $74,702 | $79,594 | $90,000 | $55,000 | $78,000 |
| 39 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,500.00 | $2,000.00 | $2,173.40 | $2,744.14 | $1,200.00 | $1,200.00 | $2,500.00 |
| 40 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,700.00 | $2,000.00 | $1,624.90 | $8,899.03 | $10,000 | $3,000.00 | $2,300.00 |
| 41 | Removing structure (pipe) (496-7007) | LF | 244 | $60.00 | $30.00 | $50.10 | $92.48 | $100.00 | $30.00 | $90.00 |
| 42 | Removing rock riprap (496-7040) | LF | 222 | $175.00 | $50.00 | $27.90 | $70.04 | $35.00 | $60.00 | $150.00 |
| 43 | Mobilization (500-7001) | LS | 1 | $361,625 | $300,000 | $360,000 | $360,000 | $373,000 | $350,000 | $468,000 |
| 44 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $5,000.00 | $8,000.00 | $2,069.30 | $3,289.93 | $15,000 | $5,000.00 | $22,000 |
| 45 | Portable changeable message sign (503-7001) | DAY | 358 | $150.00 | $120.00 | $82.60 | $142.27 | $100.00 | $100.00 | $180.00 |
| 46 | TMA (stationary) (505-7001) | DAY | 80 | $275.00 | $300.00 | $302.60 | $470.96 | $260.00 | $250.00 | $200.00 |
| 47 | TMA (mobile operation) (505-7002) | HR | 72 | $90.00 | $100.00 | $58.20 | $136.10 | $60.00 | $250.00 | $200.00 |
| 48 | Rock filter dams (install) (type 2) (506-7002) | LF | 82 | $51.00 | $55.00 | $58.20 | $45.00 | $90.00 | $60.00 | $51.00 |
| 49 | Rock filter dams (install) (type 3) (506-7003) | LF | 26 | $75.00 | $155.00 | $87.30 | $45.00 | $93.00 | $89.00 | $75.00 |
| 50 | Rock filter dams (remove) (506-7011) | LF | 108 | $15.00 | $30.00 | $29.10 | $20.00 | $20.00 | $30.00 | $28.00 |
| 51 | Construction exits (install) (type 1) (506-7020) | SY | 156 | $35.00 | $30.00 | $34.90 | $22.00 | $25.00 | $60.00 | $75.00 |
| 52 | Construction exits (remove) (506-7024) | SY | 156 | $12.00 | $10.00 | $11.60 | $11.00 | $10.00 | $30.00 | $29.00 |
| 53 | Temporary sediment control fence (install) (506-7039) | LF | 1,632 | $4.00 | $5.00 | $2.30 | $2.10 | $5.00 | $5.00 | $5.00 |
| 54 | Temporary sediment control fence (remove) (506-7041) | LF | 1,632 | $1.25 | $2.00 | $0.60 | $0.50 | $1.50 | $2.50 | $2.00 |
| 55 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 148 | $10.00 | $10.00 | $10.50 | $7.00 | $10.00 | $11.00 | $10.00 |
| 56 | Biodegradable erosion control logs (remove) (506-7046) | LF | 148 | $2.50 | $2.00 | $2.30 | $2.00 | $2.00 | $2.50 | $3.00 |
| 57 | Constructing detours (508-7001) | SY | 4,083 | $140.00 | $100.00 | $125.00 | $141.92 | $70.00 | $100.00 | $110.00 |
| 58 | Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021) | LF | 2,740 | $16.00 | $20.00 | $15.00 | $12.83 | $14.00 | $25.00 | $20.00 |
| 59 | Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022) | LF | 480 | $22.00 | $25.00 | $15.00 | $16.00 | $14.00 | $30.00 | $39.00 |
| 60 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 8,120 | $25.00 | $18.00 | $10.40 | $6.04 | $4.00 | $20.00 | $10.00 |
| 61 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 1,440 | $25.00 | $26.00 | $10.40 | $5.68 | $4.00 | $30.00 | $10.00 |
| 62 | Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045) | LF | 2,740 | $22.00 | $10.00 | $15.00 | $13.20 | $14.00 | $10.00 | $18.00 |
| 63 | Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046) | LF | 480 | $35.00 | $10.00 | $15.00 | $16.54 | $14.00 | $10.00 | $42.00 |
| 64 | Driveways (concrete) (530-7006) | SY | 65 | $95.00 | $120.00 | $139.60 | $278.34 | $160.00 | $125.00 | $244.00 |
| 65 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,225 | $33.00 | $25.00 | $26.20 | $22.50 | $24.00 | $31.00 | $27.00 |
| 66 | Remove metal beam guard fence (542-7001) | LF | 369 | $4.00 | $5.00 | $2.90 | $2.50 | $3.00 | $2.50 | $3.20 |
| 67 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,520.00 | $2,700.00 | $3,666.60 | $3,150.00 | $3,200.00 | $3,500.00 | $3,500.00 |
| 68 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $360.00 | $400.00 | $291.00 | $250.00 | $260.00 | $378.00 | $215.00 |
| 69 | Wire fence (type A) (552-7001) | LF | 144 | $34.00 | $40.00 | $40.70 | $10.00 | $20.00 | $41.00 | $42.00 |
| 70 | Wire fence (remove) (552-7011) | LF | 144 | $5.50 | $7.00 | $11.60 | $2.00 | $10.00 | $41.00 | $40.00 |
| 71 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $1,000.00 | $1,500.00 | $1,065.10 | $915.00 | $950.00 | $1,170.00 | $953.56 |
| 72 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $110.00 | $150.00 | $98.90 | $85.00 | $85.00 | $130.00 | $280.00 |
| 73 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 26,888 | $0.50 | $0.50 | $0.40 | $0.42 | $0.30 | $0.50 | $0.35 |
| 74 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 23,658 | $0.50 | $0.60 | $0.40 | $0.42 | $0.30 | $0.50 | $0.35 |
| 75 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 3,288 | $1.40 | $2.50 | $2.40 | $1.27 | $3.60 | $2.50 | $2.20 |
| 76 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 3,734 | $0.85 | $3.00 | $2.40 | $1.27 | $3.60 | $2.50 | $2.20 |
| 77 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 51 | $0.85 | $6.00 | $5.80 | $1.27 | $12.00 | $6.00 | $5.30 |
| 78 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 116 | $7.00 | $8.00 | $7.00 | $7.00 | $7.00 | $7.00 | $6.40 |
| 79 | Eliminating existing PM & markers (6") (677-7002) | LF | 7,073 | $0.70 | $1.00 | $0.60 | $0.49 | $0.51 | $0.65 | $0.60 |
| 80 | Underseal course (3006-7001) | GAL | 172 | $7.60 | $5.00 | $17.50 | $4.50 | $4.00 | $915.00 | $4.00 |
| 81 | High friction surface treatment (3009-7001) | SY | 1,395 | $23.00 | $25.00 | $61.10 | $21.50 | $40.00 | $61.00 | $40.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way