TxDOT contract A00131299 bid tabulation
Bridge Replacement, county road 443 (CR 254 @ PERRY CREEK to (MAP #82)). Let by Texas DOT on July 1, 2026, Limestone, Waco District. 8 bids received; low bid $2,080,558 by Tucan Contracting, LLC, -8.9% against the engineer's estimate of $2,284,078.
- Owner
- Texas DOT
- Letting
- 01 JUL 2026
- Pay items
- 48
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Tucan Contracting, LLC | $2,080,558 | Low | -9.0% |
| 2 | Texas Steel Industrial Placing, LLC | $2,167,348 | +4.0% | -5.0% |
| 3 | Hodges and Son Construction Company, Inc. | $2,377,286 | +14% | +4.0% |
| 4 | Knife River Corporation - South | $2,459,292 | +18% | +8.0% |
| 5 | Pmco Construction LLC | $2,534,874 | +22% | +11% |
| 6 | Yoko Excavating, LLC | $2,819,410 | +36% | +23% |
| 7 | Presidio Contracting, LLC | $2,881,522 | +38% | +26% |
| 8 | Joe Bland Construction LLC | $3,038,937 | +46% | +33% |
Engineer's estimate: $2,284,078.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Tucan Contracting, LLC | 2. Texas Steel Industrial Placing, LLC | 3. Hodges and Son Construction Company, Inc. | 4. Knife River Corporation - South | 5. Pmco Construction LLC | 6. Yoko Excavating, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 17.75 | $2,900.00 | $2,725.00 | $1,000.00 | $2,300.00 | $3,900.00 | $4,000.00 | $5,945.30 |
| 2 | Remove (0"-6") TRT/untrt base & asphalt pavement (105-7046) | SY | 2,663 | $6.00 | $10.90 | $5.00 | $4.00 | $6.50 | $10.00 | $14.18 |
| 3 | Excavation (roadway) (110-7001) | CY | 1,692 | $30.00 | $10.90 | $10.00 | $20.00 | $22.00 | $20.00 | $23.15 |
| 4 | Excavation (channel) (110-7002) | CY | 945 | $25.00 | $10.90 | $10.00 | $20.00 | $29.00 | $24.00 | $44.40 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 861 | $40.00 | $27.25 | $20.00 | $30.00 | $15.00 | $24.00 | $92.81 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 5,141 | $3.00 | $4.36 | $4.00 | $1.00 | $1.45 | $4.00 | $10.17 |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 5,141 | $3.00 | $0.45 | $0.75 | $2.00 | $1.10 | $2.15 | $2.02 |
| 8 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 5,141 | $0.43 | $0.40 | $0.75 | $1.50 | $0.75 | $2.15 | $1.29 |
| 9 | Vegetative watering (168-7001) | TGL | 84 | $37.00 | $43.60 | $1.00 | $1.00 | $25.00 | $25.00 | $137.37 |
| 10 | Soil retention blankets (CL 1) (type B) (169-7043) | SY | 5,141 | $0.85 | $0.80 | $1.50 | $2.00 | $1.40 | $2.20 | $2.01 |
| 11 | FL BS (compacted in place)(type D GR 3)(final pos) (247-7189) | CY | 794 | $75.00 | $38.15 | $90.00 | $90.00 | $100.00 | $125.00 | $109.40 |
| 12 | Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004) | GAL | 5,718 | $4.00 | $10.90 | $6.00 | $6.00 | $1.00 | $9.00 | $8.63 |
| 13 | Cem stabil BKFL (400-7010) | CY | 350 | $210.00 | $196.20 | $160.00 | $285.00 | $282.00 | $300.00 | $280.25 |
| 14 | Drilled shaft (24 in) (416-7004) | LF | 1,185 | $200.00 | $206.46 | $275.00 | $170.00 | $235.00 | $205.00 | $297.65 |
| 15 | Drilled shaft (30 in) (416-7005) | LF | 102 | $256.15 | $400.00 | $275.00 | $335.00 | $320.00 | $681.42 | |
| 16 | Class C concrete (abutment) (420-7012) | CY | 106.80 | $1,400.00 | $1,090.00 | $1,030.00 | $1,600.00 | $1,650.00 | $1,500.00 | $1,777.97 |
| 17 | Class C concrete (cap) (420-7022) | CY | 6.70 | $1,600.00 | $1,635.00 | $1,600.00 | $2,000.00 | $2,050.00 | $3,000.00 | $1,867.36 |
| 18 | Class C concrete (column) (420-7038) | CY | 3.10 | $1,600.00 | $1,962.00 | $2,000.00 | $2,800.00 | $2,950.00 | $3,500.00 | $3,900.23 |
| 19 | Reinforced concrete slab (box beam) (422-7005) | SF | 1,962 | $22.89 | $20.00 | $28.00 | $29.00 | $30.00 | $21.02 | |
| 20 | Reinforced concrete slab (slab beam) (422-7007) | SF | 5,200 | $27.00 | $21.80 | $20.00 | $26.00 | $29.00 | $30.00 | $28.14 |
| 21 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 370 | $273.09 | $220.00 | $305.00 | $305.00 | $305.00 | $300.70 | |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 617.50 | $290.00 | $281.85 | $210.00 | $305.00 | $305.00 | $295.00 | $294.17 |
| 23 | Prestressed concrete box beam (4B28) (425-7028) | LF | 298 | $283.76 | $300.00 | $375.00 | $375.00 | $272.00 | $357.55 | |
| 24 | Prestressed concrete box beam (5B28) (425-7029) | LF | 149 | $338.63 | $300.00 | $375.00 | $375.00 | $322.00 | $399.83 | |
| 25 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,694 | $200.00 | $147.15 | $150.00 | $170.00 | $135.00 | $160.00 | $166.98 |
| 26 | Rail (type T223) (450-7008) | LF | 690 | $170.00 | $196.20 | $150.00 | $220.00 | $165.00 | $150.00 | $165.62 |
| 27 | Type A joint (454-7001) | LF | 266 | $65.00 | $76.00 | $60.00 | $75.00 | $40.00 | $40.00 | $41.03 |
| 28 | RC pipe (CL IV)(18 in) (464-7019) | LF | 25 | $100.00 | $119.90 | $100.00 | $60.00 | $120.00 | $160.00 | $306.53 |
| 29 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,350.00 | $1,199.00 | $1,300.00 | $1,200.00 | $1,500.00 | $1,550.00 | $1,865.01 |
| 30 | Removing structure (pipe) (496-7007) | LF | 21 | $20.00 | $16.35 | $20.00 | $20.00 | $20.00 | $40.00 | $49.31 |
| 31 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 5 | $11,250 | $10,900 | $22,000 | $12,000 | $16,500 | $12,750 | $24,980 |
| 32 | Mobilization (500-7001) | LS | 1 | $54,730 | $100,000 | $216,715 | $200,000 | $220,000 | $250,000 | $112,850 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $5,000.00 | $1,090.00 | $1,000.00 | $4,500.00 | $1,500.00 | $3,000.00 | $2,494.90 |
| 34 | Rock filter dams (install) (type 1) (506-7001) | LF | 664 | $40.00 | $43.85 | $30.00 | $1.00 | $45.00 | $30.00 | $44.98 |
| 35 | Rock filter dams (remove) (506-7011) | LF | 664 | $10.00 | $13.70 | $10.00 | $1.00 | $10.00 | $10.00 | $14.03 |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 3,737 | $5.14 | $3.27 | $4.00 | $1.00 | $6.00 | $4.00 | $5.30 |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 3,737 | $1.50 | $1.09 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 38 | Driveways (surface treat) (530-7016) | SY | 56 | $35.00 | $49.05 | $65.00 | $95.00 | $50.00 | $125.00 | $82.60 |
| 39 | Metal W-beam guard fence (steel post) (540-7002) | LF | 375 | $34.00 | $32.70 | $26.00 | $30.00 | $33.00 | $32.00 | $31.59 |
| 40 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 20 | $1,500.00 | $2,398.00 | $2,250.00 | $2,200.00 | $3,100.00 | $2,300.00 | $2,799.28 |
| 41 | Downstream anchor terminal section (540-7015) | EACH | 10 | $1,400.00 | $1,308.00 | $1,300.00 | $1,500.00 | $1,300.00 | $1,375.00 | $1,593.75 |
| 42 | Guardrail end treatment (install) (544-7001) | EACH | 10 | $3,350.00 | $3,270.00 | $2,800.00 | $3,000.00 | $3,100.00 | $3,165.00 | $3,000.00 |
| 43 | Remove and install existing gate (550-7017) | EACH | 1 | $2,000.00 | $2,725.00 | $900.00 | $500.00 | $2,000.00 | $2,250.00 | $1,500.00 |
| 44 | Wire fence (type C) (552-7003) | LF | 1,543 | $20.00 | $16.35 | $25.00 | $20.00 | $15.00 | $20.00 | $16.26 |
| 45 | Remove SM RD SN sup&AM (644-7073) | EACH | 5 | $163.50 | $100.00 | $50.00 | $50.00 | $176.00 | $173.84 | |
| 46 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 24 | $40.00 | $21.80 | $40.00 | $20.00 | $22.00 | $35.00 | $31.40 |
| 47 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 40 | $40.00 | $49.05 | $40.00 | $45.00 | $50.00 | $45.00 | $44.84 |
| 48 | Rem lead-containing coating(location) (5011-7001) | EACH | 1 | $9,810.00 | $7,875.00 | $500.00 | $5,000.00 | $7,501.00 | $7,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.