TxDOT contract A00176955 bid tabulation
Intersection Improvements With Right And/Or Left Turn Lanes, SH 80 (.5 Mi N of FM 792 to .5 MI S of FM 792). Let by Texas DOT on December 2, 2025, Karnes, Corpus Christi District. 5 bids received; low bid $11,964,433 by Relmco, Inc., +8.3% against the engineer's estimate of $11,047,663.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 118
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Relmco, Inc. | $11,964,433 | Low | +8.0% |
| 2 | Hunter Industries, LTD. | $12,123,721 | +1.0% | +10% |
| 3 | E-Z Bel Construction, LLC | $13,596,031 | +14% | +23% |
| 4 | R Construction Civil, LLC | $13,735,035 | +15% | +24% |
| 5 | Ragle Construction, Inc. | $16,675,536 | +39% | +51% |
Engineer's estimate: $11,047,663.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Relmco, Inc. | 2. Hunter Industries, LTD. | 3. E-Z Bel Construction, LLC | 4. R Construction Civil, LLC | 5. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 47 | $1,500.00 | $3,500.00 | $1,820.40 | $6,000.00 | $1,750.00 | $35,000 |
| 2 | Removing concrete (mowstrip) (104-7004) | CY | 400 | $94.00 | $70.00 | $22.96 | $291.00 | $40.00 | $10.00 |
| 3 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 6,148 | $8.00 | $6.00 | $5.46 | $10.00 | $7.00 | $12.70 |
| 4 | Excavation (roadway) (110-7001) | CY | 15,530.84 | $10.80 | $15.00 | $15.32 | $15.75 | $20.00 | $23.20 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 7,329.25 | $18.00 | $18.00 | $15.32 | $65.00 | $22.00 | $18.00 |
| 6 | Compost manuf topsoil (4") (161-7002) | SY | 28,615 | $2.50 | $0.86 | $0.84 | $1.00 | $0.80 | $0.79 |
| 7 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 5.95 | $2,000.00 | $713.76 | $687.28 | $649.00 | $650.00 | $648.88 |
| 8 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 5.95 | $1,000.00 | $594.28 | $572.23 | $540.00 | $540.00 | $540.27 |
| 9 | Vegetative watering (168-7001) | TGL | 525.40 | $22.00 | $50.00 | $22.96 | $115.00 | $48.00 | $47.45 |
| 10 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 8,718 | $60.00 | $73.00 | $61.57 | $75.00 | $93.00 | $92.00 |
| 11 | Lime (com or QK)(slurry) (260-7005) | TON | 130 | $345.00 | $340.00 | $336.96 | $498.00 | $330.00 | $312.00 |
| 12 | Lime TRT (subgrade) (11") (260-7023) | SY | 10,461 | $10.00 | $2.00 | $2.75 | $4.00 | $5.00 | $3.70 |
| 13 | Cement (275-7001) | TON | 597 | $212.00 | $220.00 | $199.80 | $286.00 | $195.00 | $183.00 |
| 14 | Cement TRT (subgrade) (8") (275-7018) | SY | 5,865 | $8.13 | $2.00 | $2.20 | $3.75 | $6.40 | $2.83 |
| 15 | Cement TRT (new base)(9") (275-7019) | SY | 8,414 | $3.00 | $5.00 | $2.20 | $6.00 | $6.40 | $6.60 |
| 16 | Prime coat (MC-30) (310-7004) | GAL | 4,322 | $9.00 | $4.77 | $4.44 | $5.00 | $4.00 | $7.50 |
| 17 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 290 | $129.00 | $254.40 | $118.04 | $240.00 | $155.00 | $150.47 |
| 18 | Asphalt (multi option) (316-7263) | GAL | 10,982 | $4.00 | $5.30 | $2.93 | $5.00 | $4.00 | $4.75 |
| 19 | D-GR HMA type-B sac-B PG70-22 (341-7007) | TON | 4,958 | $75.00 | $103.88 | $86.80 | $98.00 | $160.00 | $159.00 |
| 20 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 3,855 | $112.00 | $116.60 | $92.20 | $110.00 | $160.00 | $159.00 |
| 21 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 11.63 | $130.00 | $371.00 | $137.02 | $350.00 | $160.00 | $297.00 |
| 22 | Tack coat (341-7082) | GAL | 2,462 | $4.00 | $3.71 | $3.25 | $4.00 | $1.80 | $5.50 |
| 23 | Planing asphalt concrete pavement(0" to 1") (354-7031) | SY | 6,576 | $1.50 | $3.18 | $1.41 | $3.00 | $1.15 | $1.82 |
| 24 | Planing asphalt concrete pavement(2") (354-7051) | SY | 2,751 | $1.25 | $4.25 | $3.02 | $4.00 | $2.75 | $3.70 |
| 25 | Planing asphalt concrete pavement(5") (354-7054) | SY | 2,615 | $3.75 | $6.36 | $3.02 | $6.00 | $2.75 | $4.95 |
| 26 | Struct excavation (pipe) (400-7003) | CY | 167 | $10.00 | $25.00 | $43.02 | $21.00 | $17.00 | $36.60 |
| 27 | Cem stabil BKFL (400-7010) | CY | 379 | $225.00 | $185.00 | $246.22 | $252.00 | $135.00 | $144.20 |
| 28 | Trench excavation protection (402-7001) | LF | 1,131 | $3.94 | $15.00 | $11.72 | $3.00 | $5.00 | $8.62 |
| 29 | Temporary special shoring (403-7001) | SF | 2,978 | $19.00 | $22.87 | $24.00 | $53.00 | $42.72 | |
| 30 | Foundaton loadtest(D4945)(drilld shaft) (405-7003) | EACH | 1 | $27,500 | $46,698 | $25,000 | $38,000 | $25,000 | |
| 31 | Drilled shaft (18 in) (416-7002) | LF | 150 | $125.00 | $264.33 | $271.00 | $290.00 | $127.70 | |
| 32 | Drilled shaft (36 in) (416-7006) | LF | 1,144 | $415.00 | $432.36 | $374.00 | $500.00 | $241.20 | |
| 33 | Drilled shaft (60 in) (416-7010) | LF | 795 | $890.00 | $865.29 | $890.00 | $880.00 | $698.00 | |
| 34 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 90 | $280.00 | $397.75 | $215.66 | $270.00 | $290.00 | $231.34 |
| 35 | Class C concrete (abutment) (420-7012) | CY | 85.40 | $1,507.80 | $1,600.00 | $1,400.00 | $1,200.00 | $1,058.00 | |
| 36 | Class C concrete (cap) (420-7022) | CY | 31 | $1,064.40 | $1,500.00 | $1,250.00 | $2,000.00 | $1,692.00 | |
| 37 | Class C concrete (cap)(mass) (420-7024) | CY | 227.60 | $1,066.40 | $1,150.00 | $1,375.00 | $1,800.00 | $1,030.00 | |
| 38 | Class C concrete (column) (420-7038) | CY | 22.10 | $1,120.00 | $1,050.00 | $1,550.00 | $2,100.00 | $1,517.90 | |
| 39 | Class C concrete (column)(mass) (420-7040) | CY | 248.30 | $1,022.00 | $1,100.00 | $1,200.00 | $1,500.00 | $1,416.00 | |
| 40 | Reinforced concrete slab (422-7001) | SF | 36,633 | $24.78 | $29.00 | $26.00 | $28.00 | $26.00 | |
| 41 | Approach slab (422-7013) | CY | 102.80 | $535.00 | $700.00 | $803.00 | $1,300.00 | $628.00 | |
| 42 | Prestressed concrete girder (TX46) (425-7004) | LF | 2,011.50 | $225.00 | $190.00 | $265.00 | $275.00 | $195.00 | |
| 43 | Riprap (concrete)(5 in) (432-7002) | CY | 23 | $531.00 | $575.00 | $727.39 | $739.00 | $810.00 | $656.80 |
| 44 | Riprap (concrete)(CL B) (432-7005) | CY | 3.15 | $800.00 | $800.00 | $1,050.00 | $966.00 | $2,500.00 | $971.00 |
| 45 | Riprap (mow strip)(4 in) (432-7013) | CY | 67 | $495.00 | $575.00 | $705.00 | $924.00 | $615.00 | $664.00 |
| 46 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,611 | $135.00 | $200.00 | $175.00 | $230.00 | $201.60 | |
| 47 | Elastomeric bearing (EE4) (434-7006) | EACH | 14 | $1,200.00 | $5,705.22 | $5,745.00 | $1,025.00 | $1,798.00 | |
| 48 | Elastomeric bearing (F7) (434-7037) | EACH | 7 | $1,200.00 | $8,227.79 | $3,830.00 | $1,025.00 | $3,936.00 | |
| 49 | STR steel (plate girder) (442-7001) | LB | 1,183,531 | $2.45 | $2.74 | $2.83 | $2.85 | $2.25 | |
| 50 | Rail (type SSTR) (450-7024) | LF | 1,174 | $75.00 | $70.19 | $61.00 | $100.00 | $65.50 | |
| 51 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 263 | $185.00 | $292.32 | $259.00 | $165.00 | $184.60 | |
| 52 | RC pipe (CL III)(18 in) (464-7003) | LF | 330 | $80.00 | $68.00 | $93.80 | $106.00 | $110.00 | $81.20 |
| 53 | RC pipe (CL III)(30 in) (464-7007) | LF | 800 | $124.00 | $98.00 | $134.84 | $128.00 | $135.00 | $129.00 |
| 54 | Inlet (complete)(PSL)(RC)(4FTX4FT) (465-7071) | EACH | 2 | $6,700.00 | $3,950.00 | $8,676.35 | $10,267 | $6,300.00 | $10,688 |
| 55 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 2 | $4,800.00 | $4,865.00 | $5,393.40 | $6,677.00 | $3,600.00 | $6,183.00 |
| 56 | Inlet (complete)(PSL)(FG)(4FTX4FT-3FTX3FT) (465-7127) | EACH | 2 | $9,100.00 | $6,375.00 | $7,503.87 | $8,827.00 | $5,300.00 | $10,204 |
| 57 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 1 | $2,400.00 | $1,900.00 | $3,282.94 | $3,000.00 | $2,600.00 | $2,952.00 |
| 58 | Pipe (PVC) (schedule 80) (4 in) (481-7025) | LF | 282 | $10.00 | $13.54 | $123.00 | $16.00 | $34.50 | |
| 59 | Removing structure (bridge 500 - 999 FT length) (496-7011) | EACH | 1 | $450,000 | $485,942 | $450,000 | $400,000 | $1,200,000 | |
| 60 | Removing structure (pipe) (496-7037) | EACH | 1 | $500.00 | $2,500.00 | $2,931.20 | $537.00 | $1,200.00 | $362.00 |
| 61 | Mobilization (500-7001) | LS | 1 | $1,093,620 | $1,000,000 | $912,868 | $1,000,000 | $900,000 | $1,645,000 |
| 62 | Barricades, signs and traffic handling (502-7001) | MO | 22 | $4,300.00 | $4,000.00 | $4,134.27 | $1,002.00 | $1,650.00 | $68,180 |
| 63 | Portable changeable message sign (503-7001) | DAY | 24 | $110.00 | $300.00 | $115.06 | $1,034.00 | $475.00 | $500.00 |
| 64 | Rock filter dams (install) (type 2) (506-7007) | CY | 9 | $300.00 | $142.47 | $498.26 | $470.00 | $500.00 | $470.42 |
| 65 | Rock filter dams (remove) (506-7012) | CY | 9 | $1.25 | $38.48 | $137.18 | $130.00 | $140.00 | $129.52 |
| 66 | Construction exits (install) (type 1) (506-7020) | SY | 312 | $30.00 | $12.67 | $37.05 | $35.00 | $66.00 | $34.98 |
| 67 | Construction exits (remove) (506-7024) | SY | 312 | $14.00 | $5.36 | $12.20 | $12.00 | $14.00 | $11.52 |
| 68 | Temporary sediment control fence (install) (506-7039) | LF | 60 | $2.00 | $1.67 | $5.17 | $5.00 | $5.00 | $4.88 |
| 69 | Temporary sediment control fence (remove) (506-7041) | LF | 60 | $1.25 | $8.25 | $1.61 | $2.00 | $1.60 | $1.52 |
| 70 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 80 | $10.00 | $8.25 | $7.94 | $8.00 | $8.00 | $7.50 |
| 71 | Biodegradable erosion control logs (remove) (506-7046) | LF | 80 | $3.00 | $1.67 | $1.61 | $2.00 | $1.55 | $1.52 |
| 72 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 1,920 | $15.00 | $30.00 | $50.00 | $92.00 | $72.00 | $77.00 |
| 73 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 1,920 | $8.50 | $12.00 | $13.00 | $27.00 | $3.30 | $7.30 |
| 74 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 1,920 | $6.00 | $25.00 | $20.00 | $26.00 | $5.50 | $9.00 |
| 75 | Intersections (ACP) (530-7002) | SY | 750 | $68.50 | $85.00 | $54.52 | $80.00 | $22.00 | $163.00 |
| 76 | Driveways (ACP) (530-7010) | SY | 943 | $31.00 | $45.00 | $41.40 | $25.00 | $31.00 | $83.50 |
| 77 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 11,244 | $0.20 | $0.50 | $0.62 | $1.00 | $0.50 | $0.20 |
| 78 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 6,944 | $0.24 | $0.50 | $0.45 | $1.00 | $0.50 | $0.15 |
| 79 | Metal W-beam guard fence (timber post) (540-7001) | LF | 725 | $27.00 | $25.85 | $25.17 | $25.00 | $25.00 | $22.00 |
| 80 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,459.00 | $2,029.50 | $1,946.00 | $1,964.00 | $1,700.00 | $2,300.00 |
| 81 | Remove metal beam guard fence (542-7001) | LF | 930 | $2.40 | $11.00 | $4.00 | $4.00 | $3.30 | $3.00 |
| 82 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,090.00 | $3,245.00 | $3,443.00 | $3,443.00 | $3,400.00 | $3,050.00 |
| 83 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $750.00 | $800.00 | $925.00 | $925.00 | $2,400.00 | $1,415.00 |
| 84 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $534.00 | $600.00 | $925.00 | $925.00 | $850.00 | $1,188.00 |
| 85 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 2 | $7,886.00 | $8,350.00 | $8,250.00 | $8,250.00 | $6,600.00 | $7,483.00 |
| 86 | In RD IL (type SA) 50T-10 (400W EQ) LED (610-7198) | EACH | 9 | $6,000.00 | $12,060 | $5,585.65 | $6,900.00 | $6,750.00 | $5,549.42 |
| 87 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,630 | $10.00 | $30.60 | $7.55 | $15.00 | $14.00 | $11.49 |
| 88 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 390 | $25.00 | $64.80 | $30.19 | $28.00 | $20.00 | $17.46 |
| 89 | Electrical conductor (no.12) insulated (620-7004) | LF | 6,260 | $1.50 | $3.33 | $0.86 | $1.00 | $1.00 | $0.90 |
| 90 | Ground box type A (122311)W/apron (624-7002) | EACH | 4 | $1,500.00 | $280.00 | $916.56 | $1,150.00 | $1,400.00 | $1,189.63 |
| 91 | Elc SRV type A 240/480 060(NS)SS(E)GC(O) (628-7044) | EACH | 1 | $10,000 | $22,770 | $7,332.51 | $13,500 | $10,500 | $9,149.03 |
| 92 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 18 | $1,300.00 | $880.00 | $800.00 | $775.00 | $850.00 | $784.45 |
| 93 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 5 | $879.00 | $990.00 | $900.00 | $1,050.00 | $1,100.00 | $960.74 |
| 94 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 11 | $1,098.00 | $1,100.00 | $1,000.00 | $1,200.00 | $1,300.00 | $801.23 |
| 95 | Remove SM RD SN sup&AM (644-7073) | EACH | 25 | $125.00 | $110.00 | $100.00 | $75.00 | $80.00 | $109.59 |
| 96 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 24,088 | $0.63 | $0.35 | $0.32 | $0.32 | $0.35 | $0.32 |
| 97 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 34,028 | $0.50 | $0.35 | $0.32 | $0.32 | $0.35 | $0.32 |
| 98 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,300 | $1.30 | $3.00 | $1.53 | $2.75 | $1.50 | $2.37 |
| 99 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 583 | $1.24 | $3.00 | $1.53 | $2.75 | $1.75 | $1.85 |
| 100 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 666 | $1.75 | $1.21 | $1.10 | $1.00 | $1.15 | $1.10 |
| 101 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 318 | $1.10 | $1.21 | $1.10 | $1.00 | $1.15 | $1.10 |
| 102 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 1,105 | $1.25 | $1.21 | $1.10 | $1.00 | $1.15 | $1.10 |
| 103 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 600 | $3.00 | $2.20 | $2.00 | $2.00 | $2.00 | $2.00 |
| 104 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 440 | $0.50 | $1.21 | $1.10 | $1.00 | $1.15 | $1.10 |
| 105 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 17,171 | $0.50 | $1.07 | $0.88 | $1.00 | $1.00 | $0.98 |
| 106 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 19,418 | $0.75 | $1.07 | $0.88 | $1.00 | $1.00 | $0.98 |
| 107 | PRFB rumble strip (BLK)(4')(transverse) (668-7001) | LF | 40 | $20.00 | $10.00 | $16.00 | $16.00 | $25.00 | $21.27 |
| 108 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 44 | $16.00 | $17.60 | $16.00 | $16.00 | $17.00 | $16.00 |
| 109 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 6 | $210.00 | $220.00 | $200.00 | $200.00 | $215.00 | $200.00 |
| 110 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $400.00 | $550.00 | $500.00 | $500.00 | $525.00 | $500.00 |
| 111 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 6 | $253.00 | $330.00 | $300.00 | $300.00 | $325.00 | $300.00 |
| 112 | Prefabricated PM type C (Y)(24")(solid) (668-7127) | LF | 475 | $16.00 | $19.80 | $18.00 | $18.00 | $19.00 | $18.00 |
| 113 | Reflectorized pavement marker type I-C (672-7002) | EACH | 211 | $5.00 | $8.25 | $7.50 | $8.00 | $8.00 | $7.50 |
| 114 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 972 | $8.25 | $8.25 | $7.50 | $8.00 | $8.00 | $7.50 |
| 115 | Traffic button type Y (672-7008) | EACH | 222 | $3.00 | $6.00 | $7.50 | $8.00 | $20.00 | $4.06 |
| 116 | Eliminating existing PM & markers (4") (677-7001) | LF | 22,161 | $0.50 | $0.33 | $0.30 | $0.30 | $0.35 | $0.30 |
| 117 | Eliminating existing PM & markers (rumble strip) (677-7030) | LF | 11,082 | $5.00 | $0.49 | $0.45 | $0.45 | $0.45 | $0.45 |
| 118 | Tip testing(drilled shaft) (4003-7001) | EACH | 3 | $5,500.00 | $11,502 | $5,000.00 | $5,000.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.