TxDOT contract A00178602 bid tabulation
Widen Road - Add Shoulders, FM 1977 (FM 621 to Guadalupe/Caldwell County Line). Let by Texas DOT on January 8, 2025, Guadalupe, San Antonio District. 5 bids received; low bid $1,001,033 by Hunter Industries, LTD., -48% against the engineer's estimate of $1,929,704.
- Owner
- Texas DOT
- Letting
- 08 JAN 2025
- Pay items
- 70
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $1,001,033 | Low | -48% |
| 2 | Dan Williams Company | $1,292,451 | +29% | -33% |
| 3 | CK Newberry, LLC | $1,330,285 | +33% | -31% |
| 4 | LCR Total Transport LLC | $1,381,668 | +38% | -28% |
| 5 | Dean Word Company, LTD. | $1,398,963 | +40% | -28% |
Engineer's estimate: $1,929,704.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. Dan Williams Company | 3. CK Newberry, LLC | 4. LCR Total Transport LLC | 5. Dean Word Company, LTD. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 17 | $22,000 | $1,750.00 | $7,000.00 | $3,000.00 | $5,960.00 | $3,500.00 |
| 2 | Tree protection (install) (100-7013) | EACH | 6 | $650.00 | $1,000.00 | $1,000.00 | $200.00 | $850.00 | $1,740.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 302 | $32.00 | $50.00 | $25.00 | $14.71 | $25.00 | $41.00 |
| 4 | Remove (17") TRT/untrt base & asphalt pavement (105-7037) | SY | 4,384 | $20.00 | $18.00 | $14.00 | $18.00 | $24.00 | $12.50 |
| 5 | Excavation (roadway) (110-7001) | CY | 2,928.90 | $45.00 | $39.00 | $35.00 | $24.00 | $30.00 | $31.50 |
| 6 | Embankment (final)(OC)(type D) (132-7011) | CY | 400.50 | $90.00 | $34.00 | $60.00 | $30.00 | $36.00 | $23.00 |
| 7 | Furn & place topsoil (4") (160-7002) | SY | 6,410 | $6.50 | $1.50 | $1.50 | $2.50 | $2.50 | $6.50 |
| 8 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 6,410 | $4.00 | $0.31 | $0.26 | $0.30 | $0.30 | $0.50 |
| 9 | Vegetative watering (168-7001) | TGL | 101 | $200.00 | $46.00 | $15.00 | $50.00 | $56.00 | $177.50 |
| 10 | Soil ret BLKT(SL_mod_clay_short_roll) (169-7009) | SY | 340 | $3.40 | $3.85 | $1.00 | $5.00 | $4.00 | $5.00 |
| 11 | FL BS (roadway del)(type A GR 1-2)(final pos) (247-7259) | CY | 1,325 | $85.00 | $63.00 | $50.00 | $100.00 | $111.00 | $100.00 |
| 12 | FL BS (roadway del)(type D GR 1-2)(final pos) (247-7271) | CY | 21 | $57.00 | $263.00 | $80.00 | $200.00 | $82.00 | $100.00 |
| 13 | Rework BS metal (type B)(8")(ord comp) (251-7027) | SY | 6,580 | $23.00 | $5.75 | $11.00 | $10.00 | $19.75 | $16.50 |
| 14 | Cement (275-7001) | TON | 75 | $400.00 | $306.00 | $225.00 | $225.00 | $255.00 | $310.00 |
| 15 | Cement TRT (new base)(8") (275-7011) | SY | 6,191 | $22.00 | $2.95 | $8.50 | $10.00 | $1.75 | $7.00 |
| 16 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,238 | $10.00 | $6.60 | $5.00 | $8.00 | $5.25 | $6.50 |
| 17 | Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071) | GAL | 3,705 | $6.00 | $6.25 | $6.25 | $6.00 | $5.35 | $5.00 |
| 18 | Aggregate (type-PB, GR-3)(sac-B) (316-7208) | CY | 55 | $150.00 | $165.00 | $450.00 | $450.00 | $251.00 | $276.00 |
| 19 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 48 | $230.00 | $175.00 | $450.00 | $325.00 | $251.00 | $304.50 |
| 20 | Cut & restoring pavement (400-7006) | SY | 53 | $220.00 | $350.00 | $225.00 | $100.00 | $150.00 | $389.00 |
| 21 | Cem stabil BKFL (400-7010) | CY | 68 | $240.00 | $210.00 | $300.00 | $225.00 | $180.00 | $331.00 |
| 22 | Trench excavation protection (402-7001) | LF | 20 | $45.00 | $102.00 | $1.00 | $50.00 | $82.00 | $22.00 |
| 23 | Riprap (concrete)(5 in) (432-7002) | CY | 142.20 | $715.00 | $479.00 | $525.00 | $650.00 | $696.00 | $800.00 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 6 | $650.00 | $753.00 | $750.00 | $1,000.00 | $1,050.00 | $934.50 |
| 25 | RC pipe (CL III)(18 in) (464-7003) | LF | 22 | $130.00 | $134.00 | $275.00 | $150.00 | $77.00 | $165.50 |
| 26 | RC pipe (CL III)(24 in) (464-7005) | LF | 57 | $200.00 | $150.00 | $250.00 | $150.00 | $95.00 | $209.50 |
| 27 | RC pipe (CL IV)(18 in) (464-7019) | LF | 96 | $320.00 | $113.00 | $165.00 | $125.00 | $88.00 | $214.50 |
| 28 | RC pipe (arch)(CL III)(des 1) (464-7040) | LF | 66 | $300.00 | $225.00 | $300.00 | $175.00 | $204.00 | $467.50 |
| 29 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 4 | $2,400.00 | $1,284.00 | $2,500.00 | $3,000.00 | $1,725.00 | $3,456.50 |
| 30 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,800.00 | $1,498.00 | $3,000.00 | $3,100.00 | $2,050.00 | $4,242.50 |
| 31 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $2,800.00 | $2,139.00 | $3,250.00 | $3,200.00 | $2,500.00 | $4,717.00 |
| 32 | Set (type II) (des 1) (RCP) (6: 1) (P) (467-7418) | EACH | 2 | $2,700.00 | $4,626.00 | $3,750.00 | $4,500.00 | $3,990.00 | $5,292.00 |
| 33 | Removing structure (set) (496-7004) | EACH | 7 | $650.00 | $535.00 | $500.00 | $5,000.00 | $712.00 | $1,270.00 |
| 34 | Removing structure (pipe) (496-7007) | LF | 239 | $60.00 | $27.00 | $25.00 | $30.00 | $30.00 | $81.00 |
| 35 | Mobilization (500-7001) | LS | 1 | $167,791 | $92,067 | $120,000 | $130,000 | $200,000 | $100,000 |
| 36 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $12,000 | $4,793.67 | $17,500 | $20,000 | $3,007.00 | $1,405.00 |
| 37 | Portable changeable message sign (503-7002) | EACH | 3 | $12,500 | $3,591.93 | $12,000 | $15,000 | $12,900 | $11,429 |
| 38 | TMA (stationary) (505-7001) | DAY | 10 | $350.00 | $359.19 | $300.00 | $325.00 | $415.00 | $529.00 |
| 39 | TMA (mobile operation) (505-7002) | HR | 8 | $100.00 | $153.94 | $75.00 | $100.00 | $117.00 | $213.00 |
| 40 | Rock filter dams (install) (type 2) (506-7002) | LF | 200 | $50.00 | $39.82 | $46.00 | $40.00 | $54.00 | $53.50 |
| 41 | Rock filter dams (remove) (506-7011) | LF | 200 | $20.00 | $8.36 | $25.00 | $8.00 | $29.00 | $11.00 |
| 42 | Temporary sediment control fence (install) (506-7039) | LF | 1,170 | $5.60 | $3.85 | $4.00 | $4.00 | $4.50 | $5.00 |
| 43 | Temporary sediment control fence (remove) (506-7041) | LF | 1,170 | $1.70 | $0.55 | $1.00 | $1.00 | $1.00 | $0.50 |
| 44 | One-way traffic control (port traffic signal) (510-7003) | MO | 6 | $4,200.00 | $9,983.33 | $4,000.00 | $5,000.00 | $11,500 | $15,788 |
| 45 | Driveways (concrete) (530-7006) | SY | 253 | $125.00 | $116.15 | $135.00 | $175.00 | $175.00 | $158.00 |
| 46 | Short radius (28") (540-7013) | LF | 100 | $175.00 | $50.77 | $49.00 | $60.00 | $55.00 | $71.00 |
| 47 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,800.00 | $1,645.35 | $1,600.00 | $2,250.00 | $1,780.00 | $2,306.50 |
| 48 | Metal beam guard fence trans (31"-28")(25') (540-7031) | EACH | 1 | $1,300.00 | $1,293.60 | $1,300.00 | $1,150.00 | $1,400.00 | $1,813.00 |
| 49 | Remove metal beam guard fence (542-7001) | LF | 100 | $7.00 | $2.10 | $3.00 | $10.00 | $2.25 | $3.00 |
| 50 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $250.00 | $126.00 | $150.00 | $600.00 | $137.00 | $176.50 |
| 51 | Relocate existing mailbox (560-7012) | EACH | 2 | $550.00 | $670.90 | $650.00 | $600.00 | $256.00 | $896.50 |
| 52 | Conduit (PVC) (schedule 40) (1") (618-7021) | LF | 7 | $25.00 | $52.06 | $75.00 | $50.00 | $45.00 | $110.50 |
| 53 | Electrical conductor (no.12) insulated (620-7004) | LF | 7 | $2.25 | $11.16 | $10.00 | $10.00 | $10.00 | $14.50 |
| 54 | Ground box type A (122311)W/apron (624-7002) | EACH | 1 | $1,600.00 | $2,729.06 | $1,500.00 | $2,500.00 | $2,400.00 | $1,839.50 |
| 55 | Aluminum signs (type A) (636-7001) | SF | 86 | $45.00 | $35.26 | $27.00 | $50.00 | $28.50 | $39.00 |
| 56 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 16 | $900.00 | $756.82 | $700.00 | $1,000.00 | $800.00 | $1,011.00 |
| 57 | Remove SM RD SN sup&AM (644-7073) | EACH | 9 | $160.00 | $102.73 | $100.00 | $200.00 | $131.00 | $137.00 |
| 58 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BR) (658-7017) | EACH | 9 | $35.00 | $17.63 | $17.00 | $50.00 | $18.00 | $23.50 |
| 59 | Install object marker assembly (OM-2X)(WC)GND (658-7055) | EACH | 6 | $80.00 | $52.05 | $50.00 | $100.00 | $54.00 | $69.50 |
| 60 | Remove delin & object marker assms (658-7078) | EACH | 4 | $35.00 | $22.03 | $20.00 | $20.00 | $22.75 | $29.50 |
| 61 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 300 | $6.00 | $5.38 | $10.00 | $5.00 | $4.50 | $10.50 |
| 62 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 46 | $16.00 | $20.19 | $25.00 | $20.00 | $17.00 | $37.00 |
| 63 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 20 | $11.00 | $20.19 | $20.00 | $20.00 | $17.00 | $29.50 |
| 64 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 3,099 | $6.00 | $3.36 | $3.00 | $3.00 | $3.00 | $4.50 |
| 65 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 2,949 | $1.80 | $3.36 | $3.00 | $3.00 | $3.00 | $4.50 |
| 66 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 37 | $8.50 | $10.09 | $7.75 | $10.00 | $8.50 | $11.50 |
| 67 | Eliminating existing PM & markers (4") (677-7001) | LF | 4,377 | $1.50 | $1.62 | $3.00 | $2.00 | $1.40 | $2.50 |
| 68 | Eliminating existing PM & markers (6") (677-7002) | LF | 3,400 | $1.00 | $2.29 | $3.00 | $2.00 | $2.00 | $3.00 |
| 69 | Eliminating existing PM & markers (24") (677-7008) | LF | 57 | $5.00 | $6.73 | $30.00 | $6.00 | $6.00 | $14.50 |
| 70 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 1 | $9,500.00 | $14,502 | $25,000 | $12,000 | $12,400 | $21,856 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.