TxDOT contract A00182660 bid tabulation
Bridge Replacement, IH 20 (SH 350 to @ IH 20). Let by Texas DOT on March 4, 2025, Howard, Abilene District. 6 bids received; low bid $14,287,270 by Ragle Construction, Inc., -14% against the engineer's estimate of $16,650,393.
- Owner
- Texas DOT
- Letting
- 04 MAR 2025
- Pay items
- 160
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ragle Construction, Inc. | $14,287,270 | Low | -14% |
| 2 | James Construction Group, LLC | $14,714,280 | +3.0% | -12% |
| 3 | Reece Albert, Inc. | $15,472,574 | +8.0% | -7.0% |
| 4 | Altus Construction LLC | $15,703,296 | +10% | -6.0% |
| 5 | Coppell Construction Co., Inc. | $15,757,313 | +10% | -5.0% |
| 6 | Gilvin-Terrill, LTD. | $17,976,912 | +26% | +8.0% |
Engineer's estimate: $16,650,393.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ragle Construction, Inc. | 2. James Construction Group, LLC | 3. Reece Albert, Inc. | 4. Altus Construction LLC | 5. Coppell Construction Co., Inc. | 6. Gilvin-Terrill, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 2,343 | $18.00 | $7.00 | $9.76 | $20.73 | $20.17 | $15.00 | $25.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 2,674 | $65.00 | $12.25 | $18.03 | $27.61 | $40.34 | $20.00 | $25.00 |
| 3 | Removing concrete (medians) (104-7008) | SY | 1,390 | $47.00 | $19.00 | $20.17 | $36.28 | $40.34 | $20.00 | $25.00 |
| 4 | Removing concrete (pavers) (104-7010) | SY | 191 | $16.00 | $25.78 | $43.37 | $12.30 | $20.00 | $25.00 | |
| 5 | Removing concrete (curb & gutter) (104-7017) | LF | 3,100 | $29.00 | $11.00 | $11.30 | $14.99 | $19.48 | $15.00 | $15.00 |
| 6 | Remove (14") TRT/untrt base & asphalt pavement (105-7034) | SY | 11,497 | $15.00 | $11.50 | $12.89 | $10.20 | $37.35 | $9.00 | $30.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 625 | $59.00 | $170.00 | $38.36 | $37.51 | $24.00 | $40.00 | $50.00 |
| 8 | Embankment (final)(DC)(type B) (132-7004) | CY | 4,001 | $54.00 | $50.00 | $53.19 | $69.56 | $100.68 | $70.00 | $50.00 |
| 9 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 1,993 | $2.00 | $0.75 | $2.50 | $2.77 | $1.01 | $2.50 | $3.00 |
| 10 | Broadcast seed (temporary_warm) (164-7005) | SY | 1,993 | $2.00 | $0.75 | $2.50 | $2.77 | $1.01 | $2.50 | $3.00 |
| 11 | Broadcast seed (temporary_cool) (164-7006) | SY | 1,993 | $2.00 | $0.75 | $2.50 | $2.77 | $1.01 | $2.50 | $3.00 |
| 12 | Vegetative watering (168-7001) | TGL | 39.10 | $115.00 | $60.00 | $58.94 | $180.55 | $36.89 | $200.00 | $70.00 |
| 13 | Loose aggregate GRND cover (192-7022) | SY | 169 | $35.00 | $30.00 | $80.87 | $44.98 | $35.30 | $10.00 | $13.50 |
| 14 | Prime coat (MC-30) (310-7004) | GAL | 2,485 | $20.00 | $7.00 | $14.00 | $13.89 | $8.07 | $11.00 | $16.00 |
| 15 | Tack coat (341-7082) | GAL | 3,975 | $22.00 | $5.50 | $15.00 | $16.62 | $5.07 | $20.00 | $15.00 |
| 16 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 5,466 | $250.00 | $212.00 | $259.00 | $285.86 | $338.54 | $200.00 | $265.00 |
| 17 | Cem stabil BKFL (400-7010) | CY | 604 | $381.00 | $100.00 | $288.36 | $308.03 | $265.15 | $215.00 | $500.00 |
| 18 | Temporary special shoring (403-7001) | SF | 228 | $50.00 | $52.30 | $90.19 | $40.34 | $200.00 | $200.00 | |
| 19 | Drilled shaft (36 in) (416-7006) | LF | 1,540 | $420.00 | $375.00 | $258.72 | $306.99 | $352.32 | $300.00 | $290.00 |
| 20 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 55 | $460.00 | $300.00 | $300.00 | $332.40 | $494.88 | $470.00 | $332.00 |
| 21 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 78 | $625.00 | $450.00 | $450.00 | $498.60 | $625.32 | $560.00 | $485.00 |
| 22 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 22 | $500.00 | $500.00 | $554.00 | $880.83 | $875.00 | $545.00 | |
| 23 | Class C concrete (abutment)(HPC) (420-7013) | CY | 160.90 | $2,200.00 | $1,280.00 | $1,435.80 | $2,363.59 | $1,710.68 | $1,750.00 | $2,000.00 |
| 24 | Class C concrete (cap)(HPC) (420-7023) | CY | 238.20 | $2,100.00 | $1,850.00 | $2,125.02 | $3,141.01 | $1,923.46 | $1,650.00 | $2,000.00 |
| 25 | Class C concrete (column)(HPC) (420-7039) | CY | 156 | $2,300.00 | $1,750.00 | $2,322.25 | $1,825.65 | $1,923.39 | $1,770.00 | $2,000.00 |
| 26 | Reinforced concrete slab (422-7001) | SF | 41,393 | $45.00 | $30.00 | $40.51 | $40.88 | $33.56 | $42.00 | $41.00 |
| 27 | Bridge sidewalk (422-7012) | SF | 7,514 | $45.00 | $12.00 | $36.77 | $22.07 | $73.93 | $21.00 | $21.00 |
| 28 | Approach slab (422-7013) | CY | 908 | $1,600.00 | $540.00 | $1,074.89 | $934.29 | $388.02 | $800.00 | $1,500.00 |
| 29 | Prestressed concrete girder (TX28) (425-7001) | LF | 2,728.11 | $290.00 | $448.72 | $334.29 | $374.02 | $340.00 | $250.00 | |
| 30 | Prestressed concrete X-beam (5XB20) (425-7035) | LF | 2,619.16 | $300.00 | $400.00 | $456.32 | $385.54 | $364.20 | $340.00 | $310.00 |
| 31 | Silicone resin paint finish (427-7004) | SF | 8,077 | $17.00 | $4.25 | $4.25 | $3.92 | $5.72 | $5.00 | $4.70 |
| 32 | Riprap (concrete)(4 in) (432-7001) | CY | 374 | $900.00 | $610.00 | $932.96 | $1,293.38 | $765.28 | $650.00 | $1,000.00 |
| 33 | Riprap (concrete)(5 in) (432-7002) | CY | 46 | $1,300.00 | $625.00 | $1,068.87 | $1,058.43 | $662.22 | $750.00 | $1,000.00 |
| 34 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 1,110 | $20.00 | $17.00 | $20.00 | $21.99 | $20.17 | $30.00 | $20.00 |
| 35 | Rail (type C221)(HPC) (450-7033) | LF | 1,042 | $190.00 | $130.00 | $220.70 | $194.37 | $345.81 | $235.00 | $285.00 |
| 36 | Rail (handrail)(type F) (450-7063) | LF | 24 | $233.00 | $280.00 | $283.90 | $362.74 | $191.71 | $430.00 | $310.00 |
| 37 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 429 | $265.00 | $190.00 | $293.62 | $342.81 | $219.78 | $225.00 | $250.00 |
| 38 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 2 | $450,000 | $869,000 | $106,000 | $268,311 | $136,151 | $300,000 | $1,300,000 |
| 39 | Removing structure (ret wall) (496-7019) | LF | 25 | $50.00 | $102.49 | $214.02 | $302.57 | $140.00 | $500.00 | |
| 40 | Mobilization (500-7001) | LS | 1 | $1,600,000 | $1,400,000 | $1,280,436 | $1,540,002 | $1,562,499 | $1,500,000 | $1,795,000 |
| 41 | Barricades, signs and traffic handling (502-7001) | MO | 20 | $40,000 | $55,000 | $12,856 | $25,009 | $31,938 | $85,000 | $50,000 |
| 42 | Portable changeable message sign (503-7002) | EACH | 5 | $35,000 | $27,868 | $13,599 | $9,694.62 | $15,000 | $18,500 | |
| 43 | TMA (stationary) (505-7001) | DAY | 120 | $252.00 | $450.00 | $1,142.51 | $523.03 | $224.18 | $275.00 | $700.00 |
| 44 | TMA (mobile operation) (505-7003) | DAY | 8 | $638.00 | $800.00 | $1,745.24 | $986.97 | $252.15 | $350.00 | $950.00 |
| 45 | Construction exits (install) (type 1) (506-7020) | SY | 888 | $35.00 | $35.00 | $48.00 | $43.92 | $34.29 | $40.00 | $40.00 |
| 46 | Construction exits (remove) (506-7024) | SY | 888 | $16.00 | $12.00 | $20.00 | $1.52 | $12.76 | $10.00 | $20.00 |
| 47 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 3,105 | $9.00 | $5.00 | $4.92 | $5.45 | $10.09 | $5.00 | $10.00 |
| 48 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,105 | $3.00 | $1.00 | $0.80 | $0.89 | $2.02 | $1.00 | $1.00 |
| 49 | Constructing detours (508-7001) | SY | 888 | $190.00 | $70.00 | $130.50 | $109.74 | $147.97 | $425.00 | $150.00 |
| 50 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 920 | $64.00 | $125.00 | $122.01 | $82.07 | $50.43 | $110.00 | $95.00 |
| 51 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 120 | $68.00 | $125.00 | $122.01 | $194.61 | $87.64 | $116.00 | $85.00 |
| 52 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 2,070 | $30.00 | $12.88 | $12.25 | $14.12 | $40.00 | $15.00 | |
| 53 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 2,070 | $17.00 | $10.00 | $5.71 | $13.93 | $11.09 | $20.00 | $15.00 |
| 54 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 1,680 | $12.00 | $10.00 | $7.41 | $32.27 | $15.13 | $20.00 | $15.00 |
| 55 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 320 | $12.00 | $10.00 | $7.61 | $16.43 | $14.82 | $20.00 | $15.00 |
| 56 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 2,140 | $19.00 | $10.00 | $12.46 | $21.64 | $12.10 | $25.00 | $15.00 |
| 57 | Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045) | LF | 920 | $17.00 | $10.00 | $13.47 | $16.78 | $17.15 | $25.00 | $9.99 |
| 58 | Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046) | LF | 120 | $17.00 | $10.00 | $11.37 | $65.70 | $22.19 | $120.00 | $15.00 |
| 59 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 1,920 | $122.00 | $130.00 | $255.98 | $176.54 | $155.27 | $200.00 | $160.00 |
| 60 | Concrete curb (type II) (529-7002) | LF | 575 | $58.00 | $14.00 | $44.52 | $60.95 | $72.78 | $50.00 | $50.00 |
| 61 | Concrete curb (type IV) (529-7005) | LF | 775 | $60.00 | $18.00 | $40.42 | $41.51 | $151.29 | $60.00 | $25.00 |
| 62 | Concrete curb & gutter (type II) (529-7009) | LF | 2,101 | $75.00 | $30.00 | $62.01 | $51.20 | $77.76 | $50.00 | $45.00 |
| 63 | Concrete sidewalks (4") (531-7001) | SY | 521 | $133.00 | $62.00 | $131.46 | $91.72 | $136.98 | $90.00 | $135.00 |
| 64 | Curb ramps (type 1) (531-7005) | EACH | 4 | $2,987.00 | $2,070.00 | $4,211.70 | $2,102.43 | $3,429.18 | $3,500.00 | $2,000.00 |
| 65 | Curb ramps (type 2) (531-7006) | EACH | 7 | $3,636.00 | $2,350.00 | $4,744.44 | $2,472.45 | $3,530.04 | $3,500.00 | $2,300.00 |
| 66 | Curb ramps (type 7) (531-7010) | EACH | 1 | $3,129.00 | $2,770.00 | $4,744.50 | $2,901.29 | $3,277.89 | $3,500.00 | $2,000.00 |
| 67 | Curb ramps (type 22) (531-7014) | EACH | 8 | $2,656.00 | $3,750.00 | $8,453.35 | $5,646.94 | $3,690.52 | $4,000.00 | $4,200.00 |
| 68 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $2,985.00 | $2,000.00 | $2,000.00 | $3,253.09 | $2,521.45 | $2,500.00 | $2,165.00 |
| 69 | Remove metal beam guard fence (542-7001) | LF | 1,525 | $4.00 | $3.00 | $3.00 | $2.22 | $3.25 | $3.00 | $2.00 |
| 70 | Remove terminal anchor section (542-7002) | EACH | 7 | $330.00 | $200.00 | $200.00 | $221.60 | $277.86 | $250.00 | $215.00 |
| 71 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $200.00 | $200.00 | $221.60 | $219.37 | $250.00 | $225.00 | |
| 72 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,765.00 | $3,000.00 | $3,000.00 | $9,972.01 | $3,360.13 | $3,500.00 | $3,165.00 |
| 73 | Guardrail end treatment (remove) (544-7003) | EACH | 8 | $439.00 | $200.00 | $200.00 | $221.60 | $322.75 | $230.00 | $325.00 |
| 74 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $4,327.00 | $1,100.00 | $2,500.00 | $488.85 | $1,659.12 | $3,000.00 | $1,600.00 |
| 75 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $2,410.00 | $1,100.00 | $1,000.00 | $733.28 | $1,008.58 | $1,200.00 | $800.00 |
| 76 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 6 | $10,000 | $8,700.00 | $5,992.79 | $10,020 | $10,000 | $7,825.00 | |
| 77 | Remove RD IL asm (trans-base) (610-7009) | EACH | 8 | $1,320.00 | $950.00 | $500.00 | $2,770.00 | $336.19 | $290.00 | $2,500.00 |
| 78 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 615 | $22.33 | $20.00 | $20.00 | $22.16 | $13.45 | $11.00 | $20.00 |
| 79 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,330 | $32.00 | $25.00 | $25.00 | $27.70 | $47.07 | $41.00 | $25.00 |
| 80 | Conduit (PVC) (schedule 80) (2") (concrete encse) (618-7057) | LF | 580 | $10.30 | $30.00 | $30.00 | $33.24 | $20.17 | $17.50 | $30.00 |
| 81 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 335 | $29.00 | $30.00 | $32.00 | $33.24 | $33.62 | $30.00 | $32.00 |
| 82 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 440 | $42.85 | $30.00 | $30.00 | $33.24 | $47.07 | $40.00 | $35.00 |
| 83 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 1,450 | $56.83 | $35.00 | $35.00 | $38.78 | $60.51 | $52.00 | $35.00 |
| 84 | Electrical conductor (no.8) bare (620-7007) | LF | 3,780 | $2.30 | $2.00 | $2.00 | $2.22 | $2.02 | $1.50 | $2.00 |
| 85 | Electrical conductor (no.8) insulated (620-7008) | LF | 5,350 | $5.50 | $2.50 | $2.50 | $2.77 | $2.02 | $1.50 | $2.50 |
| 86 | Electrical conductor (no.6) insulated (620-7010) | LF | 230 | $3.17 | $2.50 | $2.50 | $2.77 | $2.69 | $2.00 | $2.50 |
| 87 | Ground box type A (122311)W/apron (624-7002) | EACH | 8 | $1,540.00 | $1,200.00 | $1,200.00 | $1,329.60 | $2,353.36 | $1,800.00 | $1,200.00 |
| 88 | Ground box type D (162922) (624-7007) | EACH | 1 | $1,000.00 | $1,000.00 | $1,108.00 | $2,487.84 | $2,100.00 | $1,000.00 | |
| 89 | Ground box type D (162922)W/apron (624-7008) | EACH | 18 | $2,053.00 | $1,500.00 | $1,500.00 | $1,662.00 | $3,160.22 | $2,500.00 | $1,500.00 |
| 90 | Remove ground box (624-7013) | EACH | 5 | $400.00 | $400.00 | $443.20 | $201.72 | $250.00 | $400.00 | |
| 91 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 4 | $8,706.26 | $10,000 | $10,000 | $11,080 | $13,448 | $11,000 | $10,000 |
| 92 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 38 | $870.00 | $700.00 | $715.00 | $792.22 | $961.51 | $830.00 | $700.00 |
| 93 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 11 | $1,000.00 | $932.00 | $891.00 | $987.23 | $1,198.20 | $1,000.00 | $932.00 |
| 94 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 8 | $1,300.00 | $1,205.00 | $1,092.00 | $1,209.94 | $1,468.50 | $1,200.00 | $1,205.00 |
| 95 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 8 | $1,217.00 | $1,355.00 | $1,226.00 | $1,358.41 | $1,648.70 | $1,450.00 | $1,355.00 |
| 96 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 4 | $3,445.00 | $2,490.00 | $1,405.00 | $1,556.74 | $1,889.41 | $1,630.00 | $2,490.00 |
| 97 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 1 | $547.00 | $235.00 | $300.00 | $332.40 | $403.43 | $350.00 | $235.00 |
| 98 | Remove SM RD SN sup&AM (644-7073) | EACH | 73 | $226.00 | $100.00 | $175.00 | $163.56 | $115.99 | $125.00 | $90.00 |
| 99 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 1 | $129.00 | $100.00 | $107.00 | $118.56 | $149.89 | $125.00 | $40.00 |
| 100 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 16 | $31.00 | $45.00 | $45.00 | $49.86 | $60.51 | $50.00 | $44.00 |
| 101 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014) | EACH | 16 | $40.00 | $45.00 | $45.00 | $50.97 | $61.86 | $50.00 | $44.50 |
| 102 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 4 | $175.00 | $45.00 | $45.00 | $49.86 | $60.51 | $50.00 | $44.00 |
| 103 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 16 | $41.00 | $45.00 | $45.00 | $50.97 | $61.86 | $50.00 | $44.50 |
| 104 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 4 | $56.00 | $45.00 | $45.00 | $49.86 | $60.51 | $50.00 | $44.00 |
| 105 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 100 | $2.00 | $2.00 | $2.22 | $2.69 | $2.00 | $2.00 | |
| 106 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 90 | $3.00 | $3.00 | $3.32 | $4.03 | $3.00 | $3.00 | |
| 107 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 13,770 | $1.50 | $1.15 | $1.15 | $1.27 | $1.55 | $1.25 | $1.15 |
| 108 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 500 | $1.50 | $1.50 | $1.66 | $2.02 | $1.50 | $1.50 | |
| 109 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 499 | $16.00 | $13.50 | $13.50 | $14.96 | $18.15 | $13.50 | $13.50 |
| 110 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 4 | $275.00 | $275.00 | $304.70 | $369.81 | $275.00 | $275.00 | |
| 111 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 4 | $540.00 | $540.00 | $598.32 | $726.18 | $540.00 | $540.00 | |
| 112 | Work zone pavement marking removing (Y)6"(DOT) (662-7099) | LF | 140 | $3.00 | $3.00 | $3.32 | $4.03 | $3.00 | $3.00 | |
| 113 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 15,950 | $1.75 | $1.15 | $1.15 | $1.27 | $1.55 | $1.25 | $1.15 |
| 114 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 10,905 | $1.50 | $1.00 | $1.00 | $1.11 | $1.34 | $1.00 | $1.00 |
| 115 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 1,560 | $2.00 | $1.45 | $1.45 | $1.61 | $1.95 | $1.50 | $1.45 |
| 116 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 2,117 | $1.45 | $1.45 | $1.61 | $1.95 | $1.45 | $1.45 | |
| 117 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 16,546 | $1.50 | $1.00 | $1.00 | $1.11 | $1.34 | $1.00 | $1.00 |
| 118 | Reflectorized pavement marking type III (Y)(6")(broken) (666-7249) | LF | 50 | $0.75 | $4.00 | $4.00 | $4.43 | $5.38 | $4.00 | $4.00 |
| 119 | Prefabricated PM type B (W)(24")(solid) (668-7021) | LF | 1,712 | $30.00 | $27.45 | $27.45 | $30.41 | $36.91 | $28.00 | $27.45 |
| 120 | Prefabricated PM type B (W)(arrow) (668-7023) | EACH | 9 | $565.00 | $565.00 | $626.02 | $759.80 | $650.00 | $565.00 | |
| 121 | Prefabricated PM type B (W)(word) (668-7031) | EACH | 9 | $765.00 | $765.00 | $847.62 | $1,028.75 | $890.00 | $765.00 | |
| 122 | Prefabricated PM type B (W)(18")(yld tri) (668-7037) | EACH | 10 | $100.00 | $100.00 | $110.80 | $134.48 | $120.00 | $100.00 | |
| 123 | Prefabricated PM type B (Y)(24")(solid) (668-7056) | LF | 109 | $27.45 | $27.45 | $30.41 | $36.91 | $30.00 | $27.45 | |
| 124 | Reflectorized pavement marker type I-C (672-7002) | EACH | 184 | $6.00 | $6.75 | $6.75 | $7.48 | $9.08 | $8.00 | $6.75 |
| 125 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 491 | $11.00 | $6.75 | $6.75 | $7.48 | $9.08 | $8.00 | $6.75 |
| 126 | Eliminating existing PM & markers (4") (677-7001) | LF | 11,050 | $1.25 | $1.00 | $1.00 | $1.11 | $1.34 | $1.00 | $1.00 |
| 127 | Eliminating existing PM & markers (24") (677-7008) | LF | 184 | $12.00 | $5.00 | $5.00 | $5.54 | $6.72 | $5.00 | $5.00 |
| 128 | Eliminating existing PM & markers (18")(yld tri) (677-7023) | EACH | 70 | $31.00 | $60.00 | $60.00 | $66.48 | $80.69 | $60.00 | $60.00 |
| 129 | Pavement surface preparation for marking (6") (678-7002) | LF | 29,061 | $0.65 | $0.27 | $0.27 | $0.30 | $0.36 | $0.30 | $0.27 |
| 130 | Pavement surface preparation for marking (8") (678-7004) | LF | 2,117 | $0.40 | $0.40 | $0.44 | $0.54 | $0.40 | $0.40 | |
| 131 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,821 | $2.00 | $2.00 | $2.00 | $2.22 | $2.69 | $2.00 | $2.00 |
| 132 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 675 | $4.50 | $1.75 | $1.75 | $1.94 | $2.35 | $2.00 | $1.75 |
| 133 | Install highway traffic signal (isolated) (680-7002) | EACH | 4 | $65,000 | $75,000 | $75,000 | $83,100 | $94,134 | $80,000 | $75,000 |
| 134 | Removing traffic signals (680-7004) | EACH | 3 | $14,500 | $6,500.00 | $6,500.00 | $7,202.01 | $11,431 | $9,500.00 | $6,500.00 |
| 135 | Temporary traffic signals (681-7001) | EACH | 2 | $75,000 | $75,000 | $83,100 | $134,478 | $115,000 | $75,000 | |
| 136 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 16 | $350.00 | $350.00 | $387.80 | $470.67 | $405.00 | $350.00 | |
| 137 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 8 | $350.00 | $350.00 | $387.80 | $470.67 | $405.00 | $350.00 | |
| 138 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 16 | $350.00 | $350.00 | $387.80 | $470.67 | $405.00 | $350.00 | |
| 139 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $350.00 | $350.00 | $387.80 | $470.67 | $405.00 | $350.00 | |
| 140 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 32 | $365.00 | $350.00 | $350.00 | $387.80 | $470.67 | $405.00 | $350.00 |
| 141 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $350.00 | $350.00 | $387.80 | $470.67 | $405.00 | $350.00 | |
| 142 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $1,000.00 | $1,000.00 | $1,108.00 | $1,277.54 | $1,100.00 | $1,000.00 | |
| 143 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 12 | $175.00 | $175.00 | $193.90 | $268.96 | $235.00 | $175.00 | |
| 144 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 8 | $250.00 | $250.00 | $277.00 | $302.57 | $240.00 | $250.00 | |
| 145 | Backplate W/reflectorized border (1SEC)(went)aluminum (682-7050) | EACH | 16 | $422.00 | $150.00 | $150.00 | $166.20 | $268.96 | $230.00 | $150.00 |
| 146 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 1,680 | $2.50 | $2.50 | $2.77 | $3.03 | $2.50 | $2.50 | |
| 147 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 1,170 | $3.45 | $3.10 | $3.10 | $3.43 | $4.03 | $3.00 | $3.10 |
| 148 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 920 | $3.94 | $3.10 | $3.10 | $3.43 | $4.37 | $3.50 | $3.10 |
| 149 | Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036) | LF | 1,650 | $4.83 | $5.75 | $5.75 | $6.37 | $6.05 | $5.00 | $5.75 |
| 150 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 3,190 | $6.74 | $6.50 | $6.50 | $7.20 | $12.10 | $10.00 | $6.50 |
| 151 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 4 | $17,250 | $14,000 | $14,000 | $15,512 | $20,172 | $17,500 | $14,000 |
| 152 | Ins traffic signal PL AM(S)1 arm(32') (686-7033) | EACH | 1 | $14,007 | $12,000 | $12,000 | $13,296 | $17,482 | $15,000 | $12,000 |
| 153 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $23,000 | $15,000 | $15,000 | $16,620 | $25,551 | $22,000 | $15,000 |
| 154 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $24,000 | $15,500 | $15,500 | $17,174 | $26,223 | $25,000 | $15,500 |
| 155 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $16,000 | $16,000 | $17,728 | $28,240 | $26,000 | $16,000 | |
| 156 | Ins traffic signal PL AM(S)1 arm(48')lum (686-7051) | EACH | 2 | $16,500 | $16,500 | $18,282 | $32,275 | $28,000 | $16,500 | |
| 157 | Ins traffic signal PL AM(S)1 arm(60')lum (686-7063) | EACH | 1 | $44,000 | $44,000 | $48,752 | $73,963 | $65,000 | $44,000 | |
| 158 | Pedestrian pole assembly (687-7001) | EACH | 4 | $3,800.00 | $3,800.00 | $4,210.40 | $3,832.61 | $3,500.00 | $3,800.00 | |
| 159 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $1,050.00 | $1,050.00 | $1,163.40 | $1,344.78 | $1,200.00 | $1,050.00 | |
| 160 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $4,250.00 | $4,250.00 | $4,709.01 | $6,723.88 | $6,000.00 | $4,250.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.