TxDOT contract A00184431 bid tabulation

Reconstruct Existing Roadway, SH 75 (IH 45 to 0.2 Mi S of IH 45). Let by Texas DOT on July 1, 2025, Madison, Bryan District. 5 bids received; low bid $820,741 by Cornerstone Paving and Construction, L.L.C., -0.2% against the engineer's estimate of $822,327.

Owner
Texas DOT
Letting
01 JUL 2025
Pay items
64
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Cornerstone Paving and Construction, L.L.C.$820,741Low0.0%
2Larry Young Paving, Inc.$894,308+9.0%+9.0%
3Big Creek Construction, LTD.$916,986+12%+12%
4Knife River Corporation - South$946,908+15%+15%
5Brazos Paving, Inc.$1,098,305+34%+34%
TxDOT contract A00184431: bids by rank

Engineer's estimate: $822,327.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Cornerstone Paving and Construction, L.L.C.2. Larry Young Paving, Inc.3. Big Creek Construction, LTD.4. Knife River Corporation - South5. Brazos Paving, Inc.
1Preparing row (100-7002)STA9.50$500.00$350.00$1,000.00$1,000.00$1,920.00$1,200.00
2Removing concrete (pavement) (104-7001)SY556$25.00$40.00$15.00$12.00$29.00$33.00
3Removing concrete (driveways) (104-7011)SY323$25.00$50.00$14.00$20.00$26.80$33.00
4Remove (8"-19") TRT/untrt base & asphalt pavement (105-7119)SY2,111$15.00$16.50$17.00$10.00$16.00$22.50
5Excavation (roadway) (110-7001)CY1,005$15.00$28.00$51.00$22.00$35.20$56.25
6Backfill (type A or B) (134-7004)STA9.50$100.00$400.00$520.00$800.00$285.00$1,300.00
7Furn & place topsoil (4") (160-7002)SY5,320$2.75$1.25$1.75$1.50$0.32$1.50
8Broadcast seed (permanent_rural_sand) (164-7001)SY5,320$2.50$0.75$1.00$0.85$0.83$1.00
9Broadcast seed (temporary_warm) (164-7005)SY2,660$3.00$0.65$0.75$0.75$0.72$0.85
10Broadcast seed (temporary_cool) (164-7006)SY2,660$2.25$0.65$0.75$0.75$0.72$0.85
11Vegetative watering (168-7001)TGL1,064$12.00$5.00$3.50$20.00$33.25$36.50
12Cem TRT(PLNT MX)(CL L)(tya)(GR1-2)(10") (276-7125)SY2,956$55.00$50.00$62.00$60.00$50.28$42.65
13Prime coat(MC-30 or AE-P) (310-7013)GAL592$11.00$13.00$10.00$4.50$10.90$12.85
14SP mixes SP-B sac-B PG64-22 (344-7002)TON326$120.00$140.35$210.00$235.00$150.00$227.00
15SP mixes SP-C sac-A PG70-22 (344-7020)TON497$135.00$148.35$150.00$200.00$152.00$178.25
16Tack coat (344-7077)GAL747$6.00$3.50$7.50$5.00$4.20$13.50
17Plane & text asphalt concrete pavement(0" to 4") (354-7004)SY1,334$5.00$8.76$7.00$7.50$7.00$11.00
18Plane & text asphalt concrete pavement(4" to 6") (354-7011)SY889$5.50$12.75$12.00$9.00$11.00$14.00
19Plane & text asphalt concrete pavement(6" to 8") (354-7012)SY556$5.75$12.75$18.00$14.00$17.00$20.15
20Planing asphalt concrete pavement(4") (354-7053)SY2,889$5.00$8.50$5.00$4.00$3.00$11.00
21RC pipe (CL III)(18 in) (464-7003)LF78$114.00$65.00$94.00$95.00$88.00$84.00
22RC pipe (CL III)(24 in) (464-7005)LF242$135.00$140.00$88.00$95.00$100.00$106.30
23Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH2$1,730.01$900.00$1,100.00$1,750.00$1,238.00$2,435.00
24Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH8$2,200.00$2,000.00$1,500.00$2,200.00$1,300.00$3,840.00
25Removing structure (inlet) (496-7002)EACH1$875.00$750.00$1,300.00$800.00$500.00$2,610.00
26Removing structure (set) (496-7004)EACH8$850.00$850.00$650.00$625.00$600.00$1,600.00
27Removing structure (wingwall) (496-7005)EACH4$2,425.00$1,200.00$720.00$1,200.00$2,700.00$630.00
28Removing structure (pipe) (496-7007)LF406$35.00$40.00$25.00$15.00$22.00$57.75
29Mobilization (500-7001)LS1$75,000$42,000$98,000$75,000$100,000$116,410
30Barricades, signs and traffic handling (502-7001)MO6$7,250.00$2,500.00$6,400.00$2,000.00$8,100.00$11,515
31Portable changeable message sign (503-7002)EACH2$10,000$5,000.00$1,800.00$15,000$6,600.00$13,000
32TMA (stationary) (505-7001)DAY89$275.00$100.00$250.00$200.00$500.00$325.00
33TMA (mobile operation) (505-7003)DAY6$325.00$100.00$1,400.00$1,000.00$900.00$850.00
34Rock filter dams (install) (type 2) (506-7002)LF80$60.00$35.00$44.00$40.00$39.00$45.50
35Rock filter dams (remove) (506-7011)LF80$20.00$10.00$13.00$12.00$10.00$13.00
36Temporary sediment control fence (install) (506-7039)LF200$5.50$5.00$6.25$5.50$5.56$6.50
37Temporary sediment control fence (remove) (506-7041)LF200$2.00$1.00$1.25$1.25$1.10$1.30
38Constructing detours (508-7001)SY178$124.25$254.00$120.00$200.00$218.00$125.00
39Intersections (ACP) (530-7002)SY418$56.00$105.50$17.00$65.00$105.00$54.60
40Driveways (ACP) (530-7010)SY449$45.00$98.50$74.00$65.00$68.50$53.15
41Relocate existing mailbox (560-7012)EACH1$400.00$250.00$340.00$525.00$330.00$624.00
42Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH8$825.00$770.00$910.00$950.00$850.00$1,000.00
43Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,070.00$1,225.00$1,000.00$1,150.00$1,361.00$1,600.00
44Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH2$1,150.00$1,200.00$1,400.00$1,150.00$1,314.00$1,540.00
45Remove SM RD SN sup&AM (644-7073)EACH15$160.00$130.00$170.00$120.00$145.00$170.00
46Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF7,644$0.45$1.05$1.25$1.75$1.17$1.35
47Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF9,788$0.70$1.05$1.25$1.75$1.17$1.35
48Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH255$5.25$7.00$8.75$9.75$7.80$9.10
49Work zone pavement marking removing (W)6"(solid) (662-7068)LF3,090$1.70$0.55$0.75$1.00$0.61$0.70
50Work zone pavement marking removing (W)8"(solid) (662-7072)LF572$2.70$1.10$1.50$1.25$1.22$1.45
51Work zone pavement marking removing (Y)6"(solid) (662-7100)LF3,488$1.50$0.55$0.75$1.00$0.60$0.70
52Reflectorized pavement marking type I (W)8"(broken)(090MIL) (666-7014)LF150$1.35$2.00$2.50$4.00$2.50$2.60
53Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023)LF422$1.35$2.00$2.50$4.00$2.50$2.60
54Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF160$1.00$5.75$7.25$3.50$6.40$7.50
55Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF160$1.00$5.75$7.25$3.50$6.40$7.50
56Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF2,930$0.85$1.35$1.75$3.00$1.50$1.75
57Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF3,328$0.85$1.35$1.75$3.00$1.50$1.75
58Prefabricated PM type C (W)(24")(solid) (668-7089)LF22$18.00$20.10$25.00$25.00$25.00$26.10
59Prefabricated PM type C (W)(arrow) (668-7091)EACH5$235.00$309.00$390.00$450.00$344.00$400.00
60Prefabricated PM type C (W)(word) (668-7103)EACH4$290.00$377.00$470.00$550.00$420.00$490.00
61PRFB rumble strip (BLK)(1')(edgeline) (668-7137)LF587$4.00$11.24$14.00$18.00$12.49$14.60
62Reflectorized pavement marker type I-C (672-7002)EACH34$5.50$7.00$8.75$10.00$8.00$9.10
63Reflectorized pavement marker type II-A-A (672-7004)EACH164$7.00$7.00$8.75$9.00$8.00$9.10
64Eliminating existing PM & markers (6") (677-7002)LF2,242$1.00$0.52$0.75$4.00$0.60$0.70
TxDOT contract A00184431: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy