TxDOT contract A00184512 bid tabulation

Hazard Elimination & Safety, SH 64 (CR 4133 to SL 571). Let by Texas DOT on January 6, 2026, Rusk, Tyler District. 5 bids received; low bid $13,629,478 by Longview Bridge and Road, LTD., +1.6% against the engineer's estimate of $13,420,245.

Owner
Texas DOT
Letting
06 JAN 2026
Pay items
141
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Longview Bridge and Road, LTD.$13,629,478Low+2.0%
2Pinto Construction Co., Inc.$14,133,502+4.0%+5.0%
3East Texas Bridge, Inc.$14,203,271+4.0%+6.0%
4A. L. Helmcamp, Inc.$14,349,366+5.0%+7.0%
5L. S. Equipment Co., Inc.$15,103,709+11%+13%
TxDOT contract A00184512: bids by rank

Engineer's estimate: $13,420,245.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Longview Bridge and Road, LTD.2. Pinto Construction Co., Inc.3. East Texas Bridge, Inc.4. A. L. Helmcamp, Inc.5. L. S. Equipment Co., Inc.
1Preparing row (100-7002)STA173.83$2,400.00$3,500.00$1,850.00$2,200.00$1,850.00$1,875.00
2Removing concrete (pavement) (104-7001)SY5,463$15.00$17.00$35.54$15.00$22.00$65.00
3Removing concrete (mowstrip) (104-7003)SY858$20.00$23.00$24.15$30.00$24.00$31.50
4Removing concrete (riprap) (104-7006)SY15$80.00$60.00$30.45$30.00$30.00$45.50
5Removing concrete (driveways) (104-7011)SY145$30.00$21.00$30.45$30.00$30.00$24.50
6Removing concrete (curb) (104-7016)LF1,104$20.00$6.00$18.38$10.00$18.00$19.50
7Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001)SY17,239$14.00$6.00$4.34$8.00$12.00$6.00
8Remove (13"-17") TRT/untrt base & asphalt pavement (105-7013)SY10,283$12.00$8.00$10.07$12.00$25.00$6.50
9Excavation (roadway) (110-7001)CY34,832$11.00$10.50$12.82$18.00$24.00$13.50
10Embankment (final)(DC)(type C) (132-7006)CY14,626$15.00$15.50$14.29$22.00$16.00$24.50
11Furn & place topsoil (4") (160-7002)SY111,150$3.00$2.50$2.10$2.50$0.90$2.50
12Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076)SY111,150$0.60$0.59$0.55$0.60$0.55$0.58
13Bond fiber MTRX seed (temporary)(warm) (164-7077)SY55,575$0.60$0.57$0.55$0.55$0.55$0.58
14Bond fiber MTRX seed (temporary)(cool) (164-7078)SY55,575$0.40$0.58$0.55$0.55$0.55$0.58
15Vegetative watering (168-7001)TGL2,445.30$12.00$11.00$0.01$12.00$1.00$0.01
16FL BS (compacted in place)(type A GR 1-2) (12") (247-7113)SY39,838$45.00$48.00$56.18$48.00$39.00$34.66
17Cement (275-7001)TON1,209$280.00$295.00$259.66$265.00$230.00$275.00
18Cement TRT (subgrade)(12") (275-7015)SY44,757$4.25$2.50$7.02$4.00$11.00$6.50
19Prime coat & blotter (MC-30) (310-7010)GAL3,818$8.00$5.85$12.60$6.25$5.50$7.00
20Emuls asphalt (erosion control)(CSS-1) (314-7010)GAL1,611$7.00$5.00$13.14$6.00$12.50$5.25
21Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068)GAL41,454$5.00$4.00$4.15$5.50$4.00$5.25
22Aggregate (type-PD or PL, GR-3) (316-7257)CY922$190.00$195.00$179.25$235.00$280.00$225.00
23SP mixes SP-C PG70-22 (344-7019)TON12,368$140.00$160.00$177.68$173.00$150.00$160.00
24Tack coat (344-7077)GAL6,111$5.00$4.00$6.30$5.00$5.00$6.00
25Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY23,947$3.75$2.75$2.30$4.00$3.50$2.92
26Planing asphalt concrete pavement(2") (354-7051)SY10,241$5.00$2.75$2.99$4.00$4.30$2.92
27Cem stabil BKFL (400-7010)CY248$280.00$250.00$246.75$350.00$255.00$250.00
28Flowable backfill (401-7001)CY4$370.00$500.00$346.50$500.00$345.00$500.00
29Trench excavation protection (402-7001)LF35$12.00$20.00$21.00$30.00$21.00$20.00
30Temporary special shoring (403-7001)SF7,886$40.00$65.00$42.00$65.00$42.00$88.00
31Drilled shaft (36 in) (416-7006)LF744$330.00$420.00$341.25$275.00$350.00$335.00
32Class C concrete (abutment)(HPC) (420-7013)CY64.60$1,700.00$1,500.00$1,890.00$1,300.00$2,715.00$1,950.00
33Class C concrete (cap)(HPC) (420-7023)CY49.80$1,800.00$1,450.00$1,575.00$1,300.00$3,000.00$1,650.00
34Class C concrete (column)(HPC) (420-7039)CY34.80$2,100.00$1,550.00$1,995.00$1,350.00$2,000.00$2,200.00
35Class C concrete (collar) (420-7061)EACH2$1,400.00$2,000.00$1,417.50$2,000.00$1,420.00$2,200.00
36CL E concrete (seal slab)(non-reinforced) (420-7070)CY14$500.00$550.00$477.75$600.00$475.00$850.00
37Reinforced concrete slab (HPC) (422-7002)SF6,900$32.00$32.00$34.13$33.00$49.00$35.50
38Approach slab (HPC) (422-7014)CY112$900.00$1,000.00$840.00$770.00$1,100.00$880.00
39Prestressed concrete girder (TX28) (425-7001)LF794.50$300.00$300.00$357.00$275.00$265.00$360.00
40Riprap (concrete)(5 in) (432-7002)CY4$900.00$750.00$756.00$800.00$756.00$1,200.00
41Riprap (mow strip)(4 in) (432-7013)CY95$700.00$600.00$971.25$650.00$970.00$800.00
42Riprap (stone common)(dry)(8 in) (432-7030)CY2$230.00$625.00$262.03$1,000.00$262.00$495.00
43Riprap (stone protection)(18 in) (432-7043)CY843$250.00$210.00$267.75$225.00$267.00$250.00
44Riprap (stone protection)(24 in) (432-7045)CY3,158$180.00$210.00$236.25$225.00$139.00$255.00
45Rail (type SSTR)(HPC) (450-7025)LF278$170.00$100.00$130.20$120.00$190.00$130.00
46Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF124$275.00$225.00$210.00$210.00$311.00$210.00
47Concrete box culvert (4 FT X 3 FT)(extend) (462-7059)LF14$990.00$2,600.00$863.10$800.00$863.00$1,750.00
48Concrete box culvert (5 FT X 5 FT)(extend) (462-7064)LF8$1,700.00$4,300.00$892.50$1,000.00$892.00$2,250.00
49Concrete box culvert (6 FT X 4 FT)(extend) (462-7067)LF15$1,500.00$2,600.00$892.50$1,000.00$892.00$1,540.00
50Concrete box culvert (7 FT X 7 FT)(extend) (462-7074)LF22$1,600.00$1,900.00$997.50$1,200.00$997.00$1,500.00
51Concrete box culvert (10 FT X 10 FT)(extend) (462-7093)LF14$2,500.00$3,000.00$1,785.00$2,000.00$1,785.00$2,475.00
52RC pipe (CL III)(18 in) (464-7003)LF4,068$55.00$50.00$65.10$62.00$65.00$76.25
53RC pipe (CL III)(24 in) (464-7005)LF98$150.00$67.00$105.00$90.00$105.00$106.50
54RC pipe (CL III)(30 in) (464-7007)LF50$220.00$130.00$210.00$130.00$210.00$249.00
55Wingwall (FW - S) (HW=5 FT) (466-7161)EACH1$11,000$16,500$13,125$10,000$13,125$15,000
56Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH1$35,000$16,700$17,325$12,000$17,325$16,000
57Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH2$27,000$18,000$26,250$18,000$26,250$21,500
58Wingwall (PW - 1) (HW=8 FT) (466-7178)EACH2$42,500$24,000$30,450$28,000$30,450$25,000
59Wingwall (PW - 1) (HW=10 FT) (466-7180)EACH2$50,000$28,000$44,100$42,000$44,100$35,000
60Wingwall (PW - 1) (HW=12 FT) (466-7182)EACH1$65,000$48,000$72,975$85,000$72,975$60,000
61Wingwall (PW - 1) (HW=13 FT) (466-7183)EACH1$24,000$45,000$75,600$60,000$75,600$60,000
62Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH199$1,000.00$975.00$945.00$1,000.00$945.00$891.25
63Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH6$2,000.00$1,400.00$1,548.75$1,500.00$1,548.00$1,525.00
64Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347)EACH2$3,800.00$2,400.00$2,310.00$3,000.00$2,310.00$2,650.00
65Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH4$2,700.00$4,500.00$4,200.00$4,700.00$4,200.00$5,500.00
66Pipe (PVC) (schedule 40) (12 in) (481-7016)LF104$40.00$55.00$40.00$40.00$65.00$25.00
67Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$80,000$55,000$131,250$90,000$140,000$100,000
68Removing structure (pipe) (496-7037)EACH100$500.00$350.00$315.00$500.00$315.00$500.00
69Mobilization (500-7001)LS1$1,051,356$1,250,000$1,000,000$1,200,000$1,300,000$1,200,000
70Barricades, signs and traffic handling (502-7001)MO16$6,000.00$6,000.00$2,630.00$10,000$13,000$9,500.00
71Portable changeable message sign (503-7001)DAY301$100.00$130.00$200.00$125.00$408.00$100.00
72TMA (stationary) (505-7001)DAY301$150.00$225.00$250.00$250.00$275.00$225.00
73TMA (mobile operation) (505-7003)DAY100$100.00$275.00$50.00$250.00$275.00$225.00
74Rock filter dams (install) (type 2) (506-7002)LF525$55.00$45.00$39.90$45.00$40.00$41.00
75Rock filter dams (install) (type 3) (506-7003)LF596$75.00$45.00$52.50$55.00$52.00$53.00
76Rock filter dams (remove) (506-7011)LF1,106$18.00$16.00$12.60$15.00$13.00$2.00
77Construction exits (install) (type 1) (506-7020)SY445$40.00$55.00$29.40$32.00$20.00$31.50
78Construction exits (remove) (506-7024)SY445$12.00$18.00$10.50$11.00$5.00$11.00
79Temporary sediment control fence (install) (506-7039)LF8,990$5.00$4.50$4.20$4.50$4.20$4.50
80Temporary sediment control fence (remove) (506-7041)LF8,990$1.70$1.25$0.53$0.60$0.55$0.50
81Biodegradable erosion control logs (install) (18") (506-7045)LF744$10.00$6.00$6.30$7.00$6.30$6.25
82Biodegradable erosion control logs (remove) (506-7046)LF744$2.00$1.50$1.05$1.00$1.05$1.10
83Constructing detours (508-7001)SY2,361$135.00$82.00$133.37$80.00$125.00$195.00
84Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017)LF540$60.00$45.00$151.48$55.00$100.00$30.00
85Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF540$28.00$5.50$65.09$15.00$50.00$23.52
86Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041)LF540$25.00$15.00$18.18$35.00$100.00$25.00
87Intersections (ACP) (530-7002)SY2,468$60.00$40.00$38.55$40.00$42.00$82.50
88Driveways (concrete) (hes) (530-7007)SY200$115.00$100.00$183.75$120.00$185.00$125.00
89Driveways (ACP) (530-7010)SY16,665$45.00$45.00$45.10$45.00$42.00$82.50
90Mill rumble strips (asphalt) (shoulder) (533-7001)LF34,036$0.33$0.22$0.16$0.35$0.34$0.25
91Mill rumble strips (asphalt) (centerline) (533-7002)LF34,036$0.25$0.22$0.18$0.35$0.34$0.25
92Metal W-beam guard fence (steel post) (540-7002)LF925$30.00$28.00$27.30$28.00$27.00$26.50
93Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,300.00$2,075.00$2,262.75$2,200.00$1,979.00$1,900.00
94Remove metal beam guard fence (542-7001)LF2,260$3.00$3.00$2.10$2.75$2.10$4.00
95Guardrail end treatment (install) (544-7001)EACH10$3,400.00$3,200.00$3,013.50$3,200.00$3,015.00$3,150.00
96Crash cushion attenuator (move & reset) (545-7002)EACH2$1,500.00$3,300.00$1,919.50$3,300.00$1,115.00$3,200.00
97Crash cushion attenuator (remove) (545-7004)EACH2$1,300.00$1,100.00$1,468.50$1,100.00$1,115.00$1,250.00
98Cca (install)(N)(TL3)(work zone) (545-7018)EACH2$7,500.00$35,500$8,206.00$36,000$35,000$33,250
99Remove and install existing gate (550-7017)EACH2$2,000.00$1,200.00$2,500.00$500.00$2,760.00$500.00
100Mailbox install-M (TWG-post) type 1 (560-7001)EACH5$670.00$800.00$874.50$800.00$619.00$750.00
101Mailbox install-S (TWG-post) type 2 (560-7002)EACH59$340.00$370.00$368.50$375.00$231.00$365.00
102Mailbox install-D (TWG-post) type 2 (560-7003)EACH13$370.00$420.00$401.50$425.00$263.00$395.00
103Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH33$900.00$720.00$830.50$725.00$725.00$675.00
104Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH2$1,200.00$990.00$957.00$1,000.00$893.00$915.00
105Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,100.00$1,150.00$1,083.50$1,150.00$1,040.00$1,150.00
106Remove SM RD SN sup&AM (644-7073)EACH7$130.00$110.00$143.00$110.00$105.00$109.50
107Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004)EACH22$70.00$90.00$115.50$55.00$79.00$55.00
108Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH13$110.00$97.00$137.50$100.00$79.00$95.00
109Install OM SM RD sign (1-OM-con)Y (658-7079)EACH4$390.00$145.00$100.00$150.00$26.00$135.00
110Install OM SM RD sign (1-OM-con)R (658-7080)EACH7$300.00$28.00$100.00$130.00$26.00$120.00
111Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF32,028$0.50$0.40$0.37$0.38$0.37$0.40
112Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF48,134$0.50$0.40$0.37$0.38$0.37$0.40
113Work zone pavement marking removing (W)6"(solid) (662-7068)LF310$1.40$5.50$5.25$5.50$5.25$7.25
114Work zone pavement marking removing (Y)6"(solid) (662-7100)LF620$1.20$5.50$5.25$5.50$5.25$7.25
115Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH2,073$2.30$2.00$3.15$2.00$0.53$2.00
116Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH4,369$2.00$2.00$3.15$2.00$0.53$2.00
117Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF90$2.00$3.30$3.15$3.30$3.15$3.20
118Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF162$2.00$3.00$2.63$2.75$2.63$2.55
119Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF877$1.00$1.75$1.58$1.65$1.58$1.75
120Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF151$6.00$8.00$7.35$7.70$7.35$7.25
121Pavement sler 6" (666-7347)LF90$2.00$2.20$2.10$2.20$2.10$2.10
122Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF349$1.00$1.10$1.05$1.10$1.05$1.05
123Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF34,191$0.50$0.95$0.89$0.93$0.89$0.92
124Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF8,738$0.50$0.95$0.89$0.93$0.89$0.92
125Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF34,951$0.50$0.95$0.89$0.93$0.89$0.92
126Prefabricated PM type C (W)(arrow) (668-7091)EACH2$225.00$250.00$236.25$275.00$236.00$235.00
127Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH2$400.00$305.00$288.75$300.00$289.00$280.00
128Prefabricated PM type C (W)(word) (668-7103)EACH2$240.00$275.00$262.50$275.00$263.00$255.00
129Reflectorized pavement marker type I-C (672-7002)EACH44$4.50$5.50$5.25$5.50$5.25$5.15
130Reflectorized pavement marker type II-A-A (672-7004)EACH1,039$6.00$5.50$5.25$5.50$5.25$5.15
131Traffic button type W (672-7007)EACH62$7.00$5.50$5.25$5.50$5.25$5.15
132Traffic button type Y (672-7008)EACH62$5.00$5.50$5.25$5.50$5.25$5.15
133Eliminating existing PM & markers (6") (677-7002)LF22,208$2.00$0.50$0.47$0.50$0.47$0.47
134Eliminating existing PM & markers (rumble strip) (677-7030)LF47,663$3.50$0.60$0.15$0.50$1.05$1.00
135Pavement surface preparation for marking (6") (678-7002)LF90$0.80$2.20$2.10$2.20$2.10$0.50
136Full - width mowing (730-7019)CYC3$5,800.00$7,500.00$3,500.00$8,000.00$6,500.00$5,000.00
137Litter removal (734-7002)CYC3$6,000.00$4,500.00$1,500.00$3,600.00$5,500.00$500.00
138RC pipe (CL III)(30 in) (464-7007)LF0$220.00$0.00$0.00$0.00$0.00$0.00
139Thermoplastic pipe (PP) (18") (468-7001)LF0$55.00$0.00$0.00$0.00$0.00$0.00
140Thermoplastic pipe (PP) (24") (468-7002)LF0$150.00$0.00$0.00$0.00$0.00$0.00
141Thermoplastic pipe (PP) (30") (468-7003)LF0$220.00$0.00$0.00$0.00$0.00$0.00
TxDOT contract A00184512: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy