TxDOT contract A00184596 bid tabulation

Widen Road - Add Shoulders, SH 71 (0.75 MI W of CR 401 to 0.75 MI E of CR 401). Let by Texas DOT on February 6, 2025, Burnet, Austin District. 8 bids received; low bid $7,072,728 by Hunter Industries, LTD., +3.3% against the engineer's estimate of $6,847,445.

Owner
Texas DOT
Letting
06 FEB 2025
Pay items
127
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hunter Industries, LTD.$7,072,728Low+3.0%
2CK Newberry, LLC$7,134,114+1.0%+4.0%
3Austin Engineering Co., Inc.$7,454,914+5.0%+9.0%
4Aaron Concrete Contractors, LLC$7,631,214+8.0%+11%
5Acme Bridge Company, Inc.$7,724,047+9.0%+13%
6Jordan Foster Construction, LLC$8,355,246+18%+22%
7C. E. Barker, LTD.$8,664,287+23%+27%
8Grey Sky Construction LLC$9,723,816+37%+42%
TxDOT contract A00184596: bids by rank

Engineer's estimate: $6,847,445.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hunter Industries, LTD.2. CK Newberry, LLC3. Austin Engineering Co., Inc.4. Aaron Concrete Contractors, LLC5. Acme Bridge Company, Inc.6. Jordan Foster Construction, LLC
1Preparing row (100-7002)STA98.25$2,700.00$749.26$450.00$745.00$1,700.00$2,050.00$6,500.00
2Removing concrete (flume) (104-7041)SY818$12.64$12.50$25.00$15.00$30.00$19.50$15.00
3Excavation (roadway) (110-7001)CY30,791$10.50$28.40$20.00$19.00$15.00$30.00$21.00
4Embankment (final)(OC)(type B) (132-7003)CY4,903$16.50$17.00$25.00$42.00$10.00$12.40$17.35
5Furn & place topsoil (4") (160-7002)SY77,070$2.70$2.18$2.10$1.40$1.50$1.38$2.50
6Broadcast seed (temporary_warm_cool) (164-7007)SY77,070$0.30$0.14$0.25$0.30$0.35$0.30$0.30
7Drill seed (permanent_urban_clay) (164-7012)SY77,070$0.50$0.21$0.25$0.30$0.35$0.31$0.17
8Vegetative watering (168-7001)TGL1,297$40.00$27.20$30.00$16.00$35.00$56.00$50.00
9Soil ret BLKT(SL_mod_clay_short) (169-7001)SY19,267.50$2.25$1.55$3.00$1.20$1.30$1.20$2.00
10Wildflower seeding (180-7001)ACRE15.93$2,500.00$2,500.00$2,000.00$2,500.00$2,900.00$2,610.00$3,600.00
11FL BS (compacted in place)(type A GR 5)(final pos) (247-7179)CY14,842$30.00$58.00$50.00$69.00$70.00$62.00$52.00
12Prime coat (multi option) (310-7015)GAL8,908$6.00$5.09$4.00$4.00$4.20$3.80$3.60
13D-GR HMA type-B PG64-22 (341-7001)TON13,470$115.00$96.70$90.00$98.00$97.00$88.60$89.00
14D-GR HMA type D PG76-22 (level-UP) (341-7059)TON993$135.00$110.00$150.00$145.00$162.00$140.00$143.00
15D-GR HMA type D PG 76-22 (exempt) (341-7065)TON4,900$130.00$106.60$120.00$123.00$127.00$112.00$115.00
16Tom-C PG76-22 sac-B (347-7002)TON5,110$150.00$140.80$150.00$160.00$163.00$145.00$150.00
17Flexible pavement structure repair(6") (351-7005)SY2,402$50.00$45.41$65.00$97.00$68.00$65.60$70.00
18Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY24,018$2.50$2.43$2.00$2.00$2.60$1.70$1.75
19Flowable backfill (401-7001)CY1$556.12$233.81$220.00$500.00$2,400.00$2,130.00$1,500.00
20Temporary special shoring (403-7001)SF529$45.00$12.81$20.00$58.00$67.00$58.70$64.00
21Drilled shaft (24 in) (416-7004)LF13$522.73$525.00$389.00$563.00$536.00$550.00
22Drilled shaft (traffic signal pole) (30 in) (416-7043)LF11$456.70$500.00$638.00$539.00$469.00$500.00
23Drilled shaft (traffic signal pole) (48 in) (416-7046)LF44$605.27$600.00$682.00$666.00$621.00$625.00
24Riprap (concrete)(6 in) (432-7003)CY163$585.00$760.93$725.00$704.00$658.00$576.00$1,100.00
25Riprap (concrete)(CL B) (432-7005)CY5.40$600.00$655.57$625.00$1,770.00$585.00$512.00$700.00
26Rirrap (stone common)(dry)(15 in) (432-7032)CY279$160.00$203.91$225.00$150.00$301.00$187.00$250.00
27Concrete box culvert (6 FT X 6 FT)(extend) (462-7069)LF16$1,500.00$1,081.38$1,100.00$1,871.00$2,615.00$2,290.00$3,500.00
28Concrete box culvert (7 FT X 4 FT)(extend) (462-7071)LF36$1,200.00$966.81$1,000.00$1,873.00$1,800.00$1,570.00$2,000.00
29Concrete box culvert (5 FT X 6 FT) (extend) (462-7113)LF21$1,300.00$906.02$900.00$1,799.00$1,800.00$1,570.00$2,000.00
30RC pipe (CL III)(18 in) (464-7003)LF76$120.00$113.40$105.00$115.00$245.00$213.00$160.00
31Wingwall (FW - S) (HW=5 FT) (466-7161)EACH1$15,000$12,684$12,000$14,617$17,000$15,200$25,000
32Wingwall (FW - S) (HW=7 FT) (466-7163)EACH1$16,000$14,613$15,000$24,700$21,000$18,500$25,000
33Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH1$22,000$19,465$20,000$19,739$19,000$17,100$25,000
34Wingwall (PW - 1) (HW=8 FT) (466-7178)EACH1$22,000$31,798$30,000$34,323$24,000$20,900$40,000
35Wingwall (PW - 1) (HW=10 FT) (466-7180)EACH1$25,000$40,800$40,000$41,155$44,000$38,800$50,000
36Wingwall (PW - 1) (HW=11 FT) (466-7181)EACH1$25,000$53,952$50,000$55,134$55,000$47,800$65,000
37Wingwall (PW - 1) (HW=12 FT) (466-7182)EACH1$25,000$73,183$70,000$55,373$63,000$55,000$70,000
38Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH2$2,400.00$1,554.85$1,500.00$5,257.00$5,000.00$4,460.00$3,000.00
39Removing structure (set) (496-7004)EACH2$800.00$233.81$500.00$623.00$275.00$240.00$550.00
40Removing structure (wingwall) (496-7005)EACH8$500.00$1,753.59$2,000.00$1,157.00$600.00$534.00$2,100.00
41Removing structure (headwall) (496-7006)EACH8$500.00$1,753.59$1,750.00$1,135.00$900.00$800.00$2,100.00
42Removing structure (pipe) (496-7007)LF50$29.50$23.38$50.00$37.00$22.00$18.70$25.00
43Mobilization (500-7001)LS1$502,860$590,712$700,000$207,000$600,000$705,000$830,000
44Barricades, signs and traffic handling (502-7001)MO12$6,000.00$7,232.70$10,000$8,604.00$4,000.00$9,500.00$20,000
45Portable changeable message sign (503-7002)EACH4$12,000$5,268.14$16,500$16,617$10,000$17,000$17,000
46TMA (stationary) (505-7001)DAY40$284.88$237.07$350.00$178.00$300.00$348.00$525.00
47TMA (mobile operation) (505-7003)DAY3$73.00$1,053.63$800.00$1,195.00$890.00$1,470.00$1,250.00
48Rock filter dams (install) (type 2) (506-7002)LF210$12.50$37.00$40.00$65.00$70.00$63.30$45.00
49Rock filter dams (remove) (506-7011)LF210$4.10$10.00$20.00$52.00$56.00$50.40$22.00
50Temporary sediment control fence (install) (506-7039)LF9,981$1.00$2.98$4.00$5.00$5.70$5.10$3.20
51Temporary sediment control fence (remove) (506-7041)LF9,981$3.50$1.00$1.00$0.80$0.90$0.78$1.20
52Biodegradable erosion control logs (install) (6") (506-7042)LF600$6.50$4.25$4.00$4.00$4.40$4.00$7.00
53Biodegradable erosion control logs (install) (12") (506-7044)LF30$1.50$4.85$5.00$9.00$9.60$8.60$8.85
54Biodegradable erosion control logs (remove) (506-7046)LF630$0.75$1.50$1.00$2.00$2.20$2.00$3.30
55Constructing detours (508-7001)SY1,134$110.00$67.50$105.00$155.00$117.00$160.00$125.00
56Intersections (ACP) (530-7002)SY533$58.00$49.50$90.00$137.00$120.00$161.00$121.00
57Driveways (ACP) (530-7010)SY132$65.00$49.50$80.00$172.00$128.00$113.00$115.00
58Wire fence (type C) (552-7003)LF192$24.00$50.00$20.00$31.00$30.00$53.40$56.00
59Conduit (PVC) (schedule 40) (2") (618-7030)LF450$17.32$20.00$27.00$28.00$19.20$20.00
60Conduit (PVC) (schedule 40) (3") (618-7036)LF140$20.38$20.00$33.00$34.00$22.60$23.00
61Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF1,370$30.57$30.00$83.00$85.00$33.90$34.00
62Electrical conductor (no.8) bare (620-7007)LF1,380$1.73$2.00$2.00$2.10$1.90$2.00
63Electrical conductor (no.8) insulated (620-7008)LF2,880$1.89$2.00$2.20$2.25$2.10$2.10
64Electrical conductor (no.6) bare (620-7009)LF260$2.09$2.00$2.40$2.50$2.30$2.35
65Electrical conductor (no.6) insulated (620-7010)LF400$2.39$2.50$2.50$2.60$2.65$2.65
66Ground box type D (162922)W/apron (624-7008)EACH8$1,462.40$1,500.00$2,710.00$2,760.00$1,620.00$1,600.00
67Elc SRV type D 120/240 070(NS)AL(E)SP(O) (628-7169)EACH1$8,733.63$9,000.00$11,537$11,730$9,680.00$9,700.00
68Aluminum signs (type A) (636-7001)SF272$64.20$30.00$42.00$46.00$24.90$25.00
69Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH24$800.00$725.00$800.00$1,034.00$1,100.00$991.00$802.00
70Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH5$948.12$1,076.00$900.00$1,016.00$1,100.00$974.00$1,200.00
71Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,188.39$1,364.00$1,200.00$1,617.00$1,700.00$1,550.00$1,500.00
72Remove SM RD SN sup&AM (644-7073)EACH15$156.56$140.00$135.00$148.00$158.00$143.00$140.00
73Install object marker assembly (OM-2X)(WC)GND (658-7055)EACH16$86.68$70.00$125.00$99.00$106.00$95.50$77.00
74Work zone pavement marking non-removing (W)4"(solid) (662-7004)LF1,185$0.66$0.46$1.50$1.50$0.50$0.46$0.50
75Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF22$11.40$11.29$18.00$19.00$12.50$11.30$12.00
76Work zone pavement marking non-removing (Y)4"(solid) (662-7035)LF740$0.66$0.46$1.50$1.50$0.50$0.46$0.50
77Work zone pavement marking removing (W)4"(solid) (662-7064)LF24,982$1.02$0.65$0.55$0.60$0.70$0.65$0.70
78Work zone pavement marking removing (W)24"(solid) (662-7077)LF22$11.80$26.63$17.00$19.00$30.00$26.70$28.00
79Work zone pavement marking removing (Y)4"(broken) (662-7095)LF5,110$0.77$0.82$1.00$1.00$0.90$0.82$0.85
80Work zone pavement marking removing (Y)4"(solid) (662-7097)LF23,383$1.03$0.65$1.00$0.60$0.70$0.65$0.65
81Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,304$2.20$1.63$1.00$3.50$1.00$2.20$2.20
82Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH2,739$2.12$1.63$1.00$3.50$1.00$2.20$2.20
83Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF1,030$1.25$1.13$1.50$1.70$1.25$1.15$1.20
84Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF25$8.50$11.29$25.00$25.00$12.50$11.30$12.00
85Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH16$180.00$160.82$450.00$476.00$178.00$161.00$165.00
86Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH12$210.00$187.45$225.00$238.00$208.00$188.00$200.00
87Reflectorized pavement marking type II (W) 6" (broken) (666-7172)LF6,044$0.82$0.27$0.50$0.30$0.30$0.27$0.30
88Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF24,509$0.35$0.27$0.50$0.25$0.30$0.27$0.30
89Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF1,030$0.60$0.27$0.50$0.60$0.30$0.27$0.30
90Reflectorized pavement marking type II (W) 24" (solid) (666-7184)LF25$4.10$4.58$5.00$6.00$5.10$4.60$5.00
91Reflectorized pavement marking type II (W) (double arrow) (666-7187)EACH16$220.00$64.97$50.00$59.00$72.00$65.10$67.00
92Reflectorized pavement marking type II (W) (word) (666-7194)EACH12$95.00$64.97$50.00$59.00$72.00$65.10$67.00
93Reflectorized pavement marking type II (Y) 6" (broken) (666-7211)LF4,687$0.50$0.27$0.50$0.30$0.30$0.27$0.30
94Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF27,344$0.30$0.27$0.25$0.25$0.30$0.27$0.30
95Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF6,044$0.80$0.75$0.75$0.75$0.80$0.75$0.75
96Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF24,509$0.50$0.65$0.60$0.70$0.70$0.65$0.65
97Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF4,687$0.50$0.65$0.60$0.75$0.70$0.65$0.65
98Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF27,344$0.50$0.65$0.60$0.70$0.70$0.65$0.65
99Reflectorized pavement marker type I-C (672-7002)EACH302$2.00$4.58$10.00$11.00$5.10$4.60$5.00
100Reflectorized pavement marker type II-A-A (672-7004)EACH788$2.00$4.58$5.00$4.50$5.10$4.60$5.00
101Eliminating existing PM & markers (6") (677-7002)LF52,634$1.09$0.27$0.30$0.35$0.30$0.27$0.30
102Eliminating existing PM & markers (24") (677-7008)LF22$5.95$5.54$9.00$9.50$6.10$5.60$5.75
103Install highway traffic signal (isolated) (680-7002)EACH1$38,726$40,000$35,559$36,000$42,900$42,181
104Removing traffic signals (680-7004)EACH1$1,019.09$1,200.00$4,586.00$4,700.00$1,130.00$1,200.00
105Vehicle signal section (12")LED(green) (682-7001)EACH12$280.25$300.00$434.00$440.00$311.00$310.00
106Vehicle signal section (12")LED(green arrow) (682-7002)EACH2$280.25$300.00$434.00$440.00$311.00$310.00
107Vehicle signal section (12")LED(yel) (682-7003)EACH16$280.25$300.00$434.00$440.00$311.00$310.00
108Vehicle signal section (12")LED(yel arrow) (682-7004)EACH4$280.25$300.00$434.00$440.00$311.00$310.00
109Vehicle signal section (12")LED(red) (682-7005)EACH12$280.25$300.00$434.00$440.00$311.00$310.00
110Vehicle signal section (12")LED(red arrow) (682-7006)EACH2$280.25$300.00$434.00$440.00$311.00$310.00
111Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH12$168.15$180.00$238.00$242.00$186.00$185.00
112Backplate W/ref border(4 sec)(vent)aluminum (682-7043)EACH2$254.77$275.00$268.00$272.00$282.00$280.00
113Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF1,270$2.34$3.00$2.50$2.50$2.60$2.65
114Traffic signal CBL (type A)(14 AWG)(6 conductor) (684-7032)LF640$3.87$5.00$2.70$2.80$4.30$4.35
115Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF840$2.65$3.00$2.90$3.00$2.95$3.00
116Install RDSD FLSH BCN assembly (solar PWRD) (685-7004)EACH2$6,277.61$6,500.00$11,780$12,000$6,960.00$7,000.00
117Ins traffic signal PL AM(S)1 arm(32')lum (686-7035)EACH1$14,267$15,000$16,000$16,700$15,800$15,800
118Ins traffic signal PL AM(S)1 arm(40')lum (686-7043)EACH1$16,815$18,000$19,000$19,600$18,600$18,700
119Ins traffic signal PL AM(S)1 arm(50')lum (686-7055)EACH2$36,178$38,000$39,000$39,730$40,100$40,300
120Tree removal (24" - 30" diameter) (752-7008)EACH1$1,000.00$5,500.00$2,500.00$534.00$2,720.00$5,000.00$14,500
121Bonding course (3007-7001)GAL12,151$4.40$3.25$4.00$4.00$4.00$3.70$3.80
122ITS com CBL (ethernet) (6005-7001)LF75$2.55$3.00$5.50$6.00$2.80$2.85
123Bbu system (external battery cabinet) (6007-7001)EACH1$9,681.38$10,000$10,125$10,300$10,700$10,800
124RVDS (presence and advance detection) (6008-7003)EACH4$8,152.74$9,000.00$8,041.00$8,200.00$9,040.00$9,100.00
125CCTV field equipment (digital) (6018-7002)EACH1$3,413.96$3,500.00$9,351.00$9,500.00$3,780.00$3,700.00
126CCTV mount (pole) (6018-7003)EACH1$1.02$500.00$893.00$910.00$1.15$1.15
127Subsurface util locate (outside rdbed) (7019-7001)EACH10$1,000.00$407.64$500.00$1,919.00$950.00$1,070.00$895.00
TxDOT contract A00184596: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy