TxDOT contract A00184763 bid tabulation
Intersection Improvement, US 79 (0.2 miles east of FM 2549 to 0.2 miles west of FM 2549). Let by Texas DOT on February 6, 2025, Robertson, Bryan District. 7 bids received; low bid $897,290 by Cornerstone Paving and Construction, L.L.C., +0.7% against the engineer's estimate of $891,318.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 72
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Paving and Construction, L.L.C. | $897,290 | Low | +1.0% |
| 2 | Big Creek Construction, LTD. | $905,552 | +1.0% | +2.0% |
| 3 | Larry Young Paving, Inc. | $939,062 | +5.0% | +5.0% |
| 4 | Texas Materials Group, Inc. | $945,782 | +5.0% | +6.0% |
| 5 | Knife River Corporation - South | $1,009,199 | +12% | +13% |
| 6 | Lakey, Inc. | $1,112,441 | +24% | +25% |
| 7 | Brazos Paving, Inc. | $1,440,590 | +61% | +62% |
Engineer's estimate: $891,318.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Cornerstone Paving and Construction, L.L.C. | 2. Big Creek Construction, LTD. | 3. Larry Young Paving, Inc. | 4. Texas Materials Group, Inc. | 5. Knife River Corporation - South | 6. Lakey, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3 | $1,250.00 | $3,000.00 | $7,000.00 | $6,200.00 | $5,100.00 | $5,000.00 | $3,700.00 |
| 2 | Removing concrete (curb) (104-7016) | LF | 30 | $10.00 | $50.00 | $15.00 | $12.00 | $43.00 | $20.00 | $14.50 |
| 3 | Remove (3"-7") TRT/untrt base & asphalt pavement (105-7003) | SY | 236 | $7.00 | $44.00 | $11.00 | $17.00 | $15.00 | $17.50 | $8.77 |
| 4 | Remove (10") TRT/untrt base & asphalt pavement (105-7030) | SY | 252 | $8.00 | $47.00 | $12.00 | $16.00 | $28.00 | $37.00 | $8.77 |
| 5 | Remove (16") TRT/untrt base & asphalt pavement (105-7036) | SY | 1,140 | $10.00 | $16.00 | $15.00 | $10.00 | $17.00 | $16.00 | $10.78 |
| 6 | Excavation (roadway) (110-7001) | CY | 791 | $25.00 | $20.00 | $18.00 | $40.00 | $17.00 | $23.00 | $58.50 |
| 7 | Embankment (final)(DC)(type C) (132-7006) | CY | 364 | $28.00 | $20.00 | $18.00 | $40.00 | $33.00 | $15.00 | $26.00 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 5,170 | $1.60 | $2.00 | $2.50 | $1.50 | $0.75 | $1.00 | $3.20 |
| 9 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 5,170 | $0.50 | $0.60 | $0.56 | $1.25 | $0.90 | $0.85 | $0.50 |
| 10 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 2,585 | $0.60 | $0.60 | $0.51 | $1.25 | $0.90 | $0.85 | $0.50 |
| 11 | Hydro mulch seed (temporary_cool) (164-7022) | SY | 2,585 | $0.60 | $0.55 | $0.49 | $1.25 | $0.90 | $0.85 | $0.86 |
| 12 | Vegetative watering (168-7001) | TGL | 51.70 | $50.00 | $20.00 | $25.00 | $35.00 | $160.00 | $70.00 | $75.00 |
| 13 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 2,913 | $23.00 | $21.00 | $20.00 | $22.00 | $20.00 | $20.00 | $18.99 |
| 14 | FL BS (compacted in place)(type A GR 1-2) (9") (247-7350) | SY | 333 | $26.00 | $50.00 | $28.00 | $36.00 | $43.00 | $40.00 | $75.00 |
| 15 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 5 | $350.00 | $1,000.00 | $350.00 | $200.00 | $1,465.00 | $360.00 | $360.90 |
| 16 | Lime TRT (existing material)(6") (260-7006) | SY | 765 | $4.00 | $7.65 | $18.00 | $2.00 | $11.00 | $20.00 | $5.86 |
| 17 | Cement (275-7001) | TON | 23 | $290.00 | $325.00 | $250.00 | $280.00 | $355.00 | $225.00 | $262.50 |
| 18 | Cement TRT (existing material)(6") (275-7002) | SY | 3,061 | $4.00 | $4.00 | $6.00 | $3.75 | $2.50 | $3.50 | $4.69 |
| 19 | Prime coat (MC-30) (310-7004) | GAL | 629 | $11.00 | $8.00 | $7.50 | $6.75 | $6.50 | $8.00 | $11.50 |
| 20 | Prime coat (RC-250) (310-7006) | GAL | 73 | $11.00 | $40.00 | $15.00 | $24.00 | $23.00 | $22.00 | $202.75 |
| 21 | Aggregate (type-PB, GR-5)(sac-B) (316-7214) | CY | 2 | $210.00 | $1,800.00 | $1,500.00 | $670.00 | $2,770.00 | $2,500.00 | $102.13 |
| 22 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 1,145 | $125.00 | $112.00 | $115.00 | $120.00 | $132.50 | $129.00 | $150.00 |
| 23 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 1,849 | $135.00 | $138.00 | $135.00 | $140.00 | $148.50 | $137.00 | $170.31 |
| 24 | Tack coat (344-7077) | GAL | 2,050 | $4.50 | $3.50 | $7.50 | $6.00 | $4.00 | $5.00 | $7.00 |
| 25 | Flexible pavement structure repair(16") (351-7015) | SY | 114 | $130.00 | $200.00 | $175.00 | $200.00 | $345.00 | $255.00 | $92.00 |
| 26 | Planing asphalt concrete pavement(2") (354-7051) | SY | 14,028 | $3.50 | $2.10 | $3.00 | $3.00 | $2.40 | $1.50 | $3.50 |
| 27 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 16 | $310.00 | $365.00 | $575.00 | $310.00 | $374.00 | $550.00 | $495.95 |
| 28 | Riprap (stone protection)(12 in) (432-7041) | CY | 9 | $290.00 | $300.00 | $350.00 | $180.00 | $340.00 | $420.00 | $220.00 |
| 29 | Set (type I)(S= 5 FT)(HW= 2 FT)(4:1)(C) (467-7092) | EACH | 2 | $7,800.00 | $12,000 | $5,750.00 | $7,000.00 | $7,565.00 | $21,000 | $22,000 |
| 30 | Removing structure (headwall) (496-7006) | EACH | 1 | $1,800.00 | $2,500.00 | $2,000.00 | $1,300.00 | $2,445.00 | $5,500.00 | $2,139.71 |
| 31 | Removing structure (box culvert) (496-7008) | LF | 12 | $200.00 | $350.00 | $175.00 | $200.00 | $200.00 | $500.00 | $120.00 |
| 32 | Mobilization (500-7001) | LS | 1 | $84,833 | $50,000 | $75,000 | $87,000 | $72,134 | $94,869 | $60,000 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $10,000 | $5,000.00 | $6,000.00 | $3,300.00 | $2,580.00 | $16,300 | $5,000.00 |
| 34 | Portable changeable message sign (503-7002) | EACH | 2 | $7,000.00 | $10,000 | $5,000.00 | $1,200.00 | $4,850.00 | $6,000.00 | $9,150.00 |
| 35 | TMA (stationary) (505-7001) | DAY | 37 | $300.00 | $125.00 | $300.00 | $220.00 | $250.00 | $550.00 | $297.50 |
| 36 | TMA (mobile operation) (505-7003) | DAY | 4 | $320.00 | $125.00 | $400.00 | $1,100.00 | $730.00 | $1,000.00 | $169.82 |
| 37 | Rock filter dams (install) (type 2) (506-7002) | LF | 45 | $50.00 | $81.00 | $50.00 | $51.00 | $40.00 | $38.00 | $54.30 |
| 38 | Rock filter dams (remove) (506-7011) | LF | 45 | $16.00 | $25.00 | $20.00 | $13.00 | $10.00 | $10.00 | $17.03 |
| 39 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 105 | $12.00 | $8.00 | $7.50 | $10.00 | $8.00 | $7.50 | $8.00 |
| 40 | Biodegradable erosion control logs (remove) (506-7046) | LF | 105 | $5.00 | $1.00 | $1.50 | $2.00 | $1.60 | $1.50 | $2.00 |
| 41 | Concrete gutter (modified) (529-7011) | LF | 152 | $50.00 | $200.00 | $50.00 | $73.00 | $59.00 | $100.00 | $125.00 |
| 42 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 5,212 | $0.40 | $0.50 | $1.35 | $1.75 | $1.45 | $0.45 | $0.45 |
| 43 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 410 | $0.50 | $1.00 | $1.35 | $1.50 | $1.45 | $1.00 | $0.85 |
| 44 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 2 | $6,000.00 | $7,228.00 | $7,000.00 | $7,300.00 | $8,890.00 | $6,500.00 | $4,897.82 |
| 45 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 55 | $16.00 | $27.00 | $30.00 | $10.00 | $16.00 | $25.00 | $16.00 |
| 46 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 100 | $26.00 | $16.00 | $50.00 | $19.00 | $26.50 | $45.00 | $27.00 |
| 47 | Electrical conductor (no.8) bare (620-7007) | LF | 225 | $2.00 | $2.20 | $3.50 | $1.00 | $2.10 | $3.00 | $2.00 |
| 48 | Electrical conductor (no.8) insulated (620-7008) | LF | 450 | $2.30 | $2.30 | $3.50 | $1.25 | $2.10 | $3.20 | $1.87 |
| 49 | Ground box type A (122311)W/apron (624-7002) | EACH | 2 | $1,600.00 | $1,843.00 | $2,500.00 | $1,000.00 | $1,200.00 | $2,200.00 | $1,530.00 |
| 50 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $7,500.00 | $10,800 | $10,000 | $7,800.00 | $9,500.00 | $9,500.00 | $6,816.05 |
| 51 | Aluminum signs (type A) (636-7001) | SF | 52 | $50.00 | $40.00 | $45.00 | $33.00 | $42.00 | $40.00 | $39.00 |
| 52 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $685.00 | $850.00 | $875.00 | $940.00 | $900.00 | $850.00 | $721.26 |
| 53 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 7 | $600.00 | $800.00 | $825.00 | $740.00 | $850.00 | $800.00 | $600.00 |
| 54 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 1 | $640.00 | $750.00 | $775.00 | $810.00 | $800.00 | $750.00 | $650.00 |
| 55 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $100.00 | $100.00 | $125.00 | $190.00 | $270.00 | $100.00 | $115.00 |
| 56 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 2 | $90.00 | $100.00 | $125.00 | $130.00 | $100.00 | $100.00 | $182.00 |
| 57 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 6,067 | $0.60 | $0.50 | $0.52 | $1.25 | $0.50 | $0.50 | $0.58 |
| 58 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 6,190 | $0.60 | $0.50 | $0.52 | $1.25 | $0.52 | $0.50 | $0.58 |
| 59 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 309 | $5.10 | $5.00 | $7.00 | $9.25 | $5.00 | $5.00 | $4.40 |
| 60 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 76 | $1.50 | $1.00 | $1.50 | $0.75 | $1.50 | $1.00 | $1.50 |
| 61 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,064 | $1.50 | $1.00 | $1.50 | $0.75 | $1.40 | $1.00 | $1.60 |
| 62 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 73 | $3.10 | $3.00 | $1.06 | $4.00 | $3.20 | $3.00 | $2.50 |
| 63 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,493 | $1.80 | $1.20 | $1.06 | $2.75 | $1.25 | $1.20 | $2.04 |
| 64 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 30 | $4.85 | $10.00 | $10.60 | $5.25 | $10.50 | $10.00 | $3.18 |
| 65 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 6,235 | $0.60 | $0.75 | $0.77 | $1.25 | $0.80 | $0.75 | $4.00 |
| 66 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 103 | $0.60 | $2.00 | $0.77 | $1.25 | $2.10 | $2.00 | $5.00 |
| 67 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 8,308 | $0.60 | $0.75 | $0.77 | $1.25 | $0.80 | $0.75 | $5.00 |
| 68 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 4 | $285.00 | $250.00 | $304.00 | $470.00 | $265.00 | $250.00 | $292.00 |
| 69 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 4 | $300.00 | $300.00 | $374.00 | $470.00 | $320.00 | $300.00 | $362.50 |
| 70 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 2 | $750.00 | $700.00 | $777.00 | $870.00 | $740.00 | $700.00 | $900.00 |
| 71 | Reflectorized pavement marker type I-C (672-7002) | EACH | 76 | $6.50 | $6.00 | $7.00 | $9.25 | $6.40 | $6.00 | $5.50 |
| 72 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 843 | $6.50 | $5.00 | $7.00 | $9.25 | $5.25 | $5.00 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.