TxDOT contract A00185405 bid tabulation
Bridge Replacement, FRANKFORD RD E (Frankford Rd WB AT Furneaux Creek to .). Let by Texas DOT on June 3, 2026, Denton, Dallas District. 5 bids received; low bid $2,342,967 by Tucan Contracting, LLC, -6.5% against the engineer's estimate of $2,505,046.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 85
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Tucan Contracting, LLC | $2,342,967 | Low | -6.0% |
| 2 | Castillo Aranda LLC | $2,400,102 | +2.0% | -4.0% |
| 3 | Ed Bell Construction Company | $2,789,652 | +19% | +11% |
| 4 | Ibctx, LLC | $2,876,413 | +23% | +15% |
| 5 | Hodges and Son Construction Company, Inc. | $3,220,896 | +37% | +29% |
Engineer's estimate: $2,505,046.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Tucan Contracting, LLC | 2. Castillo Aranda LLC | 3. Ed Bell Construction Company | 4. Ibctx, LLC | 5. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7.20 | $5,000.00 | $4,327.30 | $8,000.00 | $14,800 | $5,000.00 | $9,700.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 382 | $25.00 | $16.35 | $20.00 | $25.00 | $27.00 | $45.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 54 | $70.00 | $43.60 | $30.00 | $40.00 | $18.00 | $30.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 49 | $35.00 | $21.80 | $20.00 | $40.00 | $20.00 | $40.00 |
| 5 | Removing concrete (curb) (104-7016) | LF | 431 | $10.00 | $2.18 | $3.00 | $10.00 | $13.00 | $15.00 |
| 6 | Remove (5"-9") TRT/untrt base & asphalt pavement (105-7005) | SY | 824 | $10.88 | $20.00 | $15.00 | $14.00 | $10.00 | |
| 7 | Excavation (roadway) (110-7001) | CY | 426 | $25.00 | $32.70 | $15.00 | $50.00 | $117.00 | $35.00 |
| 8 | Excavation (channel) (110-7002) | CY | 170 | $32.70 | $20.00 | $65.00 | $50.00 | $35.00 | |
| 9 | Embankment (final)(DC)(type C1) (132-7008) | CY | 28 | $32.70 | $20.00 | $25.00 | $400.00 | $100.00 | |
| 10 | Embankment (final)(DC)(type C2) (132-7010) | CY | 130 | $70.00 | $54.50 | $20.00 | $85.00 | $100.00 | $80.00 |
| 11 | Block sodding (162-7002) | SY | 358 | $8.00 | $8.72 | $6.00 | $5.25 | $32.00 | $10.00 |
| 12 | Drill seed (permanent_urban_clay) (164-7012) | SY | 919 | $1.64 | $1.00 | $5.25 | $2.00 | $4.00 | |
| 13 | Vegetative watering (168-7001) | TGL | 190 | $20.00 | $54.50 | $50.00 | $20.00 | $1.00 | $1.00 |
| 14 | FL BS(compacted in place)(type A,B or D GR4)(12") (247-7134) | SY | 940 | $32.70 | $40.00 | $45.00 | $57.00 | $70.00 | |
| 15 | Rework BS metal (type B)(10")(density control) (251-7030) | SY | 261 | $4.00 | $5.45 | $40.00 | $16.00 | $55.00 | $40.00 |
| 16 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 189 | $15.53 | $10.00 | $16.50 | $15.00 | $25.00 | |
| 17 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 91 | $291.30 | $280.00 | $308.00 | $275.00 | $300.00 | |
| 18 | Concrete pavement (CRCP) (9") (360-7003) | SY | 236 | $120.00 | $185.30 | $70.00 | $160.00 | $262.00 | $200.00 |
| 19 | Drilled shaft (24 in) (416-7004) | LF | 834 | $175.00 | $119.90 | $250.00 | $153.00 | $200.00 | $175.00 |
| 20 | Drilled shaft (36 in) (416-7006) | LF | 222 | $212.55 | $350.00 | $273.00 | $315.00 | $275.00 | |
| 21 | Class C concrete (abutment)(HPC) (420-7013) | CY | 83.30 | $1,300.00 | $1,308.00 | $1,300.00 | $1,500.00 | $1,850.00 | $2,000.00 |
| 22 | Class C concrete (cap)(HPC) (420-7023) | CY | 58.50 | $1,500.00 | $1,471.50 | $1,200.00 | $1,500.00 | $1,850.00 | $2,000.00 |
| 23 | Class C concrete (column)(HPC) (420-7039) | CY | 33.60 | $1,300.00 | $1,744.00 | $1,000.00 | $2,500.00 | $1,850.00 | $2,000.00 |
| 24 | Reinforced concrete slab (HPC) (422-7002) | SF | 4,200 | $29.43 | $19.00 | $30.00 | $35.00 | $38.00 | |
| 25 | Reinforced concrete slab (slab beam)(HPC) (422-7008) | SF | 6,744 | $25.00 | $23.98 | $16.00 | $19.00 | $21.00 | $25.00 |
| 26 | Approach slab (HPC) (422-7014) | CY | 130.40 | $750.00 | $926.50 | $600.00 | $675.00 | $1,100.00 | $1,500.00 |
| 27 | Bridge sidewalk(HPC) (422-7022) | SF | 1,315 | $15.00 | $21.80 | $7.00 | $13.00 | $27.00 | $85.00 |
| 28 | Prestressed concrete girder (TX28) (425-7001) | LF | 553.92 | $283.40 | $300.00 | $353.00 | $325.00 | $340.00 | |
| 29 | Prestressed concrete slab beam (4SB12) (425-7016) | LF | 474.06 | $215.00 | $268.43 | $280.00 | $303.00 | $245.00 | $300.00 |
| 30 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 948.12 | $200.00 | $236.57 | $280.00 | $303.00 | $245.00 | $300.00 |
| 31 | Opaque sealer finish (427-7003) | SF | 4,026 | $3.00 | $3.27 | $5.00 | $1.38 | $4.00 | $10.00 |
| 32 | Riprap (concrete)(CL B)(5 in) (432-7008) | CY | 10.30 | $800.00 | $981.00 | $400.00 | $1,000.00 | $800.00 | $800.00 |
| 33 | Riprap (mow strip)(4 in) (432-7013) | CY | 28 | $708.50 | $450.00 | $700.00 | $800.00 | $750.00 | |
| 34 | Riprap (stone protection)(12 in) (432-7041) | CY | 490 | $174.40 | $325.00 | $180.00 | $165.00 | $200.00 | |
| 35 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 670 | $20.00 | $27.25 | $30.00 | $20.00 | $40.00 | $10.00 |
| 36 | Rail (type T223)(HPC) (450-7009) | LF | 328 | $174.40 | $220.00 | $150.00 | $175.00 | $150.00 | |
| 37 | Rail (type C221)(HPC) (450-7033) | LF | 356 | $160.00 | $196.20 | $220.00 | $200.00 | $200.00 | $200.00 |
| 38 | Armor joint (sealed) (454-7003) | LF | 170 | $150.00 | $109.00 | $200.00 | $75.00 | $130.00 | $250.00 |
| 39 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 2 | $75,000 | $43,600 | $40,000 | $30,000 | $40,000 | $75,000 |
| 40 | Remove STR (rail) (496-7017) | LF | 260 | $27.25 | $10.00 | $25.00 | $50.00 | $25.00 | |
| 41 | Mobilization (500-7001) | LS | 1 | $225,000 | $100,000 | $100,000 | $273,000 | $287,000 | $290,000 |
| 42 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $8,500.00 | $2,725.00 | $4,500.00 | $12,500 | $4,000.00 | $6,000.00 |
| 43 | TMA (stationary) (505-7001) | DAY | 100 | $250.00 | $239.80 | $200.00 | $75.00 | $25.00 | $300.00 |
| 44 | TMA (mobile operation) (505-7003) | DAY | 7 | $400.00 | $953.75 | $550.00 | $1,000.00 | $50.00 | $300.00 |
| 45 | Rock filter dams (install) (type 3) (506-7003) | LF | 299 | $50.00 | $92.65 | $30.00 | $93.00 | $90.00 | $1.00 |
| 46 | Rock filter dams (remove) (506-7011) | LF | 299 | $20.00 | $13.08 | $5.00 | $12.00 | $13.00 | $1.00 |
| 47 | Construction exits (install) (type 1) (506-7020) | SY | 267 | $36.00 | $37.06 | $30.00 | $37.40 | $36.00 | $1.00 |
| 48 | Construction exits (remove) (506-7024) | SY | 267 | $14.00 | $11.99 | $5.00 | $11.00 | $12.00 | $1.00 |
| 49 | Temporary sediment control fence (install) (506-7039) | LF | 1,006 | $5.00 | $3.87 | $4.00 | $3.90 | $8.00 | $1.00 |
| 50 | Temporary sediment control fence (remove) (506-7041) | LF | 1,006 | $1.50 | $1.20 | $1.00 | $1.10 | $4.00 | $1.00 |
| 51 | Constructing detours (508-7001) | SY | 218 | $110.00 | $196.20 | $55.00 | $250.00 | $185.00 | $200.00 |
| 52 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 200 | $50.00 | $103.55 | $60.00 | $40.00 | $50.00 | $90.00 |
| 53 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 200 | $15.00 | $38.15 | $10.00 | $20.00 | $50.00 | $50.00 |
| 54 | Remove and relay pavers (528-7003) | SY | 39 | $325.00 | $545.00 | $50.00 | $275.00 | $500.00 | $50.00 |
| 55 | Concrete curb (type II) (529-7002) | LF | 381 | $55.00 | $32.70 | $6.00 | $15.00 | $45.00 | $30.00 |
| 56 | Concrete curb & gutter (type II) (529-7009) | LF | 57 | $60.00 | $32.70 | $13.00 | $60.00 | $68.00 | $35.00 |
| 57 | Concrete sidewalks (4") (531-7001) | SY | 39 | $100.00 | $76.30 | $65.00 | $100.00 | $100.00 | $80.00 |
| 58 | Right of way markers (538-7001) | EACH | 11 | $463.25 | $20.00 | $467.50 | $500.00 | $250.00 | |
| 59 | Metal W-beam guard fence (timber post) (540-7001) | LF | 300 | $35.00 | $24.53 | $40.00 | $24.75 | $32.00 | $25.00 |
| 60 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $1,200.00 | $1,308.00 | $3,500.00 | $1,320.00 | $1,650.00 | $1,200.00 |
| 61 | Remove metal beam guard fence (542-7001) | LF | 223 | $5.00 | $3.00 | $10.00 | $9.65 | $3.00 | $2.00 |
| 62 | Guardrail end treatment (install) (544-7001) | EACH | 7 | $3,000.00 | $3,215.50 | $1,500.00 | $3,245.00 | $3,400.00 | $3,200.00 |
| 63 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $250.00 | $272.50 | $500.00 | $275.00 | $300.00 | $500.00 |
| 64 | Crash cushion attenuator (install)(S)(N)(TL2) (545-7013) | EACH | 2 | $20,000 | $9,646.50 | $24,500 | $9,950.00 | $10,000 | $10,000 |
| 65 | Wire fence (type C) (552-7003) | LF | 345 | $15.53 | $20.00 | $15.68 | $25.00 | $25.00 | |
| 66 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 2 | $25.00 | $21.80 | $20.00 | $22.00 | $16.00 | $20.00 |
| 67 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 4 | $21.80 | $500.00 | $22.00 | $16.00 | $20.00 | |
| 68 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 2 | $45.00 | $27.25 | $500.00 | $27.50 | $26.00 | $30.00 |
| 69 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 4 | $27.25 | $500.00 | $27.50 | $26.00 | $30.00 | |
| 70 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 3 | $25.00 | $21.80 | $300.00 | $22.00 | $16.00 | $30.00 |
| 71 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 4 | $25.00 | $27.25 | $500.00 | $27.50 | $26.00 | $30.00 |
| 72 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 1,969 | $0.50 | $0.95 | $1.00 | $1.25 | $1.00 | $4.00 |
| 73 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 527 | $0.80 | $1.47 | $2.00 | $2.50 | $2.00 | $4.00 |
| 74 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 2,916 | $0.50 | $0.95 | $1.00 | $1.25 | $1.00 | $4.00 |
| 75 | Pavement sler 6" (666-7347) | LF | 1,588 | $0.50 | $0.38 | $1.00 | $0.60 | $0.50 | $1.00 |
| 76 | Pavement sler 8" (666-7348) | LF | 280 | $6.00 | $0.55 | $1.00 | $0.80 | $0.75 | $2.00 |
| 77 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 1,690 | $1.00 | $1.08 | $1.00 | $1.25 | $1.25 | $4.00 |
| 78 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 920 | $1.08 | $1.00 | $1.35 | $1.25 | $4.00 | |
| 79 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 920 | $1.08 | $1.00 | $1.25 | $1.25 | $4.00 | |
| 80 | Prefabricated PM type C (W)(8")(solid) (668-7084) | LF | 410 | $6.00 | $7.50 | $7.00 | $8.00 | $7.00 | $10.00 |
| 81 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 12 | $5.45 | $6.00 | $6.00 | $6.00 | $10.00 | |
| 82 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 115 | $8.00 | $5.45 | $6.00 | $6.00 | $6.00 | $10.00 |
| 83 | Eliminating existing PM & markers (6") (677-7002) | LF | 5,412 | $1.50 | $0.81 | $1.00 | $1.00 | $1.00 | $2.00 |
| 84 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,588 | $0.50 | $0.27 | $0.50 | $0.60 | $0.30 | $1.00 |
| 85 | Pavement surface preparation for marking (8") (678-7004) | LF | 280 | $0.75 | $0.55 | $1.00 | $0.80 | $0.55 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.