TxDOT contract A00192967 bid tabulation
Intersection Improvements With Right And/Or Left Turn Lanes, FM 974 (At SH 6 West Frontage Rd. to .). Let by Texas DOT on August 7, 2025, Brazos, Bryan District. 5 bids received; low bid $2,808,685 by Larry Young Paving, Inc., -0.6% against the engineer's estimate of $2,824,746.
- Owner
- Texas DOT
- Letting
- 07 AUG 2025
- Pay items
- 169
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Larry Young Paving, Inc. | $2,808,685 | Low | -1.0% |
| 2 | Knife River Corporation - South | $2,993,064 | +7.0% | +6.0% |
| 3 | Big Creek Construction, LTD. | $3,093,585 | +10% | +10% |
| 4 | Cornerstone Paving and Construction, L.L.C. | $3,466,663 | +23% | +23% |
| 5 | Brazos Paving, Inc. | $3,721,478 | +32% | +32% |
Engineer's estimate: $2,824,746.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Larry Young Paving, Inc. | 2. Knife River Corporation - South | 3. Big Creek Construction, LTD. | 4. Cornerstone Paving and Construction, L.L.C. | 5. Brazos Paving, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 29 | $375.00 | $64.00 | $877.00 | $700.00 | $400.00 | $4,084.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 5 | $1,000.00 | $1,100.00 | $967.00 | $1,200.00 | $1,250.00 | $386.35 |
| 3 | Tree protection (install) (100-7013) | EACH | 11 | $200.00 | $700.00 | $600.00 | $600.00 | $550.00 | $710.00 |
| 4 | Tree protection (remove) (100-7015) | EACH | 11 | $130.00 | $190.00 | $163.00 | $150.00 | $150.00 | $200.00 |
| 5 | Removing concrete (pavement) (104-7001) | SY | 426 | $15.00 | $20.00 | $26.00 | $20.00 | $42.50 | $26.25 |
| 6 | Removing concrete (riprap) (104-7006) | SY | 93 | $30.00 | $20.00 | $17.70 | $15.00 | $30.00 | $44.25 |
| 7 | Removing concrete (medians) (104-7008) | SY | 112 | $15.00 | $20.00 | $33.00 | $20.00 | $30.00 | $46.85 |
| 8 | Removing concrete (curb & gutter) (104-7017) | LF | 434 | $10.00 | $9.50 | $39.00 | $17.00 | $15.00 | $13.00 |
| 9 | Removing concrete (flume) (104-7041) | SY | 79 | $50.00 | $20.00 | $18.00 | $17.00 | $30.00 | $52.40 |
| 10 | Remove (0"-6") TRT/untrt base & asphalt pavement (105-7046) | SY | 1,279 | $15.00 | $7.50 | $4.87 | $9.00 | $30.00 | $12.50 |
| 11 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 3,553 | $10.00 | $12.00 | $10.54 | $14.00 | $32.65 | $16.35 |
| 12 | Excavation (roadway) (110-7001) | CY | 2,986 | $18.00 | $26.00 | $36.48 | $26.00 | $30.00 | $29.30 |
| 13 | Embankment (final)(DC)(type C) (132-7006) | CY | 892 | $25.00 | $22.00 | $10.35 | $26.00 | $22.00 | $49.10 |
| 14 | Furn & place topsoil (4") (160-7002) | SY | 9,161 | $0.50 | $1.50 | $1.57 | $3.00 | $1.00 | $4.65 |
| 15 | Block sodding (162-7002) | SY | 210 | $7.50 | $7.75 | $6.52 | $6.60 | $6.00 | $7.75 |
| 16 | Broadcast seed (permanent_urban_sand) (164-7003) | SY | 8,266 | $1.25 | $0.50 | $0.38 | $0.40 | $0.35 | $0.45 |
| 17 | Broadcast seed (temporary_warm) (164-7005) | SY | 343 | $1.00 | $0.50 | $0.33 | $0.33 | $0.30 | $0.40 |
| 18 | Broadcast seed (temporary_cool) (164-7006) | SY | 343 | $1.00 | $0.50 | $0.33 | $0.33 | $0.30 | $0.40 |
| 19 | Vegetative watering (168-7001) | TGL | 91.70 | $100.00 | $42.00 | $44.00 | $20.00 | $50.00 | $148.30 |
| 20 | Proof rolling (216-7001) | HR | 10 | $250.00 | $93.00 | $95.00 | $250.00 | $250.00 | $149.50 |
| 21 | FL BS (compacted in place)(type A GR 1-2) (11") (247-7339) | SY | 5,587 | $35.00 | $35.00 | $28.28 | $40.00 | $45.00 | $25.00 |
| 22 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 61 | $350.00 | $750.00 | $338.00 | $375.00 | $350.00 | $425.00 |
| 23 | Lime TRT (existing material)(8") (260-7007) | SY | 5,765 | $6.50 | $6.50 | $8.99 | $6.00 | $7.75 | $17.00 |
| 24 | Cement (275-7001) | TON | 61 | $250.00 | $170.00 | $215.00 | $250.00 | $350.00 | $362.00 |
| 25 | Cement treat (subgrade) (8") (275-7017) | SY | 5,765 | $5.50 | $2.00 | $3.47 | $6.00 | $4.00 | $10.90 |
| 26 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,440 | $4.50 | $7.75 | $6.60 | $7.00 | $6.00 | $12.50 |
| 27 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 1,155 | $110.00 | $130.00 | $121.00 | $130.00 | $140.00 | $141.50 |
| 28 | Tack coat (344-7077) | GAL | 1,595 | $4.50 | $7.25 | $4.00 | $6.50 | $5.00 | $7.40 |
| 29 | Stone-MTRX-asphalt SMA-C sac-A PG76-22 (346-7001) | TON | 1,751 | $190.00 | $140.00 | $125.00 | $160.00 | $146.00 | $199.30 |
| 30 | Planing asphalt concrete pavement(2") (354-7051) | SY | 10,763 | $3.50 | $1.75 | $2.00 | $2.50 | $4.00 | $5.00 |
| 31 | Planing asphalt concrete pavement(6") (354-7055) | SY | 365 | $5.00 | $3.25 | $68.00 | $10.00 | $24.65 | $23.10 |
| 32 | Cut & restoring pavement (400-7006) | SY | 18 | $100.00 | $250.00 | $144.50 | $190.00 | $250.00 | $185.60 |
| 33 | Cem stabil BKFL (400-7010) | CY | 18 | $200.00 | $100.00 | $122.00 | $200.00 | $200.00 | $129.50 |
| 34 | Trench excavation protection (402-7001) | LF | 571 | $5.00 | $1.25 | $25.00 | $15.00 | $12.00 | $8.00 |
| 35 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 22 | $200.00 | $240.00 | $208.00 | $300.00 | $192.00 | $246.50 |
| 36 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 48 | $200.00 | $290.00 | $204.00 | $275.00 | $188.00 | $241.00 |
| 37 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 28 | $280.00 | $320.00 | $250.00 | $310.00 | $231.00 | $296.40 |
| 38 | Riprap (concrete)(4 in) (432-7001) | CY | 40 | $800.00 | $750.00 | $684.00 | $750.00 | $800.00 | $1,020.00 |
| 39 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 8 | $550.00 | $880.00 | $1,055.00 | $750.00 | $800.00 | $1,055.00 |
| 40 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 709 | $225.00 | $160.00 | $158.00 | $175.00 | $150.00 | $350.00 |
| 41 | Riprap (stone protection)(18 in) (432-7043) | CY | 260 | $200.00 | $150.00 | $157.00 | $200.00 | $240.00 | $350.00 |
| 42 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 94 | $350.00 | $360.00 | $317.00 | $450.00 | $700.00 | $417.00 |
| 43 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 50 | $425.00 | $510.00 | $524.00 | $475.00 | $750.00 | $495.65 |
| 44 | RC pipe (CL III)(18 in) (464-7003) | LF | 43 | $70.00 | $99.00 | $143.00 | $85.00 | $62.00 | $211.30 |
| 45 | RC pipe (CL III)(42 in) (464-7010) | LF | 494 | $220.00 | $190.00 | $191.00 | $225.00 | $300.00 | $275.90 |
| 46 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 1 | $7,500.00 | $7,500.00 | $6,460.00 | $8,000.00 | $5,500.00 | $7,783.00 |
| 47 | Inlet (complete)(pco)(3FT)(right) (465-7015) | EACH | 3 | $6,500.00 | $14,000 | $7,949.00 | $7,750.00 | $5,500.00 | $7,140.00 |
| 48 | Inlet (complete)(PSL)(RC)(5FTX5FT) (465-7074) | EACH | 1 | $11,500 | $15,000 | $6,970.00 | $9,000.00 | $7,000.00 | $8,390.00 |
| 49 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 3 | $10,000 | $8,800.00 | $7,584.00 | $10,500 | $7,000.00 | $9,112.00 |
| 50 | Inlet (complete)(type sidewalk bridge)(mod) (465-7374) | EACH | 6 | $10,000 | $18,000 | $36,997 | $25,000 | $35,500 | $22,134 |
| 51 | Wingwall (FW - S) (HW=4 FT) (466-7160) | EACH | 1 | $12,000 | $9,600.00 | $17,450 | $16,500 | $9,000.00 | $17,380 |
| 52 | Wingwall (SW - 0) (HW=3 FT) (466-7202) | EACH | 1 | $6,500.00 | $8,300.00 | $17,900 | $12,000 | $3,500.00 | $13,420 |
| 53 | Set (type I)(S= 3 FT)(HW= 3 FT)(6:1)(P) (467-7043) | EACH | 3 | $12,500 | $4,300.00 | $6,945.00 | $16,000 | $9,500.00 | $9,600.00 |
| 54 | Set (type II) (42 in) (RCP) (3: 1) (C) (467-7377) | EACH | 1 | $6,000.00 | $9,500.00 | $4,377.00 | $8,500.00 | $6,500.00 | $5,950.00 |
| 55 | Adjusting manholes (479-7001) | EACH | 2 | $2,000.00 | $1,600.00 | $2,810.00 | $4,500.00 | $1,200.00 | $1,300.00 |
| 56 | Clean existing culverts (480-7001) | EACH | 1 | $2,000.00 | $6,300.00 | $4,000.00 | $3,600.00 | $1,500.00 | $5,000.00 |
| 57 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,300.00 | $1,700.00 | $456.00 | $1,200.00 | $1,200.00 | $912.00 |
| 58 | Removing structure (wingwall) (496-7005) | EACH | 4 | $2,000.00 | $1,200.00 | $2,638.00 | $3,000.00 | $1,500.00 | $1,675.00 |
| 59 | Removing structure (pipe) (496-7007) | LF | 53 | $25.00 | $32.00 | $21.00 | $17.50 | $30.00 | $74.40 |
| 60 | Remove STR (driveway culvert) (496-7038) | EACH | 3 | $500.00 | $1,700.00 | $1,100.00 | $425.00 | $1,200.00 | $2,635.00 |
| 61 | Mobilization (500-7001) | LS | 1 | $270,845 | $270,000 | $244,300 | $200,000 | $220,000 | $210,850 |
| 62 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $3,700.00 | $2,600.00 | $5,200.00 | $2,500.00 | $6,500.00 | $8,175.00 |
| 63 | Portable changeable message sign (503-7002) | EACH | 2 | $9,000.00 | $1,200.00 | $13,000 | $15,000 | $18,000 | $18,385 |
| 64 | TMA (stationary) (505-7001) | DAY | 135 | $200.00 | $250.00 | $500.00 | $300.00 | $150.00 | $386.00 |
| 65 | TMA (mobile operation) (505-7003) | DAY | 6 | $250.00 | $1,200.00 | $900.00 | $600.00 | $150.00 | $800.00 |
| 66 | Rock filter dams (install) (type 2) (506-7002) | LF | 692 | $45.00 | $45.00 | $38.00 | $40.00 | $35.00 | $45.00 |
| 67 | Rock filter dams (install) (type 3) (506-7003) | LF | 25 | $75.00 | $96.00 | $81.00 | $85.00 | $75.00 | $96.50 |
| 68 | Rock filter dams (remove) (506-7011) | LF | 717 | $10.00 | $13.00 | $11.00 | $10.00 | $10.00 | $13.00 |
| 69 | Construction exits (install) (type 1) (506-7020) | SY | 222 | $20.00 | $41.00 | $35.00 | $35.00 | $32.00 | $41.20 |
| 70 | Construction exits (remove) (506-7024) | SY | 222 | $10.00 | $15.00 | $13.00 | $12.00 | $12.00 | $15.50 |
| 71 | Temporary sediment control fence (install) (506-7039) | LF | 203 | $4.00 | $5.75 | $4.89 | $5.00 | $4.50 | $5.80 |
| 72 | Temporary sediment control fence (remove) (506-7041) | LF | 203 | $1.00 | $1.25 | $1.00 | $1.00 | $1.00 | $1.30 |
| 73 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 459 | $6.00 | $6.00 | $5.16 | $5.50 | $4.75 | $6.15 |
| 74 | Biodegradable erosion control logs (remove) (506-7046) | LF | 459 | $1.50 | $1.25 | $1.00 | $1.00 | $1.00 | $1.30 |
| 75 | Constructing detours (508-7001) | SY | 496 | $60.00 | $120.00 | $131.65 | $100.00 | $155.00 | $78.85 |
| 76 | Colored textured concrete (4") (527-7001) | SY | 158 | $125.00 | $140.00 | $160.89 | $150.00 | $260.00 | $147.40 |
| 77 | Concrete curb (type II) (529-7002) | LF | 57 | $25.00 | $11.00 | $66.40 | $55.00 | $60.00 | $17.80 |
| 78 | Concrete curb & gutter (type II) (529-7009) | LF | 1,372 | $45.00 | $41.00 | $34.24 | $65.00 | $85.00 | $27.60 |
| 79 | Driveways (concrete) (530-7006) | SY | 109 | $100.00 | $120.00 | $133.00 | $130.00 | $200.00 | $116.00 |
| 80 | Driveways (ACP) (530-7010) | SY | 120 | $50.00 | $65.00 | $127.00 | $75.00 | $190.00 | $140.70 |
| 81 | Concrete sidewalks (5") (531-7002) | SY | 877 | $150.00 | $80.00 | $81.43 | $120.00 | $180.00 | $116.00 |
| 82 | Curb ramps (type 7) (531-7010) | EACH | 5 | $2,750.00 | $2,500.00 | $1,950.00 | $3,300.00 | $4,000.00 | $2,030.00 |
| 83 | Curb ramps (type 21) (531-7013) | EACH | 1 | $5,500.00 | $4,300.00 | $2,000.00 | $4,600.00 | $4,000.00 | $2,525.00 |
| 84 | Relocate existing mailbox (560-7012) | EACH | 2 | $500.00 | $480.00 | $215.00 | $250.00 | $100.00 | $450.00 |
| 85 | In RD IL (type SA) 20T-8 (150W EQ) LED (610-7036) | EACH | 2 | $1,800.00 | $5,300.00 | $5,290.00 | $6,100.00 | $4,900.00 | $6,260.00 |
| 86 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 1 | $4,600.00 | $6,000.00 | $6,215.00 | $6,600.00 | $5,720.00 | $7,356.00 |
| 87 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 1,935 | $15.00 | $10.00 | $14.59 | $8.75 | $14.00 | $17.30 |
| 88 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,595 | $20.00 | $18.00 | $20.38 | $10.15 | $19.00 | $24.15 |
| 89 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 815 | $15.00 | $14.00 | $18.21 | $15.75 | $17.00 | $21.55 |
| 90 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 665 | $25.00 | $22.00 | $26.90 | $21.00 | $25.00 | $31.85 |
| 91 | Electrical conductor (no.8) insulated (620-7008) | LF | 6,780 | $2.00 | $1.25 | $2.79 | $1.85 | $3.00 | $3.30 |
| 92 | Electrical conductor (no.6) bare (620-7009) | LF | 4,475 | $2.20 | $1.25 | $2.23 | $2.10 | $2.25 | $2.65 |
| 93 | Electrical conductor (no.6) insulated (620-7010) | LF | 535 | $2.00 | $1.50 | $2.48 | $2.55 | $2.50 | $2.95 |
| 94 | Electrical conductor (no.4) bare (620-7011) | LF | 395 | $2.75 | $2.25 | $3.52 | $3.60 | $3.25 | $4.20 |
| 95 | Electrical conductor (no.4) insulated (620-7012) | LF | 790 | $3.10 | $2.75 | $4.15 | $4.15 | $4.00 | $4.90 |
| 96 | Ground box type D (162922) (624-7007) | EACH | 2 | $1,200.00 | $1,600.00 | $1,092.00 | $1,075.00 | $1,006.00 | $1,293.00 |
| 97 | Ground box type D (162922)W/apron (624-7008) | EACH | 12 | $1,100.00 | $1,800.00 | $1,324.00 | $1,475.00 | $1,220.00 | $1,567.00 |
| 98 | Remove ground box (624-7013) | EACH | 10 | $300.00 | $470.00 | $116.00 | $525.00 | $110.00 | $137.30 |
| 99 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $7,500.00 | $8,600.00 | $9,619.00 | $11,000 | $8,900.00 | $11,386 |
| 100 | Aluminum signs (type A) (636-7001) | SF | 66 | $30.00 | $110.00 | $33.15 | $80.00 | $31.00 | $39.20 |
| 101 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 36 | $550.00 | $720.00 | $614.00 | $575.00 | $720.00 | $925.00 |
| 102 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $700.00 | $860.00 | $734.00 | $700.00 | $725.00 | $1,027.00 |
| 103 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 6 | $785.00 | $980.00 | $832.00 | $775.00 | $800.00 | $1,240.00 |
| 104 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,000.00 | $1,100.00 | $950.00 | $900.00 | $1,150.00 | $1,475.00 |
| 105 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 2 | $1,100.00 | $1,500.00 | $1,300.00 | $1,225.00 | $1,350.00 | $1,707.00 |
| 106 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 2 | $100.00 | $110.00 | $93.00 | $90.00 | $122.50 | $157.60 |
| 107 | Install object marker assembly (OM-4)(TWT)wap (658-7073) | EACH | 35 | $100.00 | $400.00 | $350.00 | $320.00 | $418.00 | $540.00 |
| 108 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 541 | $0.30 | $0.50 | $0.57 | $0.50 | $0.52 | $0.70 |
| 109 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 6,262 | $0.30 | $0.50 | $0.57 | $0.45 | $0.52 | $0.70 |
| 110 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 261 | $0.50 | $0.75 | $1.13 | $0.60 | $1.04 | $1.35 |
| 111 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 7,128 | $0.30 | $0.50 | $0.57 | $0.45 | $0.52 | $0.70 |
| 112 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 591 | $1.50 | $0.50 | $1.50 | $1.50 | $1.00 | $2.00 |
| 113 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 75 | $1.00 | $0.50 | $1.50 | $1.50 | $1.00 | $2.00 |
| 114 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 334 | $1.50 | $0.50 | $1.50 | $1.50 | $1.00 | $2.00 |
| 115 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 105 | $2.00 | $2.00 | $2.72 | $1.75 | $2.50 | $3.25 |
| 116 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 957 | $1.30 | $1.50 | $2.17 | $1.50 | $2.00 | $2.60 |
| 117 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 350 | $12.00 | $11.00 | $8.42 | $9.50 | $7.75 | $10.00 |
| 118 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 14 | $150.00 | $180.00 | $288.00 | $150.00 | $265.00 | $341.00 |
| 119 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 10 | $215.00 | $200.00 | $310.00 | $160.00 | $285.00 | $367.00 |
| 120 | Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087) | EACH | 14 | $50.00 | $45.00 | $52.00 | $40.00 | $48.00 | $61.10 |
| 121 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 200 | $5.00 | $9.00 | $9.00 | $7.50 | $8.00 | $10.00 |
| 122 | Pavement sler 6" (666-7347) | LF | 540 | $1.00 | $0.25 | $0.20 | $0.30 | $0.18 | $0.25 |
| 123 | Pavement sler 8" (666-7348) | LF | 135 | $1.25 | $0.50 | $0.26 | $0.35 | $0.24 | $0.30 |
| 124 | Pavement sler 24" (666-7352) | LF | 24 | $4.00 | $2.50 | $0.78 | $2.25 | $0.72 | $1.00 |
| 125 | Pavement sler (arrow) (666-7353) | EACH | 3 | $40.00 | $26.00 | $6.00 | $25.00 | $5.00 | $6.50 |
| 126 | Pavement sler (word) (666-7354) | EACH | 1 | $45.00 | $26.00 | $6.00 | $25.00 | $5.00 | $6.50 |
| 127 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 590 | $1.00 | $1.25 | $0.85 | $1.15 | $0.80 | $1.00 |
| 128 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 3,770 | $1.00 | $1.25 | $0.85 | $1.10 | $0.80 | $1.00 |
| 129 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 260 | $1.00 | $1.25 | $0.85 | $1.15 | $0.80 | $1.00 |
| 130 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 6,001 | $1.00 | $1.25 | $0.85 | $1.10 | $0.80 | $1.00 |
| 131 | Reflectorized pavement marker type I-C (672-7002) | EACH | 73 | $9.00 | $6.00 | $7.00 | $5.50 | $6.00 | $7.75 |
| 132 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 117 | $7.00 | $6.00 | $7.00 | $5.50 | $6.00 | $7.75 |
| 133 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 18 | $6.00 | $6.00 | $7.00 | $5.50 | $6.00 | $7.75 |
| 134 | Eliminating existing PM & markers (6") (677-7002) | LF | 10,343 | $0.75 | $1.00 | $0.53 | $0.85 | $0.50 | $0.65 |
| 135 | Eliminating existing PM & markers (8") (677-7004) | LF | 151 | $1.00 | $1.25 | $2.00 | $1.00 | $1.00 | $1.25 |
| 136 | Eliminating existing PM & markers (24") (677-7008) | LF | 40 | $3.50 | $3.25 | $3.00 | $2.75 | $2.10 | $2.70 |
| 137 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $60.00 | $96.00 | $77.00 | $80.00 | $70.00 | $90.00 |
| 138 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 5 | $80.00 | $130.00 | $77.00 | $125.00 | $70.00 | $90.00 |
| 139 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $60.00 | $96.00 | $77.00 | $100.00 | $70.00 | $90.00 |
| 140 | Pavement surface preparation for marking (6") (678-7002) | LF | 540 | $1.25 | $0.25 | $0.26 | $0.30 | $0.24 | $0.30 |
| 141 | Pavement surface preparation for marking (8") (678-7004) | LF | 135 | $1.25 | $0.25 | $0.35 | $0.35 | $0.35 | $0.40 |
| 142 | Pavement surface preparation for marking (24") (678-7008) | LF | 24 | $4.00 | $2.50 | $2.00 | $2.50 | $1.00 | $1.25 |
| 143 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 3 | $20.00 | $26.00 | $27.00 | $30.00 | $25.00 | $32.15 |
| 144 | Pavement surface preparation for marking (word) (678-7016) | EACH | 1 | $25.00 | $38.00 | $27.00 | $40.00 | $25.00 | $32.15 |
| 145 | Install highway traffic signal (system) (680-7003) | EACH | 1 | $28,000 | $70,000 | $35,200 | $46,500 | $33,000 | $41,640 |
| 146 | Removing traffic signals (680-7004) | EACH | 1 | $5,000.00 | $11,000 | $2,941.00 | $9,500.00 | $2,800.00 | $3,485.00 |
| 147 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 12 | $225.00 | $250.00 | $271.00 | $400.00 | $250.00 | $321.00 |
| 148 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 3 | $250.00 | $250.00 | $288.00 | $405.00 | $275.00 | $341.00 |
| 149 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 12 | $225.00 | $250.00 | $275.00 | $400.00 | $260.00 | $325.00 |
| 150 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 4 | $250.00 | $250.00 | $280.00 | $405.00 | $260.00 | $330.00 |
| 151 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 12 | $250.00 | $250.00 | $271.00 | $400.00 | $250.00 | $321.00 |
| 152 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 3 | $250.00 | $250.00 | $280.00 | $405.00 | $260.00 | $330.00 |
| 153 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 4 | $590.00 | $560.00 | $835.00 | $915.00 | $780.00 | $990.00 |
| 154 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 14 | $170.00 | $170.00 | $149.00 | $215.00 | $140.00 | $176.00 |
| 155 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 1 | $220.00 | $230.00 | $225.00 | $305.00 | $210.00 | $265.00 |
| 156 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 6,695 | $2.25 | $2.00 | $3.00 | $3.15 | $2.80 | $3.55 |
| 157 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 485 | $3.00 | $2.25 | $3.52 | $3.70 | $3.50 | $4.20 |
| 158 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 25 | $2.00 | $1.50 | $2.82 | $2.85 | $3.00 | $3.35 |
| 159 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 1 | $14,000 | $13,000 | $13,750 | $16,250 | $15,000 | $16,275 |
| 160 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 3 | $14,000 | $13,000 | $14,980 | $16,800 | $16,000 | $17,730 |
| 161 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $15,000 | $16,000 | $17,500 | $19,500 | $18,000 | $20,665 |
| 162 | Pedestrian pole assembly (687-7001) | EACH | 3 | $2,750.00 | $5,300.00 | $2,850.00 | $3,750.00 | $3,500.00 | $3,370.00 |
| 163 | Pedestrian detect push button (APS) (688-7001) | EACH | 4 | $1,000.00 | $1,000.00 | $1,774.00 | $1,175.00 | $2,000.00 | $2,100.00 |
| 164 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $9,000.00 | $8,400.00 | $9,537.00 | $11,750 | $10,000 | $11,300 |
| 165 | VDS prosr sys (6017-7001) | EACH | 2 | $12,000 | $12,000 | $13,330 | $15,100 | $15,000 | $15,777 |
| 166 | VIVDS cam assy var LNS (6017-7003) | EACH | 8 | $3,500.00 | $5,900.00 | $6,353.00 | $7,800.00 | $6,000.00 | $7,520.00 |
| 167 | VDS CNTRL software (6017-7009) | EACH | 1 | $400.00 | $840.00 | $1,300.00 | $1,350.00 | $1,200.00 | $1,520.00 |
| 168 | VDS atspm (6017-7010) | EACH | 1 | $4,050.00 | $250.00 | $13,960 | $15,500 | $15,000 | $16,515 |
| 169 | VDS cabling (6017-7012) | LF | 4,955 | $2.00 | $3.25 | $6.60 | $1.20 | $7.00 | $7.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 7, 2025. Compiled by Mirage Metrics.