TxDOT contract A00193148 bid tabulation
Hazard Elimination & Safety, RM 3237 (0.305 MI W of Lone Man Mountain Rd to 0.379 MI E of Lone Man Mountain Rd). Let by Texas DOT on November 6, 2025, Hays, Austin District. 7 bids received; low bid $1,989,311 by Dean Word Company, LTD., -37% against the engineer's estimate of $3,180,793.
- Owner
- Texas DOT
- Letting
- 06 NOV 2025
- Pay items
- 74
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dean Word Company, LTD. | $1,989,311 | Low | -37% |
| 2 | Texas Materials Group, Inc. | $2,153,984 | +8.0% | -32% |
| 3 | Aaron Concrete Contractors, LLC | $2,365,247 | +19% | -26% |
| 4 | Hunter Industries, LTD. | $2,376,778 | +19% | -25% |
| 5 | Joe Bland Construction LLC | $2,479,932 | +25% | -22% |
| 6 | Acme Bridge Company, Inc. | $2,582,225 | +30% | -19% |
| 7 | Lone Star Sitework, LLC | $2,701,682 | +36% | -15% |
Engineer's estimate: $3,180,793.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dean Word Company, LTD. | 2. Texas Materials Group, Inc. | 3. Aaron Concrete Contractors, LLC | 4. Hunter Industries, LTD. | 5. Joe Bland Construction LLC | 6. Acme Bridge Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 33 | $2,000.00 | $1,720.25 | $1,700.00 | $525.00 | $1,573.82 | $1,000.00 | $4,050.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 7,692 | $24.00 | $13.74 | $24.00 | $13.00 | $32.95 | $15.00 | $21.90 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 2,234 | $88.00 | $33.75 | $15.50 | $6.00 | $19.28 | $8.00 | $11.40 |
| 4 | Furn & place topsoil (4") (160-7002) | SY | 15,334 | $3.20 | $1.50 | $2.40 | $1.80 | $1.34 | $1.50 | $2.85 |
| 5 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 15,334 | $0.38 | $0.25 | $0.15 | $0.20 | $0.16 | $0.25 | $0.16 |
| 6 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 15,334 | $0.35 | $0.12 | $0.10 | $0.10 | $0.11 | $0.25 | $0.10 |
| 7 | Vegetative watering (168-7001) | TGL | 616 | $86.00 | $0.01 | $20.00 | $37.00 | $54.61 | $45.00 | $65.60 |
| 8 | Soil ret BLKT(SL_mod_clay_short) (169-7001) | SY | 15,334 | $2.00 | $0.55 | $0.51 | $0.60 | $0.54 | $2.00 | $0.53 |
| 9 | Wildflower seeding (180-7001) | ACRE | 3.17 | $3,580.00 | $1,548.00 | $1,278.00 | $1,500.00 | $1,358.57 | $2,450.00 | $1,320.00 |
| 10 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 3,916 | $90.00 | $57.50 | $61.65 | $69.00 | $60.76 | $96.00 | $80.00 |
| 11 | Lime (com or QK)(slurry) (260-7005) | TON | 81 | $350.00 | $373.00 | $309.00 | $365.00 | $345.40 | $375.00 | $225.00 |
| 12 | Lime TRT (existing material)(8") (260-7007) | SY | 3,000 | $10.00 | $2.00 | $12.00 | $5.50 | $6.85 | $11.00 | $4.15 |
| 13 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 2,697 | $4.00 | $4.25 | $4.65 | $5.50 | $5.05 | $4.00 | $4.90 |
| 14 | D-GR HMA type-B PG64-22 (exempt) (341-7003) | TON | 3,075 | $115.00 | $84.50 | $78.00 | $102.00 | $90.01 | $98.00 | $90.40 |
| 15 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 500 | $120.00 | $93.00 | $106.20 | $135.00 | $109.42 | $125.00 | $119.25 |
| 16 | D-GR HMA type D PG 76-22 (exempt) (341-7065) | TON | 1,125 | $130.00 | $114.75 | $93.33 | $118.00 | $109.42 | $146.00 | $105.10 |
| 17 | PFC-C PG76-22 sac-A (342-7001) | TON | 1,397 | $225.00 | $170.50 | $174.00 | $218.00 | $164.60 | $178.00 | $192.78 |
| 18 | Flexible pavement structure repair(6") (351-7005) | SY | 2,728 | $54.00 | $39.75 | $42.00 | $52.00 | $41.56 | $55.00 | $48.63 |
| 19 | Cut & restore asphalt paving (400-7008) | SY | 32 | $390.00 | $614.25 | $400.00 | $142.00 | $140.00 | $180.00 | $521.00 |
| 20 | Trench excavation protection (402-7001) | LF | 65 | $46.00 | $60.25 | $40.00 | $27.00 | $32.00 | $5.00 | $9.10 |
| 21 | Riprap (concrete)(CL B) (432-7005) | CY | 39 | $700.00 | $775.25 | $775.00 | $760.00 | $650.00 | $1,475.00 | $920.00 |
| 22 | Rirrap (stone common)(dry)(15 in) (432-7032) | CY | 48 | $185.00 | $255.50 | $270.00 | $205.00 | $246.07 | $305.00 | $194.00 |
| 23 | RC pipe (CL III)(24 in) (464-7005) | LF | 742 | $229.00 | $88.00 | $135.00 | $160.00 | $123.51 | $143.00 | $98.30 |
| 24 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 8 | $3,400.00 | $1,877.00 | $2,500.00 | $1,150.00 | $1,678.84 | $2,275.00 | $2,780.00 |
| 25 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 12 | $3,500.00 | $2,087.00 | $2,600.00 | $1,540.00 | $2,493.73 | $3,000.00 | $2,910.00 |
| 26 | Mobilization (500-7001) | LS | 1 | $289,163 | $151,000 | $187,000 | $175,000 | $234,672 | $85,000 | $226,000 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $6,600.00 | $2,250.00 | $5,000.00 | $1,850.00 | $8,310.08 | $8,250.00 | $12,000 |
| 28 | Portable changeable message sign (503-7001) | DAY | 222 | $250.00 | $125.75 | $10.00 | $100.00 | $50.62 | $75.00 | $137.00 |
| 29 | TMA (stationary) (505-7001) | DAY | 211 | $200.00 | $0.01 | $25.00 | $175.00 | $101.24 | $210.00 | $155.00 |
| 30 | TMA (mobile operation) (505-7003) | DAY | 78 | $160.00 | $0.01 | $25.00 | $265.00 | $506.20 | $105.00 | $334.00 |
| 31 | Rock filter dams (install) (type 2) (506-7002) | LF | 349 | $45.00 | $47.25 | $39.00 | $45.00 | $41.37 | $60.00 | $40.30 |
| 32 | Rock filter dams (remove) (506-7011) | LF | 349 | $20.00 | $15.75 | $13.00 | $15.00 | $13.83 | $25.00 | $13.50 |
| 33 | Construction exits (install) (type 1) (506-7020) | SY | 336 | $22.00 | $38.50 | $31.80 | $37.00 | $33.81 | $40.00 | $32.90 |
| 34 | Construction exits (remove) (506-7024) | SY | 336 | $11.80 | $14.00 | $11.60 | $14.00 | $12.38 | $25.00 | $12.10 |
| 35 | Temporary sediment control fence (install) (506-7039) | LF | 6,530 | $4.00 | $4.25 | $3.60 | $4.00 | $3.82 | $5.00 | $3.70 |
| 36 | Temporary sediment control fence (remove) (506-7041) | LF | 6,530 | $1.00 | $1.25 | $0.96 | $1.10 | $1.02 | $1.00 | $0.99 |
| 37 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 100 | $6.50 | $10.25 | $8.45 | $10.00 | $8.98 | $8.00 | $8.80 |
| 38 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $1.00 | $1.25 | $1.00 | $1.20 | $1.07 | $2.00 | $1.05 |
| 39 | Constructing detours (type 1) (508-7003) | SY | 492 | $85.00 | $0.01 | $87.00 | $116.00 | $70.14 | $95.00 | $119.00 |
| 40 | One-way traffic control (flagger cont) (510-7001) | HR | 64 | $200.00 | $240.50 | $68.00 | $250.00 | $93.23 | $200.00 | $240.00 |
| 41 | Driveways (ACP) (530-7010) | SY | 826 | $84.00 | $45.00 | $83.73 | $138.00 | $70.80 | $90.00 | $76.71 |
| 42 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 3 | $315.00 | $363.50 | $295.00 | $400.00 | $370.34 | $500.00 | $311.00 |
| 43 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 1 | $350.00 | $393.75 | $395.00 | $712.00 | $664.44 | $500.00 | $337.00 |
| 44 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 1 | $725.00 | $787.50 | $750.00 | $850.00 | $789.70 | $725.00 | $673.00 |
| 45 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 11 | $815.00 | $1,029.75 | $850.00 | $910.00 | $846.34 | $1,000.00 | $880.00 |
| 46 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 5 | $930.00 | $1,211.50 | $1,050.00 | $1,260.00 | $1,172.02 | $1,100.00 | $1,040.00 |
| 47 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 2 | $470.00 | $590.50 | $1,500.00 | $712.00 | $664.44 | $575.00 | $505.00 |
| 48 | Remove SM RD SN sup&AM (644-7073) | EACH | 9 | $120.00 | $121.25 | $200.00 | $117.00 | $103.48 | $110.00 | $104.00 |
| 49 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 13,437 | $1.00 | $0.50 | $0.32 | $0.50 | $0.37 | $0.50 | $0.67 |
| 50 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 13,433 | $0.60 | $0.50 | $0.32 | $0.50 | $0.37 | $0.50 | $0.67 |
| 51 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 672 | $6.00 | $4.30 | $3.50 | $5.00 | $4.06 | $7.00 | $3.95 |
| 52 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 672 | $1.60 | $2.50 | $1.35 | $0.90 | $1.63 | $1.25 | $2.00 |
| 53 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 672 | $1.60 | $2.50 | $1.35 | $0.90 | $1.63 | $1.25 | $2.00 |
| 54 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 2,450 | $2.00 | $1.00 | $0.88 | $1.10 | $1.02 | $1.25 | $1.45 |
| 55 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 32 | $20.00 | $19.50 | $16.00 | $3.75 | $18.57 | $15.00 | $12.90 |
| 56 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 12 | $250.00 | $181.75 | $150.00 | $240.00 | $174.08 | $250.00 | $152.00 |
| 57 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 8 | $320.00 | $206.00 | $170.00 | $335.00 | $197.29 | $275.00 | $191.00 |
| 58 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 7,274 | $0.50 | $0.30 | $0.28 | $0.25 | $0.32 | $0.50 | $0.34 |
| 59 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 2,450 | $1.00 | $0.75 | $0.60 | $0.30 | $0.70 | $0.75 | $0.90 |
| 60 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 32 | $10.00 | $4.75 | $4.00 | $6.25 | $4.64 | $4.50 | $3.35 |
| 61 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 12 | $150.00 | $84.75 | $70.00 | $168.00 | $81.24 | $85.00 | $61.81 |
| 62 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 8 | $112.00 | $84.75 | $70.00 | $162.00 | $81.24 | $85.00 | $78.70 |
| 63 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 390 | $0.50 | $0.50 | $0.31 | $0.25 | $0.36 | $0.50 | $0.39 |
| 64 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 8,671 | $0.50 | $0.30 | $0.28 | $0.25 | $0.32 | $0.50 | $0.34 |
| 65 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 7,274 | $2.00 | $0.90 | $0.80 | $0.75 | $0.93 | $1.25 | $1.35 |
| 66 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 8,671 | $2.50 | $0.90 | $0.80 | $0.75 | $0.93 | $1.25 | $1.35 |
| 67 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 390 | $3.00 | $2.50 | $2.00 | $0.75 | $2.32 | $1.25 | $1.50 |
| 68 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 5,810 | $8.50 | $3.80 | $3.25 | $7.20 | $3.77 | $6.50 | $4.40 |
| 69 | Reflectorized pavement marker type I-C (672-7002) | EACH | 122 | $1.25 | $4.25 | $3.70 | $6.25 | $4.29 | $6.50 | $5.60 |
| 70 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 377 | $6.50 | $4.25 | $3.70 | $6.25 | $4.29 | $6.50 | $4.50 |
| 71 | Eliminating existing PM & markers (4") (677-7001) | LF | 26,870 | $0.80 | $0.65 | $0.60 | $0.30 | $0.70 | $0.50 | $0.34 |
| 72 | Underseal course (3006-7001) | GAL | 4,140 | $4.00 | $5.50 | $3.80 | $4.90 | $4.40 | $4.00 | $4.36 |
| 73 | Bonding course (3007-7001) | GAL | 2,746 | $4.00 | $4.00 | $3.40 | $4.30 | $3.85 | $4.00 | $3.81 |
| 74 | Subsurface util locate (outside rdbed) (7019-7001) | EACH | 4 | $1,400.00 | $3,376.00 | $1,000.00 | $730.00 | $5,000.00 | $2,000.00 | $2,590.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 6, 2025. Compiled by Mirage Metrics.