| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $1,828,629 | Low | -27% |
| 2 | Larry Young Paving, Inc. | $2,041,635 | +12% | -18% |
| 3 | Texas Steel Industrial Placing, LLC | $2,084,195 | +14% | -16% |
| 4 | STX Civil | $2,330,751 | +27% | -6.0% |
| 5 | Icos Management, LLC | $2,462,384 | +35% | -1.0% |
| 6 | Ti-Zack Concrete, LLC | $2,462,642 | +35% | -1.0% |
| 7 | Skyline Bridge LLC | $2,547,377 | +39% | +2.0% |
| 8 | Tight Line Construction, LLC | $2,605,625 | +42% | +5.0% |
| 9 | Tucan Contracting, LLC | $2,620,510 | +43% | +5.0% |
| 10 | Brazos Paving, Inc. | $2,927,236 | +60% | +17% |
Engineer's estimate: $2,492,627.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Larry Young Paving, Inc. | 3. Texas Steel Industrial Placing, LLC | 4. STX Civil | 5. Icos Management, LLC | 6. Ti-Zack Concrete, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 3 | $350.00 | $500.00 | $1,300.00 | $1,000.00 | $1,192.00 | $1,070.00 | $1,045.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 3 | $900.00 | $1,200.00 | $1,500.00 | $1,200.00 | $2,216.00 | $2,140.00 | $1,942.60 |
| 3 | Tree protection (install) (100-7013) | EACH | 68 | $250.00 | $100.00 | $330.00 | $260.00 | $314.00 | $278.00 | $1.10 |
| 4 | Tree protection (remove) (100-7015) | EACH | 68 | $160.00 | $1.00 | $130.00 | $100.00 | $69.00 | $107.00 | $1.10 |
| 5 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 5,384.80 | $13.00 | $10.00 | $13.00 | $10.00 | $11.00 | $13.00 | $22.05 |
| 6 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 997.30 | $15.00 | $30.00 | $9.50 | $15.00 | $14.00 | $16.00 | $22.90 |
| 7 | Excavation (roadway) (110-7001) | CY | 2,510 | $45.00 | $30.00 | $31.00 | $15.00 | $26.00 | $13.00 | $36.39 |
| 8 | Embankment (final)(OC)(type A) (132-7001) | CY | 186 | $30.00 | $40.00 | $37.00 | $40.00 | $41.00 | $64.00 | $115.73 |
| 9 | Embankment (vehicle)(OC)(type C) (132-7017) | CY | 176.30 | $55.00 | $40.00 | $39.00 | $40.00 | $61.00 | $64.00 | $121.13 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 6,976 | $2.50 | $5.00 | $3.50 | $5.55 | $8.50 | $6.00 | $8.12 |
| 11 | Block sodding (162-7002) | SY | 6,976 | $6.00 | $8.00 | $5.75 | $4.65 | $7.50 | $5.50 | $5.50 |
| 12 | Vegetative watering (168-7001) | TGL | 69.80 | $45.00 | $50.00 | $37.00 | $35.00 | $46.00 | $35.00 | $1.10 |
| 13 | D-GR HMA type D PG64-22 (level-UP) (341-7046) | TON | 42 | $150.00 | $200.00 | $280.00 | $1,200.00 | $301.00 | $235.00 | $247.50 |
| 14 | Tack coat (344-7077) | GAL | 36 | $4.50 | $6.00 | $17.00 | $16.00 | $49.00 | $160.00 | $11.00 |
| 15 | Plan & text concrete pavement(0" to 1.5") (354-7026) | SY | 170.80 | $7.50 | $10.00 | $8.75 | $40.00 | $14.00 | $21.00 | $13.20 |
| 16 | Class A concrete (collar) (420-7008) | EACH | 2 | $2,000.00 | $1,000.00 | $1,500.00 | $1,500.00 | $3,002.00 | $1,712.00 | $1,375.00 |
| 17 | Riprap (concrete)(4 in) (432-7001) | CY | 7 | $1,000.00 | $600.00 | $720.00 | $750.00 | $637.00 | $856.00 | $498.09 |
| 18 | Riprap (stone common)(dry)(8 in) (432-7030) | CY | 40 | $200.00 | $200.00 | $240.00 | $220.00 | $285.00 | $214.00 | $220.00 |
| 19 | Rail (handrail)(type B) (450-7059) | LF | 163 | $175.00 | $150.00 | $100.00 | $117.95 | $157.00 | $214.00 | $154.00 |
| 20 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 76 | $900.00 | $500.00 | $420.00 | $600.00 | $912.00 | $535.00 | $577.50 |
| 21 | Concrete box culvert (5 FT X 2 FT)(extend) (462-7061) | LF | 28 | $1,050.00 | $600.00 | $520.00 | $800.00 | $1,365.00 | $642.00 | $726.00 |
| 22 | RC pipe (CL III)(18 in) (464-7003) | LF | 20 | $85.00 | $100.00 | $66.00 | $120.00 | $90.00 | $107.00 | $184.80 |
| 23 | RC pipe (CL III)(24 in) (464-7005) | LF | 73 | $135.00 | $120.00 | $81.00 | $120.00 | $108.00 | $128.00 | $198.00 |
| 24 | RC pipe (CL III)(36 in) (464-7009) | LF | 16 | $120.00 | $250.00 | $150.00 | $250.00 | $194.00 | $321.00 | $357.50 |
| 25 | Inlet (complete)(type aad)(hou) (465-7315) | EACH | 2 | $8,250.00 | $5,000.00 | $6,400.00 | $9,000.00 | $8,321.00 | $10,700 | $6,435.00 |
| 26 | Set (type I)(S= 3 FT)(HW= 3 FT)(6:1)(P) (467-7043) | EACH | 8 | $10,000 | $2,500.00 | $4,700.00 | $11,000 | $9,862.00 | $9,630.00 | $9,845.00 |
| 27 | Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(P) (467-7098) | EACH | 2 | $14,000 | $5,000.00 | $5,800.00 | $20,000 | $12,065 | $12,840 | $10,868 |
| 28 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 5 | $2,500.00 | $2,000.00 | $2,700.00 | $2,500.00 | $2,711.00 | $1,926.00 | $2,392.50 |
| 29 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 1 | $4,050.00 | $5,000.00 | $4,900.00 | $5,000.00 | $6,065.00 | $5,350.00 | $4,345.00 |
| 30 | Removing structure (inlet) (496-7002) | EACH | 2 | $1,000.00 | $1,000.00 | $1,300.00 | $1,250.00 | $1,314.00 | $2,140.00 | $1,650.00 |
| 31 | Removing structure (set) (496-7004) | EACH | 12 | $500.00 | $500.00 | $650.00 | $600.00 | $650.00 | $856.00 | $275.00 |
| 32 | Removing structure (pipe) (496-7007) | LF | 4 | $50.00 | $20.00 | $58.00 | $150.00 | $22.00 | $21.00 | $27.50 |
| 33 | Mobilization (500-7001) | LS | 1 | $200,000 | $100,000 | $179,000 | $208,434 | $182,000 | $78,000 | $246,816 |
| 34 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $7,500.00 | $5,000.00 | $3,800.00 | $2,150.00 | $3,500.00 | $1.00 | $3,850.00 |
| 35 | Portable changeable message sign (503-7002) | EACH | 4 | $8,000.00 | $1,000.00 | $1,100.00 | $24,000 | $7,000.00 | $10,700 | $1.10 |
| 36 | TMA (stationary) (505-7001) | DAY | 120 | $300.00 | $300.00 | $250.00 | $250.00 | $190.00 | $214.00 | $1.10 |
| 37 | TMA (mobile operation) (505-7002) | HR | 4 | $500.00 | $100.00 | $64.00 | $1.00 | $57.00 | $535.00 | $1,045.00 |
| 38 | Rock filter dams (install) (type 2) (506-7002) | LF | 98 | $50.00 | $20.00 | $57.00 | $40.00 | $75.00 | $45.00 | $1.10 |
| 39 | Rock filter dams (remove) (506-7011) | LF | 98 | $15.00 | $10.00 | $31.00 | $10.00 | $25.00 | $25.00 | $1.10 |
| 40 | Temporary sediment control fence (install) (506-7039) | LF | 2,300 | $4.80 | $5.00 | $5.00 | $4.00 | $6.00 | $4.00 | $1.10 |
| 41 | Temporary sediment control fence (remove) (506-7041) | LF | 2,300 | $4.80 | $1.00 | $1.25 | $1.00 | $1.00 | $1.00 | $0.11 |
| 42 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 1,088 | $10.00 | $5.00 | $11.00 | $8.00 | $6.00 | $8.50 | $0.11 |
| 43 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,088 | $2.00 | $1.00 | $2.00 | $1.50 | $1.00 | $2.00 | $0.11 |
| 44 | Colored textured concrete (6") (527-7003) | SY | 10.50 | $300.00 | $120.00 | $290.00 | $250.00 | $206.00 | $642.00 | $229.68 |
| 45 | Concrete curb (type I) (529-7001) | LF | 111 | $20.00 | $40.00 | $5.50 | $50.00 | $68.00 | $54.00 | $53.87 |
| 46 | Concrete curb (type II) (529-7002) | LF | 52.50 | $30.00 | $40.00 | $6.00 | $65.00 | $71.00 | $75.00 | $45.58 |
| 47 | Concrete curb & gutter (type II) (529-7009) | LF | 4,092.60 | $40.00 | $20.00 | $38.00 | $40.00 | $41.00 | $56.00 | $53.87 |
| 48 | Concrete curb (type C1) (529-7016) | LF | 573.90 | $150.00 | $150.00 | $140.00 | $140.00 | $278.00 | $161.00 | $88.88 |
| 49 | Concrete curb (type F1) (529-7017) | LF | 182 | $250.00 | $150.00 | $250.00 | $200.00 | $417.00 | $214.00 | $111.10 |
| 50 | Driveways (concrete) (530-7006) | SY | 270 | $130.00 | $100.00 | $170.00 | $100.00 | $119.00 | $192.00 | $119.33 |
| 51 | Driveways (concrete) (type 1) (530-7008) | SY | 1,452 | $155.00 | $100.00 | $110.00 | $100.00 | $119.00 | $171.00 | $138.68 |
| 52 | Driveways (concrete) (type 2) (530-7009) | SY | 1,558 | $160.00 | $100.00 | $110.00 | $100.00 | $119.00 | $171.00 | $138.68 |
| 53 | Concrete sidewalks (6") (531-7003) | SY | 4,727 | $95.00 | $75.00 | $86.00 | $75.00 | $94.00 | $96.00 | $126.29 |
| 54 | Curb ramps (type 1) (531-7015) | SY | 31 | $350.00 | $300.00 | $240.00 | $125.00 | $94.00 | $428.00 | $141.60 |
| 55 | Curb ramps (type 3) (531-7017) | SY | 24 | $200.00 | $300.00 | $230.00 | $125.00 | $94.00 | $481.00 | $142.19 |
| 56 | Curb ramps (type 5) (531-7018) | SY | 102 | $165.00 | $300.00 | $220.00 | $125.00 | $94.00 | $363.00 | $142.19 |
| 57 | Curb ramps (type 7) (531-7020) | SY | 176 | $168.00 | $300.00 | $210.00 | $125.00 | $94.00 | $363.00 | $142.19 |
| 58 | Curb ramps (type 10) (531-7021) | SY | 308 | $170.00 | $300.00 | $200.00 | $125.00 | $94.00 | $406.00 | $142.19 |
| 59 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 12 | $275.00 | $300.00 | $340.00 | $250.00 | $690.00 | $321.00 | $275.00 |
| 60 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 12 | $720.00 | $600.00 | $990.00 | $550.00 | $815.00 | $620.00 | $495.00 |
| 61 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 66 | $750.00 | $600.00 | $650.00 | $650.00 | $564.00 | $727.00 | $495.00 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $1,000.00 | $1,000.00 | $890.00 | $775.00 | $701.00 | $856.00 | $495.00 |
| 63 | Remove SM RD SN sup&AM (644-7073) | EACH | 45 | $550.00 | $100.00 | $88.00 | $75.00 | $94.00 | $86.00 | $220.00 |
| 64 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 296 | $16.00 | $30.00 | $17.00 | $28.50 | $25.00 | $32.00 | $38.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.