TxDOT contract A00210172 bid tabulation
Bridge Maintenance, SH 214 (0.9 miles south of US 60 to On SH 214). Let by Texas DOT on September 4, 2025, Parmer, Lubbock District. 10 bids received; low bid $4,197,908 by Pathfield Investments LLC, -3.1% against the engineer's estimate of $4,332,214.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 43
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Pathfield Investments LLC | $4,197,908 | Low | -3.0% |
| 2 | Scott Tucker Construction Company, LLC | $4,477,679 | +7.0% | +3.0% |
| 3 | Ti-Zack Concrete, LLC | $4,532,210 | +8.0% | +5.0% |
| 4 | Silver Creek Construction, Inc. | $4,696,702 | +12% | +8.0% |
| 5 | Gibson & Associates, Inc. | $4,909,904 | +17% | +13% |
| 6 | Ragle Construction, Inc. | $4,937,629 | +18% | +14% |
| 7 | Gilvin-Terrill, LTD. | $4,950,089 | +18% | +14% |
| 8 | Structural Integrity Group LLC | $5,184,757 | +24% | +20% |
| 9 | Built Right Construction of Oklahoma, LLC | $6,992,930 | +67% | +61% |
| 10 | Icos Management, LLC | $7,351,760 | +75% | +70% |
Engineer's estimate: $4,332,214.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Pathfield Investments LLC | 2. Scott Tucker Construction Company, LLC | 3. Ti-Zack Concrete, LLC | 4. Silver Creek Construction, Inc. | 5. Gibson & Associates, Inc. | 6. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 36 | $48.00 | $100.00 | $66.00 | $61.60 | $30.00 | $140.00 | $75.00 |
| 2 | Removing concrete (curb) (104-7016) | LF | 3,540 | $19.00 | $10.00 | $4.00 | $5.60 | $6.00 | $9.00 | $6.00 |
| 3 | Removing concrete (flume) (104-7041) | SY | 40 | $48.00 | $90.00 | $88.00 | $84.00 | $30.00 | $140.00 | $65.00 |
| 4 | Planing asphalt concrete pavement(3") (354-7052) | SY | 6,640 | $7.00 | $5.70 | $6.00 | $12.32 | $8.00 | $4.61 | $3.50 |
| 5 | Cem stabil BKFL (400-7010) | CY | 16 | $285.00 | $340.00 | $252.00 | $728.00 | $400.00 | $500.00 | $175.00 |
| 6 | Class C concrete (crashwall) (420-7050) | CY | 77.60 | $950.00 | $1,200.00 | $1,019.00 | $728.00 | $1,175.00 | $1,540.00 | $1,400.00 |
| 7 | Class C concrete (rail foundation) (420-7052) | CY | 514 | $700.00 | $550.00 | $490.00 | $616.00 | $500.00 | $649.00 | $520.00 |
| 8 | Class C concrete (vehicle defl wall) (420-7062) | CY | 63.60 | $1,710.00 | $500.00 | $1,427.00 | $1,344.00 | $1,175.00 | $1,540.00 | $1,400.00 |
| 9 | Epoxy waterproof finish (type X) (427-7005) | SF | 10,360 | $10.00 | $18.00 | $7.00 | $19.04 | $16.00 | $10.45 | $7.50 |
| 10 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 1,500 | $143.00 | $180.00 | $60.00 | $140.00 | $100.00 | $20.00 | $30.00 |
| 11 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 500 | $166.00 | $170.00 | $160.00 | $240.80 | $275.00 | $50.00 | $80.00 |
| 12 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 500 | $190.00 | $225.00 | $181.00 | $164.64 | $185.00 | $290.00 | $150.00 |
| 13 | Riprap (concrete)(5 in) (432-7002) | CY | 30 | $950.00 | $540.00 | $1,092.00 | $582.40 | $450.00 | $990.00 | $590.00 |
| 14 | Riprap (concrete)(flume) (432-7012) | CY | 10 | $760.00 | $760.00 | $1,943.00 | $728.00 | $450.00 | $1,067.00 | $755.00 |
| 15 | Polyester polymer concrete overlay (439-7025) | CY | 554 | $2,850.00 | $2,300.00 | $3,456.00 | $2,912.00 | $3,437.00 | $3,200.00 | $4,300.00 |
| 16 | Rail (type SSTR) (450-7024) | LF | 2,308 | $110.00 | $80.00 | $95.00 | $140.00 | $92.00 | $114.40 | $65.00 |
| 17 | Retrofit rail (type SSTR) (451-7024) | LF | 2,446 | $190.00 | $260.00 | $185.00 | $173.60 | $148.00 | $187.00 | $105.00 |
| 18 | Armor joint (sealed) (454-7003) | LF | 882 | $209.00 | $165.00 | $218.00 | $156.80 | $375.00 | $625.00 | $245.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $394,000 | $390,000 | $447,771 | $450,000 | $465,000 | $562,000 | $490,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $5,700.00 | $11,000 | $5,973.00 | $1,680.00 | $8,500.00 | $10,000 | $49,000 |
| 21 | Portable changeable message sign (503-7001) | DAY | 540 | $86.00 | $120.00 | $87.00 | $1.12 | $35.00 | $50.00 | $65.00 |
| 22 | TMA (stationary) (505-7001) | DAY | 306 | $143.00 | $210.00 | $289.00 | $168.00 | $150.00 | $250.00 | $10.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 10 | $475.00 | $250.00 | $494.00 | $392.00 | $450.00 | $250.00 | $570.00 |
| 24 | Sandbags for erosion control (506-7035) | EACH | 350 | $12.00 | $17.00 | $9.00 | $11.20 | $12.00 | $19.80 | $12.00 |
| 25 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 100 | $7.00 | $8.00 | $4.00 | $16.80 | $19.00 | $20.90 | $7.00 |
| 26 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $3.00 | $3.00 | $1.00 | $5.60 | $5.00 | $5.50 | $1.00 |
| 27 | Metal W-beam guard fence (steel post) (540-7002) | LF | 100 | $33.00 | $40.00 | $41.00 | $246.40 | $45.00 | $38.50 | $45.00 |
| 28 | Metal thrie-beam guard fence (steel post) (540-7020) | EACH | 4 | $2,185.00 | $600.00 | $3,509.00 | $9,520.00 | $2,600.00 | $2,420.00 | $3,200.00 |
| 29 | Remove metal beam guard fence (542-7001) | LF | 3,540 | $2.60 | $5.00 | $2.00 | $7.84 | $20.00 | $3.30 | $5.00 |
| 30 | Remove terminal anchor section (542-7002) | EACH | 4 | $285.00 | $190.00 | $365.00 | $2,240.00 | $300.00 | $220.00 | $350.00 |
| 31 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $2,850.00 | $3,500.00 | $3,205.00 | $8,960.00 | $3,300.00 | $3,602.50 | $3,750.00 |
| 32 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014) | EACH | 50 | $29.00 | $10.00 | $38.00 | $28.00 | $165.00 | $49.50 | $35.00 |
| 33 | Work zone pavement marking removing (W)6"(BKN W/marker) (662-7080) | LF | 1,100 | $3.00 | $1.00 | $5.00 | $7.28 | $6.50 | $4.13 | $3.75 |
| 34 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 2,490 | $1.00 | $1.00 | $2.00 | $3.36 | $3.00 | $1.10 | $1.00 |
| 35 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 2,490 | $1.00 | $1.00 | $2.00 | $3.36 | $3.00 | $1.10 | $1.00 |
| 36 | Prefabricated PM type C (W)(6")(solid) (668-7080) | LF | 2,490 | $3.00 | $7.00 | $5.00 | $5.60 | $5.00 | $4.73 | $4.30 |
| 37 | Prefabricated PM type C (Y)(6")(solid) (668-7123) | LF | 2,490 | $3.00 | $7.00 | $5.00 | $5.60 | $5.00 | $4.73 | $4.30 |
| 38 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 80 | $5.00 | $5.00 | $11.00 | $22.40 | $20.00 | $6.60 | $6.00 |
| 39 | Pavement surface preparation for marking (6") (678-7002) | LF | 4,980 | $1.00 | $1.00 | $1.00 | $2.24 | $2.00 | $0.55 | $0.50 |
| 40 | Full - width mowing (730-7019) | CYC | 1 | $2,850.00 | $6,000.00 | $4,561.00 | $5,600.00 | $5,000.00 | $1,500.00 | $750.00 |
| 41 | Litter removal (734-7002) | CYC | 1 | $1,900.00 | $3,000.00 | $2,976.00 | $2,240.00 | $2,500.00 | $750.00 | $750.00 |
| 42 | Concrete beam repair (CFRP) (788-7002) | EACH | 3 | $6,650.00 | $11,000 | $14,701 | $19,040 | $2,500.00 | $5,000.00 | $5,000.00 |
| 43 | Concrete beam rep(strand splice & CFRP) (788-7003) | EACH | 1 | $14,250 | $20,000 | $37,418 | $24,640 | $10,000 | $9,000.00 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.