Alabama Guardrail, Inc.: ALDOT bid record
Alabama Guardrail, Inc. submitted 24 bids on Alabama DOT contracts in the data, from 27 MAY 2022 to 28 AUG 2026, and was the low bidder on 17 of them (71%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Alabama DOT
- Low bid volume
- $2,380,260
- Latest bid
- 28 AUG 2026
- Data through
- 28 AUG 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 4 | 3 | 75% |
| 2023 | 4 | 2 | 50% |
| 2024 | 4 | 4 | 100% |
| 2025 | 5 | 3 | 60% |
| 2026 | 7 | 5 | 71% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| 0504 | 6 | 6 | 100% |
| 0103 | 4 | 4 | 100% |
| 0506 | 2 | 0 | 0% |
| 0105 | 2 | 2 | 100% |
| 0704 | 2 | 1 | 50% |
| 0104 | 1 | 1 | 100% |
| 07 | 1 | 1 | 100% |
| 0903 | 1 | 1 | 100% |
| 0803 | 1 | 0 | 0% |
| 0706 | 1 | 1 | 100% |
| 0602 | 1 | 0 | 0% |
| 0901 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Guardrail end anchor, type 20 series (MASH) | 630C080 | EACH | 18 | 12 (67%) | $3,625.00 | $3,785.66 |
| Guardrail end anchor, type special | 630C022 | EACH | 11 | 11 (100%) | $3,200.00 | $3,500.00 |
| Steel beam guardrail, class A, type 2 | 630A001 | LF | 10 | 7 (70%) | $28.50 | $29.12 |
| Steel beam guardrail, class B, type 2 | 630A004 | LF | 9 | 4 (44%) | $100.00 | $108.03 |
| Cones (36 inches high) | 740E000 | EACH | 15 | 1 (7%) | $25.00 | $20.47 |
| Removing guardrail | 206D001 | LF | 9 | 1 (11%) | $10.00 | $4.37 |
| Steel beam guardrail for culvert, class A, type 2, case 3 | 630G003 | LF | 5 | 1 (20%) | $265.00 | $250.94 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| C & H Construction Services, LLC | 19 | 5 of 19 |
| H & L Construction, Inc. | 7 | 3 of 7 |
| RMD Holdings, Inc. | 1 | 1 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 AUG 2026 | 20260828014 | 0504 | ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS) ON CR-65 0.410 MI NW OF CAHABA HILL RD; ON CR-44 0.110 MI SOU | 1 of 2 | $60,768 | Low, 3.0% under the second |
| 28 AUG 2026 | 20260828015 | 0504 | ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION) ON CR-54 OVER BRANCH OF DRY CREEK (SITE 1) AND ON CR-54 AT THE | 1 of 2 | $59,958 | Low, 10% under the second |
| 28 AUG 2026 | 20260828017 | 0103 | ROADWAY SAFETY IMPROVMENTS (GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION) ON CR-81 OVER FLAT ROCK CREEK; ON CR-30 OVER UNNAMED CREEK; AND | 1 of 1 | $164,200 | Low |
| 29 MAY 2026 | 20260529014 | 0504 | GUARDRAIL INSTALLATION ON VARIOUS ROUTES AT VARIOUS LOCATIONS AS INDICATED IN THE PLANS | 1 of 1 | $219,060 | Low |
| 27 MAR 2026 | 20260327004 | 0504 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-16 OVER LITTLE MULBERRY CREEK (SITES 1 AND 2) AND OVER SWIFT CREEK (SITES 3 AND 4) | 1 of 2 | $129,306 | Low, 6.0% under the second |
| 27 FEB 2026 | 20260227014 | 0704 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-121 OVER LITTLE CHOCTAWHATCHEE RIVER; ON CR-445 OVER COWPEN CK; ON CR-13 OVER JUDY CK | 2 of 3 | $183,574 | +1.0% |
| 30 JAN 2026 | 20260130019 | 0301 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE EAST CENTRAL REGION (BIRMINGHAM AREA) AS INDIC | 2 of 2 | $436,932 | 0.0% |
| 26 SEP 2025 | 20250926022 | 0103 | GUARDRAIL INSTALLATION ON CR-74 OVER JONES CREEK (SITE 1) AND ON CR-91 OVER LONG ISLAND CREEK (SITE 2) | 1 of 2 | $135,628 | Low, 32% under the second |
| 29 AUG 2025 | 20250829005 | 0901 | CABLE GUIDERAIL INSTALLATION ON I-65 FROM MP 16.940 TO MP 23.000 NORTH OF MOBILE | 3 of 3 | $1,127,632 | +33% |
| 27 JUN 2025 | 20250627004 | 0105 | SAFTEY IMPROVEMENTS (GUARDRAIL INSTALLATION AND END ANCHORS) ON MATT SMITH ROAD OVER GREENS CREEK IN SOUTHSIDE. LENGTH | 1 of 2 | $35,905 | Low, 16% under the second |
| 28 FEB 2025 | 20250228011 | 0602 | SAFETY IMPROVEMENTS (GUARDRAIL INSTALLATION) ON CR-49 AT DOBBS CREEK (SITE 1) AND ON CR-115 AT MOORES CREEK (SITE 2) NORTHEAST OF UNION SPRI | 2 of 3 | $118,895 | +6.0% |
| 31 JAN 2025 | 20250131012 | 0504 | ROADWAY SAFETY IMPROVEMENTS (SCORING AND GUARDRAIL) ON VARIOUS ROUTES AT VARIOUS LOCATIONS AS INDICATED IN THE PLANS | 1 of 1 | $293,617 | Low |
| 27 SEP 2024 | 20240927020 | 0504 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON VARIOUS ROUTES AT VARIOUS SITES IN THE WEST CENTRAL REGION (TUSCALOOSA AREA) AS INDICATE | 1 of 2 | $137,195 | Low, 23% under the second |
| 27 SEP 2024 | 20240927022 | 0704 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-2 OVER CLAYBANK CREEK (SITE 1); ON CR-19 OVER JUDY CREEK (SITE 2); AND ON CR-19 OVER | 1 of 3 | $164,305 | Low, 4.0% under the second |
| 30 AUG 2024 | 20240830018 | 0706 | ROADWAY SAFETY IMPROVMENTS (GUARDRAIL INSTALLATIONS) ON POPLAR SPRINGS ROAD OVER COWIKEE CREEK (SITE 1) AND ON AND ON FIVE MILE ROAD OVER CH | 1 of 3 | $178,324 | Low, 6.0% under the second |
| 26 JUL 2024 | 20240726011 | 0103 | ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL INSTALLATIONS) ON CR-48 OVER STRINGER CREEK IN SECTION (SITE 1) AND ON CR-30 OVER A TRIBUTARY TO NORT | 1 of 2 | $218,490 | Low, 6.0% under the second |
| 03 NOV 2023 | 20231103004 | 0803 | GUARDRAIL AND END ANCHOR INSTALLATIONS ON VETERANS AVENUE FROM STACEY STREET TO FOX RUN (SITE 1) AND ON IVEY STREET TO RANDOLPH STREET IN MO | 3 of 3 | $117,865 | +38% |
| 29 SEP 2023 | 20230929012 | 07 | ROADWAY SAFETY IMPROVEMENTS ON CR-43 OVER LINDSEY CREEK ; ON CR-41 OVER LINDSEY CREEK ; AND ON SHELLEY JACKSON SPUR OVER BIG CREEK | 1 of 3 | $248,125 | Low, 11% under the second |
| 29 SEP 2023 | 20230929013 | 0903 | ROADWAY SAFETY IMPROVEMENTS ON CR-67 OVER CHAVERS CREEK NORTHEAST OF POLLARD | 1 of 3 | $57,590 | Low, 14% under the second |
| 25 AUG 2023 | 20230825008 | 0506 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-2 OVER AN UNNAMED BRANCH WEST OF YORK | 2 of 2 | $118,935 | +27% |
| 26 AUG 2022 | 20220826008 | 0105 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION ON PLEASANT HILL ROAD OVER BLACK CREEK NORTHEAST OF GADSDEN | 1 of 2 | $67,800 | Low, 28% under the second |
| 26 AUG 2022 | 20220826009 | 0103 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-38 OVER DRY CREEK (SITE 1) AND ON CR-38 OVER SKELTON BRANCH (SITE 2) SOUTHEAST OF LAN | 1 of 1 | $95,550 | Low |
| 26 AUG 2022 | 20220826010 | 0104 | GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-1137 (HORTON ROAD) OVER SLAB CREEK (SITE 1) AND ON CR-1131 (OLD ONEONTA ROAD) OVER SL | 1 of 1 | $114,440 | Low |
| 27 MAY 2022 | 20220527007 | 0506 | GUARDRAIL AND END ANCHOR INSTALLATIONS ON CR-27 OVER TOOMSUBA CREEK NORTHWEST OF CUBA | 2 of 2 | $170,405 | +17% |
How this record was read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.