Alabama Guardrail, Inc. submitted 24 bids on Alabama DOT contracts in the data, from 27 MAY 2022 to 28 AUG 2026, and was the low bidder on 17 of them (71%). When it was not low, its total sat a median +17% above the low bid.

Owner
Alabama DOT
Low bid volume
$2,380,260
Latest bid
28 AUG 2026
Data through
28 AUG 2026
24Bids
17Low bids
71Win rate, percent
+17%Median gap to the low bid when not low, 7 bids

By year

YearBidsLow bidsWin rate
20224375%
20234250%
202444100%
20255360%
20267571%
Alabama Guardrail, Inc., ALDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
050466100%
010344100%
0506200%
010522100%
07042150%
010411100%
0711100%
090311100%
0803100%
070611100%
0602100%
0901100%
Alabama Guardrail, Inc., ALDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Guardrail end anchor, type 20 series (MASH)630C080EACH1812 (67%)$3,625.00$3,785.66
Guardrail end anchor, type special630C022EACH1111 (100%)$3,200.00$3,500.00
Steel beam guardrail, class A, type 2630A001LF107 (70%)$28.50$29.12
Steel beam guardrail, class B, type 2630A004LF94 (44%)$100.00$108.03
Cones (36 inches high)740E000EACH151 (7%)$25.00$20.47
Removing guardrail206D001LF91 (11%)$10.00$4.37
Steel beam guardrail for culvert, class A, type 2, case 3630G003LF51 (20%)$265.00$250.94
Alabama Guardrail, Inc., ALDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
C & H Construction Services, LLC195 of 19
H & L Construction, Inc.73 of 7
RMD Holdings, Inc.11 of 1
Alabama Guardrail, Inc., ALDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
28 AUG 2026202608280140504ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS) ON CR-65 0.410 MI NW OF CAHABA HILL RD; ON CR-44 0.110 MI SOU1 of 2$60,768Low, 3.0% under the second
28 AUG 2026202608280150504ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION) ON CR-54 OVER BRANCH OF DRY CREEK (SITE 1) AND ON CR-54 AT THE1 of 2$59,958Low, 10% under the second
28 AUG 2026202608280170103ROADWAY SAFETY IMPROVMENTS (GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION) ON CR-81 OVER FLAT ROCK CREEK; ON CR-30 OVER UNNAMED CREEK; AND1 of 1$164,200Low
29 MAY 2026202605290140504GUARDRAIL INSTALLATION ON VARIOUS ROUTES AT VARIOUS LOCATIONS AS INDICATED IN THE PLANS1 of 1$219,060Low
27 MAR 2026202603270040504GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-16 OVER LITTLE MULBERRY CREEK (SITES 1 AND 2) AND OVER SWIFT CREEK (SITES 3 AND 4)1 of 2$129,306Low, 6.0% under the second
27 FEB 2026202602270140704GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-121 OVER LITTLE CHOCTAWHATCHEE RIVER; ON CR-445 OVER COWPEN CK; ON CR-13 OVER JUDY CK2 of 3$183,574+1.0%
30 JAN 2026202601300190301GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE EAST CENTRAL REGION (BIRMINGHAM AREA) AS INDIC2 of 2$436,9320.0%
26 SEP 2025202509260220103GUARDRAIL INSTALLATION ON CR-74 OVER JONES CREEK (SITE 1) AND ON CR-91 OVER LONG ISLAND CREEK (SITE 2)1 of 2$135,628Low, 32% under the second
29 AUG 2025202508290050901CABLE GUIDERAIL INSTALLATION ON I-65 FROM MP 16.940 TO MP 23.000 NORTH OF MOBILE3 of 3$1,127,632+33%
27 JUN 2025202506270040105SAFTEY IMPROVEMENTS (GUARDRAIL INSTALLATION AND END ANCHORS) ON MATT SMITH ROAD OVER GREENS CREEK IN SOUTHSIDE. LENGTH1 of 2$35,905Low, 16% under the second
28 FEB 2025202502280110602SAFETY IMPROVEMENTS (GUARDRAIL INSTALLATION) ON CR-49 AT DOBBS CREEK (SITE 1) AND ON CR-115 AT MOORES CREEK (SITE 2) NORTHEAST OF UNION SPRI2 of 3$118,895+6.0%
31 JAN 2025202501310120504ROADWAY SAFETY IMPROVEMENTS (SCORING AND GUARDRAIL) ON VARIOUS ROUTES AT VARIOUS LOCATIONS AS INDICATED IN THE PLANS1 of 1$293,617Low
27 SEP 2024202409270200504GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON VARIOUS ROUTES AT VARIOUS SITES IN THE WEST CENTRAL REGION (TUSCALOOSA AREA) AS INDICATE1 of 2$137,195Low, 23% under the second
27 SEP 2024202409270220704GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-2 OVER CLAYBANK CREEK (SITE 1); ON CR-19 OVER JUDY CREEK (SITE 2); AND ON CR-19 OVER 1 of 3$164,305Low, 4.0% under the second
30 AUG 2024202408300180706ROADWAY SAFETY IMPROVMENTS (GUARDRAIL INSTALLATIONS) ON POPLAR SPRINGS ROAD OVER COWIKEE CREEK (SITE 1) AND ON AND ON FIVE MILE ROAD OVER CH1 of 3$178,324Low, 6.0% under the second
26 JUL 2024202407260110103ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL INSTALLATIONS) ON CR-48 OVER STRINGER CREEK IN SECTION (SITE 1) AND ON CR-30 OVER A TRIBUTARY TO NORT1 of 2$218,490Low, 6.0% under the second
03 NOV 2023202311030040803GUARDRAIL AND END ANCHOR INSTALLATIONS ON VETERANS AVENUE FROM STACEY STREET TO FOX RUN (SITE 1) AND ON IVEY STREET TO RANDOLPH STREET IN MO3 of 3$117,865+38%
29 SEP 20232023092901207ROADWAY SAFETY IMPROVEMENTS ON CR-43 OVER LINDSEY CREEK ; ON CR-41 OVER LINDSEY CREEK ; AND ON SHELLEY JACKSON SPUR OVER BIG CREEK1 of 3$248,125Low, 11% under the second
29 SEP 2023202309290130903ROADWAY SAFETY IMPROVEMENTS ON CR-67 OVER CHAVERS CREEK NORTHEAST OF POLLARD1 of 3$57,590Low, 14% under the second
25 AUG 2023202308250080506GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-2 OVER AN UNNAMED BRANCH WEST OF YORK2 of 2$118,935+27%
26 AUG 2022202208260080105GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATION ON PLEASANT HILL ROAD OVER BLACK CREEK NORTHEAST OF GADSDEN1 of 2$67,800Low, 28% under the second
26 AUG 2022202208260090103GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-38 OVER DRY CREEK (SITE 1) AND ON CR-38 OVER SKELTON BRANCH (SITE 2) SOUTHEAST OF LAN1 of 1$95,550Low
26 AUG 2022202208260100104GUARDRAIL AND GUARDRAIL END ANCHOR INSTALLATIONS ON CR-1137 (HORTON ROAD) OVER SLAB CREEK (SITE 1) AND ON CR-1131 (OLD ONEONTA ROAD) OVER SL1 of 1$114,440Low
27 MAY 2022202205270070506GUARDRAIL AND END ANCHOR INSTALLATIONS ON CR-27 OVER TOOMSUBA CREEK NORTHWEST OF CUBA2 of 2$170,405+17%
Alabama Guardrail, Inc.: latest ALDOT bids in the data

How this record was read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy