ALDOT contract 20250725024 bid tabulation
BRIDGE CULVERT REPLACEMENT AND APPROACHES ON WEST MORGAN ROAD OVER BAKERS CREEK SOUTHWEST OF DECATUR. Let by Alabama DOT on July 25, 2025, Morgan, 0202. 6 bids received; low bid $1,243,628 by Rogers Group, Inc..
- Owner
- Alabama DOT
- Letting
- 25 JUL 2025
- Pay items
- 50
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rogers Group, Inc. | $1,243,628 | Low |
| 2 | Grayson Carter & Son Contracting, Inc. | $1,292,278 | +4.0% |
| 3 | Wiregrass Construction Company, Inc. | $1,454,049 | +17% |
| 4 | Carcel & G. Construction, LLC | $1,506,408 | +21% |
| 5 | Glasgow Construction Co., Inc. | $1,533,636 | +23% |
| 6 | Gillespie Construction, LLC | $1,772,168 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group, Inc. | 2. Grayson Carter & Son Contracting, Inc. | 3. Wiregrass Construction Company, Inc. | 4. Carcel & G. Construction, LLC | 5. Glasgow Construction Co., Inc. | 6. Gillespie Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 3 acres) (201A002) | LS | 1 | $24,000 | $24,000 | $24,000 | $23,188 | $24,000 | $24,000 |
| 0020 | Removal of old box culvert, station 6+17.00 (206B000) | LS | 1 | $7,000.00 | $19,110 | $18,535 | $20,096 | $123,500 | $40,000 |
| 0030 | Removing concrete driveway (206C010) | SY | 41 | $27.00 | $27.19 | $79.61 | $39.33 | $20.00 | $55.00 |
| 0040 | Removing pipe (206D000) | LF | 188 | $43.00 | $29.65 | $43.09 | $17.15 | $30.00 | $75.00 |
| 0050 | Mailbox reset, single (209A000) | EACH | 7 | $450.00 | $385.83 | $777.55 | $509.72 | $300.00 | $750.00 |
| 0060 | Unclassified excavation (210A000) | CY | 5,914 | $18.50 | $15.97 | $27.08 | $34.51 | $25.00 | $45.00 |
| 0070 | Borrow excavation (loose truckbed measurement) (210D001) | CY | 4,929 | $25.50 | $16.61 | $26.41 | $31.59 | $33.00 | $50.00 |
| 0080 | Borrow excavation (underwater embankment) (210F001) | TON | 1,244 | $28.50 | $34.75 | $47.89 | $58.40 | $50.00 | $75.00 |
| 0090 | Structure excavation (214A000) | CY | 529 | $38.00 | $89.25 | $86.57 | $42.21 | $35.00 | $120.00 |
| 0100 | Foundation backfill, commercial (214B001) | CY | 158 | $54.50 | $78.75 | $76.38 | $67.30 | $42.00 | $100.00 |
| 0110 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 5,600 | $10.50 | $14.67 | $14.13 | $18.25 | $7.50 | $20.00 |
| 0120 | Crushed aggregate, section 825, type B, for miscellaneous use (305B078) | TON | 200 | $41.00 | $40.97 | $55.06 | $42.58 | $40.76 | $50.00 |
| 0130 | Bituminous treatment A (401A000) | SY | 4,600 | $0.90 | $1.45 | $1.10 | $1.10 | $3.50 | $1.10 |
| 0140 | Tack coat (405A000) | GAL | 1,320 | $3.00 | $4.47 | $3.80 | $3.86 | $10.00 | $3.85 |
| 0150 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range A/B (424A340) | TON | 308 | $95.00 | $126.49 | $123.67 | $119.58 | $225.00 | $119.35 |
| 0160 | Superpave bituminous concrete upper binder layer, 3/4" maximum aggregate size mix, esal range A/B (424B635) | TON | 363 | $108.00 | $113.90 | $108.50 | $134.46 | $225.00 | $134.20 |
| 0170 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range A/B (424B666) | TON | 550 | $91.00 | $97.39 | $91.40 | $112.41 | $200.00 | $112.20 |
| 0180 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 635 | $29.00 | $36.28 | $48.08 | $48.63 | $40.76 | $45.00 |
| 0190 | Aggregate surfacing (aldot #2) (430B046) | TON | 100 | $34.50 | $62.70 | $63.26 | $56.29 | $50.65 | $45.00 |
| 0200 | Steel reinforcement (502A000) | LB | 44,576 | $1.95 | $1.73 | $1.68 | $1.83 | $1.50 | $1.75 |
| 0210 | Culvert concrete (524A010) | CY | 200 | $1,350.00 | $1,585.50 | $1,537.81 | $1,450.00 | $1,200.00 | $1,150.00 |
| 0220 | 18" side drain pipe (535A001) | LF | 60 | $100.00 | $96.54 | $155.22 | $91.64 | $50.00 | $220.00 |
| 0230 | 24" side drain pipe (535A002) | LF | 60 | $114.00 | $115.37 | $170.53 | $105.69 | $100.00 | $250.00 |
| 0240 | 36" side drain pipe (535A004) | LF | 30 | $165.00 | $165.16 | $189.90 | $153.06 | $158.00 | $350.00 |
| 0250 | Mobilization (600A000) | LS | 1 | $148,000 | $134,699 | $123,367 | $150,933 | $74,500 | $150,000 |
| 0260 | Loose riprap, class 2 (610C001) | TON | 90 | $40.00 | $58.65 | $104.28 | $65.25 | $50.66 | $110.00 |
| 0270 | Filter blanket, geotextile (610D003) | SY | 67 | $4.00 | $15.39 | $12.45 | $6.00 | $7.00 | $15.00 |
| 0280 | Concrete driveway, 6" thick (includes wire mesh) (618B003) | SY | 148 | $101.50 | $107.04 | $175.88 | $129.02 | $125.00 | $130.00 |
| 0290 | 18" side drain pipe end treatment, class 1 (619A101) | EACH | 6 | $1,450.00 | $1,390.85 | $1,867.87 | $1,371.47 | $2,775.00 | $1,800.00 |
| 0300 | 24" side drain pipe end treatment, class 1 (619A102) | EACH | 6 | $1,600.00 | $1,508.95 | $1,867.87 | $1,560.41 | $3,630.00 | $2,400.00 |
| 0310 | 36" side drain pipe end treatment, class 1 (619A104) | EACH | 2 | $2,375.00 | $2,271.64 | $1,868.27 | $2,534.36 | $4,400.00 | $3,000.00 |
| 0320 | Topsoil (650A000) | CY | 660 | $48.00 | $30.95 | $48.72 | $20.62 | $45.00 | $35.00 |
| 0330 | Seeding (652A100) | ACRE | 4 | $1,700.00 | $1,543.70 | $1,876.04 | $1,534.39 | $2,000.00 | $1,200.00 |
| 0340 | Mulching (656A010) | ACRE | 4 | $675.00 | $1,415.89 | $1,768.83 | $1,593.47 | $1,500.00 | $1,000.00 |
| 0350 | Erosion control product, type S3 (659C001) | SY | 1,334 | $3.00 | $4.47 | $1.75 | $5.13 | $4.75 | $3.50 |
| 0360 | Temporary seeding (665A000) | ACRE | 3 | $1,300.00 | $922.63 | $1,742.03 | $1,327.87 | $1,500.00 | $1,200.00 |
| 0370 | Temporary mulching (665B001) | TON | 6 | $315.00 | $794.82 | $1,554.43 | $1,271.19 | $1,200.00 | $250.00 |
| 0380 | Silt fence (665J002) | LF | 700 | $4.00 | $5.94 | $2.78 | $4.33 | $5.00 | $6.00 |
| 0390 | Silt fence removal (665O001) | LF | 700 | $3.00 | $3.61 | $1.13 | $2.15 | $2.00 | $1.00 |
| 0400 | Wattle (665Q002) | LF | 250 | $5.00 | $14.15 | $8.63 | $5.71 | $20.00 | $12.00 |
| 0410 | Geometric controls (680A001) | LS | 1 | $36,800 | $18,996 | $33,005 | $10,000 | $30,000 | $40,000 |
| 0420 | Construction fuel (maximum bid limited to $ 67,448.00) (698A000) | LS | 1 | $0.00 | $0.01 | $0.00 | $0.00 | $1.00 | $0.00 |
| 0430 | Solid temporary traffic stripe (701E000) | LF | 3,600 | $1.50 | $1.58 | $1.07 | $1.21 | $1.70 | $1.50 |
| 0440 | Solid white, class 2, type A traffic stripe (701G249) | LF | 3,600 | $2.00 | $2.10 | $2.14 | $3.15 | $2.23 | $2.50 |
| 0450 | Solid yellow, class 2, type A traffic stripe (701G263) | LF | 3,600 | $2.00 | $2.10 | $2.14 | $3.15 | $2.31 | $2.50 |
| 0460 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 45 | $10.00 | $10.50 | $10.72 | $15.99 | $11.00 | $12.00 |
| 0470 | Removal of existing roadway signs (710C000) | LS | 1 | $975.00 | $1,094.05 | $1,073.98 | $1,653.15 | $6,000.00 | $2,500.00 |
| 0480 | Construction signs (740B000) | SF | 407 | $6.00 | $6.74 | $6.61 | $7.71 | $12.00 | $20.00 |
| 0490 | Cones (36 inches high) (740E000) | EACH | 50 | $21.00 | $23.57 | $23.13 | $44.08 | $60.00 | $56.00 |
| 0500 | Barricades, type III (740F002) | EACH | 10 | $225.00 | $252.47 | $247.84 | $220.42 | $400.00 | $400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of July 25, 2025. Compiled by Mirage Metrics.