ARDOT contract 090647 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 5 IN BAXTER COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, PORTLAND CEMENT CONCRETE BASE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, PORTLAND CEMENT CONCRETE DRIVEWAY, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE, EROSION CONTROL, PAVEMENT MARKING, CONSTRUCT A QUINT R.C. BOX CULVERT (64'4"), AND MISC ITEMS. Let by Arkansas DOT on September 17, 2025, Baxter. 6 bids received; low bid $2,373,216 by Crouse Construction Co..
- Owner
- Arkansas DOT
- Letting
- 17 SEP 2025
- Pay items
- 88
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Crouse Construction Co. | $2,373,216 | Low |
| 2 | Robertson Contractors, Inc. | $2,742,159 | +16% |
| 3 | West Plains BR. & Grading, LLC | $2,785,000 | +17% |
| 4 | Apac-Central, Inc. | $2,997,503 | +26% |
| 5 | Mobley Contractors, Inc. | $3,771,941 | +59% |
| 6 | R.L. Persons Construction, Inc. | $5,298,999 | +123% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crouse Construction Co. | 2. Robertson Contractors, Inc. | 3. West Plains BR. & Grading, LLC | 4. Apac-Central, Inc. | 5. Mobley Contractors, Inc. | 6. R.L. Persons Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 5 | $1,000.00 | $2,000.00 | $1,200.00 | $5,800.00 | $856.29 | $3,805.00 |
| 0002 | Grubbing (201111) | STA | 5 | $1,000.00 | $2,000.00 | $1,200.00 | $6,800.00 | $856.29 | $2,750.00 |
| 0003 | Removal and disposal of curb (202001) | LF | 130 | $10.00 | $8.00 | $6.00 | $12.50 | $22.26 | $57.00 |
| 0004 | Removal and disposal of fence (202011) | LF | 58 | $5.00 | $10.00 | $4.00 | $16.50 | $41.36 | $63.00 |
| 0005 | Removal and disposal of retaining walls (202032) | LF | 58 | $45.00 | $25.00 | $27.00 | $30.00 | $75.65 | $127.50 |
| 0006 | Removal and disposal of concrete pavement (202042) | SY | 191 | $40.00 | $10.00 | $19.50 | $28.75 | $58.04 | $44.00 |
| 0007 | Removal and disposal of concrete driveways (202062) | SY | 132 | $30.00 | $10.00 | $22.50 | $46.50 | $83.98 | $60.50 |
| 0008 | Removal and disposal of sign foundations (202084) | EACH | 3 | $500.00 | $500.00 | $135.00 | $1,475.00 | $1,042.15 | $2,885.00 |
| 0009 | Removal and disposal of pipe culverts (202096) | EACH | 3 | $750.00 | $850.00 | $600.00 | $190.00 | $2,854.30 | $1,165.00 |
| 0010 | Removal and disposal of guardrail (202132) | LF | 518 | $5.00 | $25.00 | $8.00 | $27.00 | $11.80 | $41.50 |
| 0011 | Removal and disposal of signs (202191) | EACH | 3 | $400.00 | $250.00 | $105.00 | $195.00 | $799.62 | $585.00 |
| 0012 | Removal and disposal of planters (202198) | EACH | 1 | $600.00 | $500.00 | $210.00 | $1,500.00 | $599.72 | $1,750.00 |
| 0013 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $40,000 | $40,000 | $35,000 | $47,000 | $277,523 | $49,750 |
| 0014 | Unclassified excavation (210213) | CY | 4,328 | $20.00 | $18.50 | $25.00 | $13.75 | $18.94 | $75.00 |
| 0015 | Compacted embankment (210611) | CY | 4,700 | $15.00 | $24.35 | $35.00 | $37.00 | $77.75 | $50.00 |
| 0016 | Soil stabilization (210702) | TON | 25 | $10.00 | $200.00 | $75.00 | $20.00 | $105.00 | $1,160.00 |
| 0017 | Aggregate base course (class 7) (303117) | TON | 784 | $25.00 | $35.00 | $42.50 | $50.00 | $111.11 | $51.70 |
| 0018 | Portland cement concrete base (5" uniform thickness) (309505) | SY | 62 | $100.00 | $130.00 | $125.00 | $84.00 | $161.99 | $130.50 |
| 0019 | Portland cement concrete base (5 1/2" uniform thickness) (309516) | SY | 162 | $100.00 | $145.00 | $115.00 | $51.00 | $112.26 | $145.00 |
| 0020 | Tack coat (401011) | GAL | 641 | $3.50 | $3.75 | $3.75 | $3.25 | $3.94 | $7.25 |
| 0021 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 419 | $130.00 | $95.09 | $95.09 | $130.00 | $99.84 | $246.50 |
| 0022 | Asphalt binder (PG 64-22) in achm base course (1 1/2") (minimum bid $120.00) (405402) | TON | 20 | $120.00 | $120.00 | $120.00 | $120.00 | $126.00 | $203.00 |
| 0023 | Mineral aggregate in achm binder course (1") (406161) | TON | 445 | $130.00 | $110.17 | $110.17 | $130.00 | $115.68 | $253.75 |
| 0024 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 23 | $120.00 | $120.00 | $120.00 | $120.00 | $126.00 | $203.00 |
| 0025 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,014 | $130.00 | $116.58 | $116.58 | $130.00 | $122.41 | $265.35 |
| 0026 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 4 | $120.00 | $120.00 | $120.00 | $120.00 | $126.00 | $203.00 |
| 0027 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 60 | $120.00 | $120.00 | $120.00 | $120.00 | $126.00 | $217.50 |
| 0028 | Cold milling asphalt pavement (412002) | SY | 267 | $35.00 | $18.82 | $22.00 | $34.00 | $19.76 | $58.00 |
| 0029 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 3 | $450.00 | $300.00 | $150.00 | $425.00 | $262.50 | $725.00 |
| 0030 | Achm patching of existing roadway (415011) | TON | 3 | $450.00 | $300.00 | $150.00 | $425.00 | $262.50 | $725.00 |
| 0031 | Portland cement concrete driveway (505011) | SY | 293 | $110.00 | $218.27 | $100.00 | $60.00 | $137.92 | $210.00 |
| 0032 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $100,000 | $130,000 | $132,500 | $120,000 | $159,919 | $250,000 |
| 0033 | Furnishing field office (602011) | EACH | 1 | $20,000 | $25,000 | $20,000 | $18,750 | $59,374 | $61,500 |
| 0034 | Maintenance of traffic (603010) | LS | 1 | $75,000 | $50,000 | $234,372 | $155,000 | $342,034 | $1,010,525 |
| 0035 | Signs (604003) | SF | 408 | $12.00 | $12.00 | $12.00 | $16.09 | $12.60 | $17.40 |
| 0036 | Barricades (604013) | LF | 32 | $25.00 | $25.00 | $25.00 | $32.17 | $26.25 | $36.25 |
| 0037 | Traffic drums (604023) | EACH | 19 | $50.00 | $50.00 | $50.00 | $69.70 | $52.50 | $123.50 |
| 0038 | Traffic cone (604026) | EACH | 24 | $25.00 | $25.00 | $25.00 | $32.17 | $26.25 | $36.25 |
| 0039 | Furnishing and installing precast concrete barrier (604031) | LF | 133 | $120.00 | $85.00 | $90.00 | $128.68 | $136.50 | $130.50 |
| 0040 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 133 | $30.00 | $15.00 | $22.00 | $32.17 | $31.50 | $31.90 |
| 0041 | Construction pavement markings (604041) | LF | 7,822 | $2.50 | $2.50 | $2.50 | $3.23 | $2.63 | $3.65 |
| 0042 | Vertical panels (604083) | EACH | 19 | $75.00 | $75.00 | $75.00 | $64.34 | $78.75 | $108.75 |
| 0043 | Concrete ditch paving (type B) (605012) | SY | 120 | $110.00 | $166.88 | $125.00 | $100.00 | $223.65 | $250.00 |
| 0044 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 82 | $90.00 | $115.00 | $90.00 | $130.00 | $177.21 | $245.00 |
| 0045 | 12" side drain (606701) | LF | 600 | $25.00 | $75.00 | $14.00 | $87.00 | $66.66 | $150.00 |
| 0046 | 24" side drain (606704) | LF | 110 | $80.00 | $120.00 | $85.00 | $130.00 | $178.02 | $135.00 |
| 0047 | 51" X 31" side drain (606730) | LF | 42 | $175.00 | $235.00 | $165.00 | $358.71 | $406.80 | $275.00 |
| 0048 | Selected pipe bedding (606994) | CY | 70 | $10.00 | $82.00 | $32.75 | $38.00 | $39.83 | $145.00 |
| 0049 | Drop inlets (type MO) (609134) | EACH | 8 | $8,000.00 | $7,450.00 | $9,250.00 | $7,000.00 | $12,227 | $7,300.00 |
| 0050 | Drop inlets (type special) (609144) | EACH | 2 | $10,000 | $8,500.00 | $9,800.00 | $10,000 | $8,149.50 | $11,685 |
| 0051 | Drop inlet extensions (4') (609311) | EACH | 4 | $1,500.00 | $2,500.00 | $2,200.00 | $2,400.00 | $2,362.21 | $1,225.00 |
| 0052 | Yard drains (609511) | EACH | 6 | $1,000.00 | $1.00 | $4,500.00 | $3,000.00 | $1,906.07 | $4,325.00 |
| 0053 | 4" pipe underdrains (611008) | LF | 500 | $15.00 | $1.00 | $4.05 | $45.00 | $23.33 | $88.50 |
| 0054 | Underdrain outlet protectors (611013) | EACH | 2 | $500.00 | $1.00 | $525.00 | $2,150.00 | $1,886.16 | $1,165.00 |
| 0055 | Lime (620001) | TON | 3 | $65.00 | $65.00 | $200.00 | $225.00 | $68.25 | $94.25 |
| 0056 | Seeding (620011) | ACRE | 1.34 | $1,398.29 | $1,398.29 | $2,500.00 | $2,680.93 | $1,468.20 | $2,025.00 |
| 0057 | Mulch cover (620022) | ACRE | 7.49 | $1,132.64 | $1,132.64 | $1,250.00 | $1,340.47 | $1,189.27 | $1,650.00 |
| 0058 | Water (620030) | MGAL | 268.30 | $10.00 | $10.00 | $10.00 | $10.72 | $10.50 | $14.50 |
| 0059 | Temporary seeding (621001) | ACRE | 6.15 | $787.46 | $787.46 | $750.00 | $804.28 | $826.83 | $1,150.00 |
| 0060 | Silt fence (621021) | LF | 1,579 | $4.00 | $3.61 | $3.50 | $3.75 | $3.79 | $5.25 |
| 0061 | Sand bag ditch checks (621031) | BAG | 248 | $10.89 | $10.89 | $10.00 | $10.72 | $11.43 | $16.00 |
| 0062 | Sediment removal and disposal (621111) | CY | 86 | $8.00 | $1.00 | $0.50 | $17.24 | $47.08 | $73.25 |
| 0063 | Rock ditch checks (621151) | CY | 68 | $100.00 | $95.00 | $85.00 | $60.00 | $171.03 | $145.00 |
| 0064 | Filter sock (12") (621168) | LF | 288 | $9.64 | $9.64 | $9.00 | $9.65 | $10.12 | $14.00 |
| 0065 | Second seeding application (623001) | ACRE | 1.34 | $425.00 | $425.00 | $400.00 | $428.95 | $446.25 | $616.25 |
| 0066 | Solid sodding (624001) | SY | 481 | $6.87 | $6.87 | $6.00 | $6.43 | $7.21 | $12.60 |
| 0067 | Erosion control matting (class 3) (626003) | SY | 304 | $5.95 | $5.95 | $7.00 | $7.53 | $6.25 | $8.65 |
| 0068 | Concrete walks (633011) | SY | 434 | $100.00 | $127.08 | $98.00 | $65.00 | $90.63 | $95.00 |
| 0069 | Hand railing (633201) | LF | 137 | $90.00 | $150.00 | $95.00 | $162.00 | $125.27 | $175.00 |
| 0070 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 1,382 | $30.00 | $38.00 | $48.00 | $33.00 | $63.94 | $49.75 |
| 0071 | Roadway construction control (635001) | LS | 1 | $20,000 | $40,000 | $30,000 | $65,000 | $34,597 | $90,000 |
| 0072 | Wheelchair ramps (type 3) (641020) | SY | 16 | $700.00 | $769.84 | $450.00 | $800.00 | $653.90 | $875.00 |
| 0073 | Thermoplastic pavement marking white (6") (719002) | LF | 245 | $3.50 | $3.50 | $3.50 | $4.02 | $3.68 | $5.00 |
| 0074 | Thermoplastic pavement marking white (12") (719005) | LF | 22 | $20.00 | $20.00 | $20.00 | $26.81 | $21.00 | $29.00 |
| 0075 | Thermoplastic pavement marking yellow (6") (719102) | LF | 2,137 | $3.50 | $3.50 | $3.50 | $4.30 | $3.68 | $5.00 |
| 0076 | Thermoplastic pavement marking (words) (719201) | EACH | 2 | $500.00 | $500.00 | $500.00 | $589.81 | $525.00 | $725.00 |
| 0077 | Thermoplastic pavement marking (arrows) (719202) | EACH | 3 | $450.00 | $450.00 | $450.00 | $536.19 | $472.50 | $652.50 |
| 0078 | Raised pavement markers (type II) (721002) | EACH | 41 | $25.00 | $25.00 | $25.00 | $32.17 | $26.25 | $36.25 |
| 0079 | Temporary impact attenuation barrier (731071) | EACH | 1 | $8,500.00 | $9,820.00 | $8,500.00 | $9,651.35 | $11,025 | $19,575 |
| 0080 | Temporary impact attenuation barrier (repair) (731072) | EACH | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $2,144.75 | $1,050.00 | $1,450.00 |
| 0081 | Temporary impact attenuation barrier (relocation) (731075) | EACH | 1 | $7,500.00 | $7,500.00 | $7,500.00 | $8,578.98 | $9,975.00 | $18,125 |
| 0082 | Unclassified excavation for structures-roadway (801101) | CY | 354 | $90.00 | $85.00 | $325.00 | $251.90 | $371.73 | $700.00 |
| 0083 | Class S concrete-roadway (802012) | CY | 877.17 | $1,100.00 | $1,280.00 | $1,000.00 | $1,375.00 | $1,136.04 | $1,435.00 |
| 0084 | Reinforcing steel-roadway (grade 60) (804003) | LB | 118,994 | $1.50 | $1.95 | $2.25 | $0.77 | $2.05 | $2.00 |
| 0085 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 296 | $98.50 | $78.00 | $122.00 | $166.78 | $195.00 | |
| 0087 | 18" smooth spiral rib polymer precoated metallic coated corrugated steel pipe (605903) | LF | 296 | $65.00 | |||||
| 0088 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 1 | $1,550.00 | $2,500.00 | $7,800.00 | $2,985.84 | $1,800.00 | |
| 0090 | 18" flared end sections for corrugated steel pipe culverts (605857) | EACH | 1 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of September 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.