ARDOT letting results, September 23, 2026

9 contracts let by Arkansas DOT on September 23, 2026, $52,268,591 in low bids, a median of 3 bidders per contract.

Owner
Arkansas DOT
Contracts
9
Low bids, total
$52,268,591
Data through
04 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapSource
070458THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT ONE FOUR LANE MEDIAN STRUCTURE ON HIGHWAY 82 IN COLUMBIA COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMColumbia7Mobley Contractors, Inc.$27,033,828$28,810,764+7.0%ARDOT
061938THE PURPOSE OF THIS PROJECT IS TO PLACE GUARDRAILS ALONG VARIOUS INTERSTATES IN PULASKI COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, EARTHWORK, Pulaski2Collins & Hermann, Inc.$14,778,442$14,954,812+1.0%ARDOT
110716THE PURPOSE OF THIS PROJECT IS TO REPLACE THREE STRUCTURES ON HIGHWAYS 185 AND 318 IN PHILLIPS COUNTY. THIS PROJECT CONSISITS OF CLEARING AND GRUBBING, REMOVAL Phillips81911 Construction Company, Inc.$2,994,162$3,533,216+18%ARDOT
061921THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT CROSSWALKS, PEDESTRIAN, AND ADA IMPROVEMENTS ON HIGHWAYS 10 AND 365 IN PULASKI COUNTY. THIS PROJECT CONSISTS OF REMOPulaski3Ti-Zack Concrete, LLC$2,643,278$2,717,266+3.0%ARDOT
012559THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT CROSSWALKS, PEDESTRIAN, AND ADA IMPROVEMENTS ON HIGHWAYS 70 AND 91 IN CRITTENDEN AND CRAIGHEAD COUNTIES. THIS PROJECCraighead, Crittenden2Shelby Electric Co., Inc.$2,560,413$2,681,034+5.0%ARDOT
CB0401THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT A QUINT. 12' X 8' R.C. BOX CULVERT AND APPROACHES ON 0.138 MILE OF BREDEHOEFT ROAD IN THE CITY OF SPRINGTOWN IN BENTBenton6Mobley Contractors, Inc.$1,094,785$1,289,754+18%ARDOT
061950THE PURPOSE OF THIS PROJECT IS TO RESURFACE AND UPDATE PAVEMENT MARKING OF THE PARKING LOTS AT THE ARDOT CENTRAL OFFICE IN PULASKI COUNTY. THIS PROJECT CONSISTSPulaski2Redstone Construction Group, Inc.$725,172$799,989+10%ARDOT
SA2046THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.96 MILE OF COUNTY ROAD 246 IN DALLAS COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, ACHM PATCHIDallas3Redstone Construction Group, Inc.$299,878$331,498+11%ARDOT
SA6949THE PURPOSE OF THIS PROJECT IS TO SURFACE 0.18 MILE OF HERPEL ROAD IN STONE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, RECONSTRUCTED BASE COURSE, AStone1Atlas Asphalt, Inc.$138,633ARDOT
ARDOT contracts let on September 23, 2026, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ARDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy