ARDOT contract 070458 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT ONE FOUR LANE MEDIAN STRUCTURE ON HIGHWAY 82 IN COLUMBIA COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, ACHM BASE, BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH SLABS AND GUTTERS, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPS IN ASPHALT SHOULDERS, PAVEMENT MARKING, CONSTRUCT ONE CONTINUOUS PLATE GIRDER UNIT (856.16'), AND MISC. ITEMS. Let by Arkansas DOT on September 23, 2026, Columbia. 7 bids received; low bid $27,033,828 by Mobley Contractors, Inc..
- Owner
- Arkansas DOT
- Letting
- 23 SEP 2026
- Pay items
- 97
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mobley Contractors, Inc. | $27,033,828 | Low |
| 2 | Capital Paving & Construction, LLC | $28,810,764 | +7.0% |
| 3 | Robertson Contractors, Inc. | $29,331,953 | +9.0% |
| 4 | JB James Construction, LLC | $29,718,607 | +10% |
| 5 | McMillen, Inc. | $30,640,849 | +13% |
| 6 | WL Bass Construction, Inc. | $30,668,520 | +13% |
| 7 | Manhattan Road & Bridge Co. | $31,163,931 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mobley Contractors, Inc. | 2. Capital Paving & Construction, LLC | 3. Robertson Contractors, Inc. | 4. JB James Construction, LLC | 5. McMillen, Inc. | 6. WL Bass Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 69 | $1,312.50 | $1,582.43 | $1,250.00 | $2,000.00 | $5,000.00 | $1,300.00 |
| 0002 | Grubbing (201111) | STA | 69 | $656.25 | $791.21 | $625.00 | $1,000.00 | $3,000.00 | $650.00 |
| 0003 | Removal and disposal of curb and gutter (202003) | LF | 2,595 | $5.25 | $6.33 | $5.00 | $8.00 | $19.05 | $5.00 |
| 0004 | Removal and disposal of fence (202011) | LF | 1,320 | $4.20 | $5.06 | $4.00 | $5.00 | $5.71 | $4.00 |
| 0005 | Removal and disposal of gates (202017) | EACH | 1 | $210.00 | $253.19 | $200.00 | $165.00 | $1,473.53 | $200.00 |
| 0006 | Removal and disposal of concrete pavement (202042) | SY | 4,100 | $10.50 | $12.66 | $10.00 | $10.00 | $13.57 | $10.00 |
| 0007 | Removal and disposal of pipe culverts (202096) | EACH | 1 | $262.50 | $316.49 | $250.00 | $1,000.00 | $11,875 | $250.00 |
| 0008 | Removal and disposal of concrete ditch paving (202125) | SY | 840 | $21.00 | $25.32 | $20.00 | $20.00 | $33.61 | $20.00 |
| 0009 | Unclassified excavation (210213) | CY | 26,486 | $9.89 | $11.93 | $9.42 | $14.00 | $25.00 | $10.00 |
| 0010 | Compacted embankment (210611) | CY | 146,587 | $11.03 | $13.29 | $10.50 | $14.00 | $21.00 | $11.00 |
| 0011 | Soil stabilization (210702) | TON | 1,500 | $420.00 | $506.37 | $400.00 | $300.00 | $330.00 | $400.00 |
| 0012 | Aggregate base course (class 7) (303117) | TON | 18,601 | $51.66 | $62.29 | $49.20 | $55.00 | $62.00 | $50.00 |
| 0013 | Tack coat (401011) | GAL | 3,445 | $4.46 | $5.26 | $4.25 | $4.25 | $5.00 | $5.00 |
| 0014 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 3,554 | $156.01 | $183.51 | $148.58 | $150.00 | $150.00 | $150.00 |
| 0015 | Asphalt binder (PG 70-22) in achm base course (1 1/2") (minimum bid $120.00) (405412) | TON | 179 | $126.00 | $148.21 | $120.00 | $120.00 | $125.00 | $120.00 |
| 0016 | Mineral aggregate in achm binder course (1") (406161) | TON | 3,116 | $160.14 | $188.36 | $152.51 | $152.00 | $155.00 | $155.00 |
| 0017 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 164 | $126.00 | $148.21 | $120.00 | $120.00 | $125.00 | $120.00 |
| 0018 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 5,662 | $172.25 | $202.62 | $164.05 | $164.00 | $164.00 | $165.00 |
| 0019 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 381 | $126.00 | $148.21 | $120.00 | $120.00 | $125.00 | $120.00 |
| 0020 | Cold milling asphalt pavement (412002) | SY | 767 | $16.38 | $19.27 | $15.60 | $16.00 | $17.00 | $16.00 |
| 0021 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 10 | $735.00 | $864.55 | $750.00 | $970.00 | $900.00 | $750.00 |
| 0022 | Achm patching of existing roadway (415011) | TON | 10 | $525.00 | $617.53 | $500.00 | $500.00 | $650.00 | $550.00 |
| 0023 | Approach slabs (504031) | CY | 280.40 | $725.28 | $492.88 | $905.00 | $750.00 | $600.00 | $670.00 |
| 0024 | Approach gutters (504264) | CY | 16.80 | $1,555.60 | $1,536.23 | $1,560.00 | $1,200.00 | $1,130.00 | $2,100.00 |
| 0025 | Furnishing field office (602011) | EACH | 1 | $107,467 | $122,519 | $75,000 | $30,000 | $90,000 | $22,000 |
| 0026 | Maintenance of traffic (603009) | LS | 1 | $1,162,886 | $769,424 | $300,000 | $480,000 | $150,000 | $500,000 |
| 0027 | Signs (604003) | SF | 409 | $15.75 | $16.06 | $15.00 | $15.00 | $29.52 | $15.00 |
| 0028 | Construction project information sign update (604010) | EACH | 6 | $472.50 | $61.75 | $50.00 | $100.00 | $64.18 | $1,000.00 |
| 0029 | Barricades (604013) | LF | 80 | $57.75 | $37.05 | $55.00 | $25.00 | $32.09 | $55.00 |
| 0030 | Traffic drums (604023) | EACH | 59 | $57.75 | $49.40 | $55.00 | $50.00 | $64.18 | $55.00 |
| 0031 | Furnishing and installing precast concrete barrier (604031) | LF | 632 | $53.72 | $59.28 | $48.00 | $48.00 | $66.54 | $78.00 |
| 0032 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 572 | $12.60 | $14.82 | $12.00 | $12.00 | $16.64 | $19.50 |
| 0033 | Construction pavement markings (604041) | LF | 23,604 | $0.26 | $0.31 | $0.25 | $0.60 | $0.74 | $0.30 |
| 0034 | Removable construction pavement markings (604051) | LF | 3,716 | $2.10 | $2.47 | $2.00 | $4.00 | $5.33 | $2.00 |
| 0035 | Removal of permanent pavement markings (604061) | LF | 7,686 | $1.05 | $1.24 | $1.00 | $1.00 | $1.28 | $1.00 |
| 0036 | Vertical panels (604083) | EACH | 34 | $57.75 | $55.58 | $55.00 | $75.00 | $96.27 | $55.00 |
| 0037 | Concrete ditch paving (type B) (605012) | SY | 274 | $159.89 | $116.96 | $235.00 | $140.00 | $118.43 | $110.00 |
| 0038 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 82 | $128.18 | $154.55 | $122.08 | $260.00 | $338.16 | $125.00 |
| 0039 | 24" reinforced concrete pipe culverts (class V) (605609) | LF | 245 | $314.39 | $379.05 | $299.42 | $190.00 | $164.65 | $300.00 |
| 0040 | 36" reinforced concrete pipe culverts (class IV) (605618) | LF | 234 | $324.46 | $391.19 | $309.01 | $290.00 | $238.55 | $320.00 |
| 0041 | 60" reinforced concrete pipe culverts (class III) (605636) | LF | 88 | $583.66 | $703.70 | $555.87 | $600.00 | $2,131.69 | $600.00 |
| 0042 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 2 | $2,020.17 | $2,435.64 | $1,923.97 | $7,000.00 | $9,038.38 | $2,000.00 |
| 0043 | 36" flared end sections for reinforced concrete pipe culverts (605862) | EACH | 4 | $3,569.31 | $4,303.39 | $3,399.34 | $7,000.00 | $7,127.80 | $3,500.00 |
| 0044 | 60" flared end sections for reinforced concrete pipe culverts (605870) | EACH | 2 | $7,986.47 | $9,628.99 | $7,606.16 | $8,000.00 | $12,825 | $8,000.00 |
| 0045 | 18" side drain (606703) | LF | 236 | $83.30 | $100.43 | $79.33 | $210.00 | $129.91 | $80.00 |
| 0046 | Selected pipe bedding (606994) | CY | 60 | $78.75 | $94.95 | $75.00 | $140.00 | $250.00 | $77.00 |
| 0047 | Drop inlets (type RM special) (609141) | EACH | 4 | $3,574.73 | $3,412.47 | $9,800.00 | $5,000.00 | $5,312.21 | $5,500.00 |
| 0048 | 4" pipe underdrains (611008) | LF | 3,000 | $23.63 | $28.48 | $22.50 | $12.00 | $30.00 | $25.00 |
| 0049 | Underdrain outlet protectors (611013) | EACH | 12 | $523.36 | $630.99 | $498.44 | $900.00 | $750.00 | $500.00 |
| 0050 | Pavement repair over culverts (asphalt) (615022) | TON | 34 | $529.83 | $617.53 | $525.00 | $500.00 | $360.09 | $770.00 |
| 0051 | Guardrail (type A) (617005) | LF | 450 | $34.65 | $40.76 | $33.00 | $33.00 | $42.36 | $33.00 |
| 0052 | Guardrail terminal (type 2) (617312) | EACH | 4 | $3,543.75 | $4,168.36 | $3,375.00 | $3,375.00 | $4,332.09 | $3,400.00 |
| 0053 | Thrie beam guardrail terminal (617332) | EACH | 4 | $2,625.00 | $3,087.68 | $2,500.00 | $2,500.00 | $3,208.96 | $2,500.00 |
| 0054 | Wire fence (type C) (619027) | LF | 1,293 | $9.07 | $10.67 | $8.64 | $9.00 | $11.09 | $9.00 |
| 0055 | 7' steel chain link fence (619134) | LF | 260 | $136.50 | $160.56 | $130.00 | $130.00 | $200.00 | $130.00 |
| 0056 | Lime (620001) | TON | 90 | $132.30 | $155.62 | $126.00 | $126.00 | $130.00 | $126.00 |
| 0057 | Seeding (620011) | ACRE | 45.01 | $1,522.50 | $1,790.85 | $1,450.00 | $1,450.00 | $1,450.00 | $1,450.00 |
| 0058 | Mulch cover (620022) | ACRE | 112.04 | $1,039.50 | $1,222.72 | $990.00 | $990.00 | $1,000.00 | $990.00 |
| 0059 | Water (620030) | MGAL | 5,963.70 | $5.00 | $6.18 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0060 | Temporary seeding (621001) | ACRE | 67.03 | $787.50 | $926.30 | $750.00 | $750.00 | $750.00 | $750.00 |
| 0061 | Silt fence (621021) | LF | 27,709 | $3.36 | $3.95 | $3.20 | $5.00 | $3.20 | $5.00 |
| 0062 | Sand bag ditch checks (621031) | BAG | 264 | $10.50 | $12.35 | $10.00 | $10.00 | $12.00 | $11.00 |
| 0063 | Diversion ditch (621041) | LF | 1,672 | $3.24 | $4.58 | $10.00 | $12.00 | $12.00 | $120.00 |
| 0064 | Sediment basin (621071) | CY | 2,117 | $5.88 | $3.62 | $14.00 | $4.00 | $20.00 | $8.00 |
| 0065 | Obliteration of sediment basin (621101) | CY | 2,117 | $5.88 | $3.62 | $14.00 | $4.00 | $10.00 | $9.00 |
| 0066 | Sediment removal and disposal (621111) | CY | 3,233 | $5.88 | $3.56 | $16.00 | $10.00 | $24.00 | $21.00 |
| 0067 | Pipe for slope drains (621131) | LF | 181 | $38.42 | $45.10 | $80.00 | $40.00 | $75.00 | $33.00 |
| 0068 | Rock ditch checks (621151) | CY | 234 | $129.17 | $71.95 | $125.00 | $220.00 | $135.00 | $160.00 |
| 0069 | Filter sock (18") (621169) | LF | 92 | $13.65 | $16.06 | $13.00 | $13.00 | $17.00 | $14.00 |
| 0070 | Second seeding application (623001) | ACRE | 45.01 | $367.50 | $432.28 | $350.00 | $350.00 | $449.25 | $350.00 |
| 0071 | Solid sodding (624001) | SY | 417 | $8.90 | $10.47 | $8.48 | $9.00 | $10.88 | $9.00 |
| 0072 | Erosion control matting (class 3) (626003) | SY | 89 | $11.03 | $12.97 | $10.50 | $105.00 | $13.48 | $11.00 |
| 0073 | Roadway construction control (635001) | LS | 1 | $168,298 | $527,626 | $150,000 | $500,000 | $192,537 | $300,000 |
| 0074 | Bridge construction control (636001) | LS | 1 | $74,996 | $259,365 | $205,000 | $500,000 | $256,717 | $300,000 |
| 0075 | Rumble strips in asphalt shoulders (642001) | LF | 8,953 | $1.82 | $1.79 | $0.80 | $0.25 | $2.23 | $1.00 |
| 0076 | Thermoplastic pavement marking white (6") (719002) | LF | 13,640 | $1.05 | $1.24 | $1.00 | $1.00 | $1.25 | $1.00 |
| 0077 | Thermoplastic pavement marking yellow (6") (719102) | LF | 13,660 | $1.05 | $1.24 | $1.00 | $1.00 | $1.25 | $1.00 |
| 0078 | Raised pavement markers (type II) (721002) | EACH | 257 | $7.35 | $8.65 | $7.00 | $7.00 | $8.99 | $7.00 |
| 0079 | Unclassified excavation for structures-bridge (801001) | CY | 543 | $111.12 | $154.72 | $130.00 | $130.00 | $29.50 | $75.00 |
| 0080 | Unclassified excavation for structures-roadway (801101) | CY | 36 | $53.73 | $4.10 | $340.00 | $130.00 | $479.63 | $350.00 |
| 0081 | Class S concrete-roadway (802012) | CY | 95.39 | $2,307.82 | $1,048.46 | $1,650.00 | $6,000.00 | $1,766.24 | $1,200.00 |
| 0082 | Class S concrete-bridge (802112) | CY | 1,573 | $1,097.99 | $1,140.84 | $1,600.00 | $1,800.00 | $750.00 | $1,700.00 |
| 0083 | Class S(AE) concrete-bridge (802122) | CY | 1,785 | $1,244.03 | $1,067.52 | $1,685.00 | $1,800.00 | $1,000.00 | $1,750.00 |
| 0084 | Class 2 protective surface treatment (803004) | SY | 7,876.80 | $5.78 | $1.80 | $6.50 | $8.00 | $6.42 | $12.00 |
| 0085 | Reinforcing steel-roadway (grade 60) (804003) | LB | 44,390 | $2.08 | $2.52 | $2.40 | $2.20 | $1.90 | $2.00 |
| 0086 | Reinforcing steel-bridge (grade 60) (804013) | LB | 300,200 | $1.87 | $1.40 | $2.10 | $2.20 | $1.47 | $2.00 |
| 0087 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 491,300 | $1.78 | $1.50 | $2.25 | $2.20 | $1.67 | $1.60 |
| 0088 | Concrete piling (18" square) (805213) | LF | 12,955 | $165.28 | $166.64 | $265.00 | $140.00 | $290.00 | $160.00 |
| 0089 | Test pile (18" square) (805663) | LF | 521 | $282.01 | $346.02 | $550.00 | $1,000.00 | $378.00 | $300.00 |
| 0090 | Structural steel in plate girder spans (A709, GR. 50W) (807234) | LB | 2,081,050 | $4.03 | $4.69 | $3.70 | $3.50 | $4.44 | $4.80 |
| 0091 | Painting structural steel (807301) | TON | 131.80 | $2,100.77 | $2,717.15 | $1,050.00 | $2,000.00 | $2,200.00 | $2,000.00 |
| 0092 | Elastomeric bearings (808002) | CUIN | 70,725 | $3.25 | $3.39 | $5.10 | $3.00 | $4.00 | $3.50 |
| 0093 | Armored joint with neoprene strip seal (809013) | LF | 154 | $549.27 | $642.48 | $570.00 | $500.00 | $501.41 | $400.00 |
| 0094 | Bridge name plate (type D) (812004) | EACH | 1 | $1,411.03 | $1,260.98 | $2,500.00 | $2,500.00 | $2,553.28 | $700.00 |
| 0095 | Dumped riprap (816111) | CY | 10 | $182.30 | $460.59 | $345.00 | $450.00 | $450.00 | $220.00 |
| 0096 | Concrete riprap (816121) | CY | 356 | $825.69 | $630.69 | $1,510.00 | $1,000.00 | $659.05 | $1,300.00 |
| 0097 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $949,196 | $529,183 | $1,345,000 | $1,400,000 | $1,458,000 | $1,400,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of September 23, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way