FDOT contract T1906 bid tabulation
SR 25 (US 27) FROM STITT RANCH TO W OF FLAGHOLE RD. Let by Florida DOT on March 26, 2025, Hendry, District 1. 6 bids received; low bid $9,321,660 by Ohla USA Inc.
- Owner
- Florida DOT
- Letting
- 26 MAR 2025
- Pay items
- 104
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ohla USA Inc | $9,321,660 | Low |
| 2 | Pigott Asphalt and Sitework LLC | $9,357,540 | 0.0% |
| 3 | C.W. Roberts Contracting, Inc. | $9,450,606 | +1.0% |
| 4 | General Asphalt Company, LLC | $9,548,165 | +2.0% |
| 5 | Ranger Construction Industries, Inc. | $9,984,743 | +7.0% |
| 6 | Ajax Paving Industries of Florida LLC | $10,396,865 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohla USA Inc | 2. Pigott Asphalt and Sitework LLC | 3. C.W. Roberts Contracting, Inc. | 4. General Asphalt Company, LLC | 5. Ranger Construction Industries, Inc. | 6. Ajax Paving Industries of Florida LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $930,000 | $1,000,000 | $650,000 | $990,000 | $975,000 | $950,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $594,226 | $650,000 | $180,000 | $1,000,000 | $450,000 | $1,091,300 |
| 0015 | Traffic control officer (0102-14) | HR | 1,000 | $0.01 | $65.00 | $85.75 | $88.00 | $108.60 | $121.09 |
| 0020 | Work zone sign (0102-60) | ED | 18,025 | $0.23 | $0.20 | $0.30 | $0.27 | $0.22 | $0.30 |
| 0025 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 17,951 | $0.01 | $5.00 | $45.75 | $0.01 | $50.00 | $20.00 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 244,250 | $0.12 | $0.05 | $0.12 | $0.11 | $0.11 | $0.12 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 500 | $6.09 | $5.00 | $5.85 | $5.45 | $5.72 | $5.77 |
| 0040 | Temporary crash cushion, redirective option (0102-89-1) | LO | 10 | $0.01 | $500.00 | $3,400.00 | $910.15 | $6,507.00 | $1,268.55 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 1,792 | $10.96 | $10.00 | $12.00 | $11.17 | $10.30 | $11.82 |
| 0050 | Portable regulatory, sign (0102-150-1) | ED | 1,000 | $5.48 | $5.00 | $5.50 | $5.18 | $5.15 | $5.48 |
| 0055 | Radar speed display unit (0102-150-2) | ED | 1,000 | $6.09 | $5.00 | $5.50 | $5.18 | $5.72 | $5.48 |
| 0060 | Removable tape, white, solid 6" (0102-913-21) | GM | 1.35 | $0.01 | $3,500.00 | $15,000 | $13,625 | $14,860 | $14,415 |
| 0065 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.03 | $0.71 | $7,500.00 | $5,000.00 | $5,450.00 | $6,860.00 | $5,766.14 |
| 0070 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.05 | $0.94 | $3,500.00 | $14,000 | $13,625 | $14,860 | $14,415 |
| 0075 | Sediment barrier (0104-10-3) | LF | 39,721 | $2.13 | $1.65 | $1.85 | $0.01 | $1.84 | $2.02 |
| 0080 | Floating turbidity barrier (0104-11) | LF | 390 | $15.22 | $12.00 | $11.50 | $21.80 | $14.30 | $14.42 |
| 0085 | Inlet protection system (0104-18) | EACH | 18 | $182.65 | $300.00 | $148.50 | $218.00 | $160.10 | $172.98 |
| 0090 | Litter removal (0107-1) | ACRE | 585.65 | $35.31 | $10.00 | $53.75 | $1.10 | $33.15 | $33.44 |
| 0095 | Mowing (0107-2) | ACRE | 555.38 | $96.19 | $25.00 | $106.25 | $1.10 | $90.30 | $91.10 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $778,000 | $65,000 | $67,500 | $216,365 | $248,500 | $150,000 |
| 0105 | Mailbox, F&I single (0110-7-1) | EACH | 6 | $365.30 | $350.00 | $350.00 | $545.00 | $514.50 | $144.15 |
| 0110 | Regular excavation (0120-1) | CY | 1,765 | $55.55 | $36.00 | $27.00 | $96.36 | $47.55 | $46.77 |
| 0115 | Subsoil excavation (0120-4) | CY | 89 | $134.90 | $50.00 | $76.50 | $54.50 | $102.60 | $113.60 |
| 0120 | Embankment (0120-6) | CY | 1,695 | $83.13 | $30.00 | $19.00 | $71.72 | $49.15 | $69.67 |
| 0125 | Type B stabilization (0160-4) | SY | 2,374 | $35.50 | $15.00 | $34.00 | $25.29 | $31.85 | $29.90 |
| 0130 | Optional base, base group 09 (0285-709) | SY | 211 | $450.69 | $150.00 | $110.00 | $224.54 | $133.80 | $92.24 |
| 0135 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 1,028 | $3.91 | $3.00 | $7.50 | $8.69 | $4.45 | $16.37 |
| 0140 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 1,508 | $3.91 | $3.00 | $115.00 | $5.93 | $3.55 | $11.12 |
| 0145 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 7,785 | $3.91 | $2.50 | $4.00 | $3.78 | $3.09 | $6.09 |
| 0150 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 54,074 | $3.91 | $2.50 | $2.00 | $3.53 | $3.78 | $3.62 |
| 0155 | Milling existing asphalt pavement, 1 3/4" avg depth (0327-70-13) | SY | 382 | $3.91 | $5.00 | $14.50 | $16.55 | $3.25 | $26.43 |
| 0160 | Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15) | SY | 29,496 | $3.91 | $2.50 | $2.25 | $4.18 | $4.24 | $2.89 |
| 0165 | Milling existing asphalt pavement, 3 1/4" avg depth (0327-70-17) | SY | 25,227 | $3.91 | $2.50 | $3.15 | $5.03 | $4.71 | $4.26 |
| 0170 | Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20) | SY | 22,616 | $3.91 | $2.50 | $2.80 | $5.27 | $5.17 | $4.85 |
| 0175 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 34.70 | $1,100.00 | $500.00 | $575.25 | $1,477.06 | $376.00 | $642.07 |
| 0180 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 16,095.60 | $135.00 | $178.00 | $181.00 | $148.97 | $155.00 | $168.15 |
| 0185 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 5,392.80 | $185.00 | $240.00 | $239.25 | $192.93 | $207.30 | $254.76 |
| 0190 | Miscellaneous asphalt (0339-1) | TN | 1,178.20 | $240.00 | $300.00 | $186.50 | $230.35 | $184.40 | $270.41 |
| 0195 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 8 | $400.00 | $600.00 | $540.00 | $872.00 | $571.50 | $394.25 |
| 0200 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 1 | $6,485.49 | $3,000.00 | $4,800.00 | $6,343.80 | $5,145.00 | $5,461.91 |
| 0205 | Concrete curb & gutter, type E (0520-1-7) | LF | 2,005 | $36.10 | $65.00 | $38.00 | $71.40 | $87.70 | $25.37 |
| 0210 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 151 | $89.68 | $150.00 | $116.00 | $183.99 | $160.50 | $54.49 |
| 0215 | Concrete slope pavement,non reinforced, 4" (0524-2-2) | SY | 59 | $205.78 | $165.00 | $186.00 | $204.92 | $186.50 | $57.66 |
| 0220 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 7.10 | $627.66 | $200.00 | $291.50 | $436.00 | $285.80 | $345.97 |
| 0225 | Bedding stone (0530-74) | TN | 5.10 | $251.06 | $200.00 | $257.00 | $436.00 | $228.70 | $230.65 |
| 0230 | Guardrail -roadway, general (0536-1-1) | LF | 34,800 | $29.19 | $25.00 | $26.50 | $24.10 | $25.30 | $25.00 |
| 0235 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 7 | $213.39 | $100.00 | $194.25 | $185.29 | $194.40 | $196.04 |
| 0240 | Guardrail removal (0536-73) | LF | 17,678 | $0.65 | $1.00 | $0.60 | $0.57 | $0.59 | $0.60 |
| 0245 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 11 | $1,843.35 | $2,500.00 | $1,700.00 | $1,264.26 | $1,326.00 | $1,337.59 |
| 0250 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 12 | $3,846.03 | $3,000.00 | $3,500.00 | $2,854.51 | $2,994.00 | $3,020.10 |
| 0255 | Performance turf, sod (0570-1-2) | SY | 51,077 | $3.62 | $3.00 | $3.35 | $5.29 | $4.27 | $4.11 |
| 0260 | Plastic erosion mat, TRM, type 2 (0571-1-12) | SY | 436 | $12.79 | $10.00 | $13.00 | $17.44 | $13.50 | $12.11 |
| 0265 | Conduit, furnish & install, open trench (0630-2-11) | LF | 196 | $32.15 | $35.00 | $40.50 | $33.35 | $40.60 | $40.94 |
| 0270 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 89 | $66.97 | $60.00 | $62.00 | $124.63 | $61.70 | $62.27 |
| 0275 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,972.61 | $1,750.00 | $2,000.00 | $2,358.01 | $2,041.00 | $2,058.51 |
| 0280 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 4 | $3,385.08 | $2,500.00 | $3,000.00 | $2,899.47 | $3,053.00 | $3,079.12 |
| 0285 | Traffic monitoring site inductive loop assembly, & install, 1 loop (0695-6-11) | EACH | 10 | $1,887.37 | $2,500.00 | $2,300.00 | $2,367.86 | $2,255.00 | $2,274.17 |
| 0290 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 4 | $3,555.56 | $2,500.00 | $2,300.00 | $2,890.09 | $2,255.00 | $2,274.17 |
| 0295 | Traffic monitoring site weigh- motion electronic sensor, furnish & install, with special foundation socket (0695-9-11) | EACH | 4 | $13,516 | $25,000 | $24,000 | $34,594 | $24,190 | $24,398 |
| 0300 | Raised pavement marker, type B (0706-1-3) | EACH | 6,555 | $4.69 | $6.00 | $5.75 | $4.91 | $5.72 | $5.19 |
| 0305 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 19.07 | $2,130.45 | $1,500.00 | $1,300.00 | $1,744.00 | $1,258.00 | $1,845.16 |
| 0310 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 1.25 | $2,829.53 | $1,600.00 | $1,700.00 | $1,962.00 | $1,715.00 | $2,075.81 |
| 0315 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 78 | $2.07 | $3.00 | $2.30 | $3.27 | $2.29 | $3.46 |
| 0320 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 60 | $2.19 | $5.00 | $2.30 | $4.36 | $2.29 | $4.61 |
| 0325 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 17.92 | $608.83 | $750.00 | $577.00 | $1,090.00 | $571.50 | $1,153.23 |
| 0330 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.15 | $913.27 | $750.00 | $800.00 | $1,090.00 | $800.50 | $1,153.23 |
| 0335 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 148 | $48.71 | $75.00 | $35.00 | $49.05 | $34.30 | $51.90 |
| 0340 | Painted pavement markings, standard, white, yield line (0710-11180) | LF | 334 | $7.31 | $5.00 | $5.75 | $16.35 | $5.72 | $17.30 |
| 0345 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 11.81 | $2,129.45 | $1,200.00 | $1,260.00 | $1,744.00 | $1,258.00 | $1,845.16 |
| 0350 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 124 | $2.07 | $3.00 | $2.30 | $3.27 | $2.29 | $3.46 |
| 0355 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 1.36 | $913.24 | $750.00 | $800.00 | $1,090.00 | $800.50 | $1,153.23 |
| 0360 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $106,330 | $106,330 | $106,330 | $106,330 | $106,330 | $106,330 |
| 0365 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 10.88 | $3,974.73 | $1,800.00 | $2,400.00 | $2,293.58 | $2,914.00 | $2,404.48 |
| 0370 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 57 | $516.29 | $600.00 | $500.00 | $561.62 | $485.00 | $488.97 |
| 0375 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 16 | $2,177.17 | $1,900.00 | $2,000.00 | $1,757.34 | $2,044.00 | $2,061.97 |
| 0380 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $487.05 | $200.00 | $470.00 | $403.56 | $457.50 | $461.29 |
| 0385 | Single column ground sign assembly, remove (0700-1600) | EACH | 36 | $60.88 | $50.00 | $59.00 | $54.50 | $57.20 | $57.66 |
| 0390 | Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113) | EACH | 2 | $6,518.11 | $9,000.00 | $6,275.00 | $6,913.63 | $6,120.00 | $6,173.23 |
| 0395 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 8 | $7,175.65 | $10,000 | $6,900.00 | $7,715.46 | $6,738.00 | $6,795.97 |
| 0400 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 8 | $8,483.41 | $11,500 | $8,200.00 | $10,698 | $7,966.00 | $8,034.54 |
| 0405 | Multi-column ground sign assembly, F&I ground mount, 1-200.0 SF (0700-2116) | EACH | 2 | $23,084 | $25,000 | $22,000 | $18,013 | $21,680 | $21,863 |
| 0410 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 20 | $1,339.42 | $1,500.00 | $1,300.00 | $1,090.00 | $1,258.00 | $1,268.55 |
| 0415 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 6 | $354.34 | $350.00 | $340.00 | $350.06 | $332.50 | $335.59 |
| 0420 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 2 | $152.21 | $250.00 | $147.00 | $172.22 | $142.90 | $144.15 |
| 0425 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 6 | $36.53 | $50.00 | $35.00 | $113.36 | $34.30 | $34.60 |
| 0430 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 6 | $66.97 | $350.00 | $65.00 | $104.64 | $62.90 | $63.43 |
| 0435 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 77 | $91.32 | $150.00 | $88.00 | $141.70 | $85.80 | $86.49 |
| 0440 | Object marker, type 1 (0705-10-1) | EACH | 24 | $249.62 | $250.00 | $240.00 | $365.15 | $234.40 | $236.41 |
| 0445 | Object marker, type 2 (0705-10-2) | EACH | 36 | $110.81 | $200.00 | $107.00 | $226.72 | $104.10 | $104.94 |
| 0450 | Delineator, non-flexible (0705-11-2) | EACH | 18 | $110.81 | $150.00 | $107.00 | $130.80 | $104.00 | $104.94 |
| 0455 | Raised pavement marker, type B (0706-1-3) | EACH | 2,702 | $4.69 | $6.00 | $5.75 | $5.45 | $5.72 | $5.77 |
| 0460 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 1,059 | $4.87 | $5.00 | $4.60 | $10.90 | $4.57 | $11.53 |
| 0465 | Painted pavement markings, surface (0710-90) | LS | 1 | $62,531 | $50,000 | $46,000 | $49,050 | $45,730 | $51,895 |
| 0470 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 39 | $7.23 | $6.00 | $7.00 | $10.90 | $6.86 | $11.53 |
| 0475 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 30 | $9.55 | $8.00 | $8.00 | $16.35 | $8.00 | $17.30 |
| 0480 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.06 | $3,293.61 | $5,000.00 | $4,500.00 | $4,905.00 | $4,573.00 | $5,189.52 |
| 0485 | Thermoplastic, standard, arrow (0711-11170) | EACH | 74 | $94.98 | $100.00 | $87.00 | $98.10 | $85.80 | $103.79 |
| 0490 | Thermoplastic, standard, yield line (0711-11180) | LF | 167 | $10.96 | $30.00 | $35.00 | $21.80 | $34.30 | $23.06 |
| 0495 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 62 | $6.71 | $8.00 | $7.00 | $10.90 | $6.86 | $11.53 |
| 0500 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.68 | $3,348.54 | $5,000.00 | $4,600.00 | $4,905.00 | $4,573.00 | $5,189.52 |
| 0505 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 7.65 | $7,761.93 | $7,000.00 | $7,850.00 | $6,322.00 | $7,775.00 | $6,688.72 |
| 0510 | Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102) | GM | 0.62 | $10,312 | $8,500.00 | $9,200.00 | $7,085.00 | $9,147.00 | $7,495.98 |
| 0515 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 7.24 | $1,941.50 | $2,500.00 | $2,500.00 | $3,815.00 | $2,515.00 | $4,036.30 |
| 0520 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 5.90 | $7,263.26 | $7,500.00 | $7,850.00 | $6,322.00 | $7,775.00 | $6,688.72 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.