FDOT contract T1948 bid tabulation
AT CENTRAL ELEMENTARY. Let by Florida DOT on August 26, 2026, Hendry, District 1. 10 bids received; low bid $731,641 by Leon America Construction.
- Owner
- Florida DOT
- Letting
- 26 AUG 2026
- Pay items
- 54
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Leon America Construction | $731,641 | Low |
| 2 | Yoroca Engineering Contractors, LLC | $844,714 | +15% |
| 3 | Alexander Design + Build, LLC | $1,013,615 | +39% |
| 4 | American Design Engineering Construction Inc. | $1,066,346 | +46% |
| 5 | Jones Benitez Corporation | $1,075,851 | +47% |
| 6 | Rogar Management & Consulting of Florida LLC | $1,091,903 | +49% |
| 7 | Wrangler Construction Inc. | $1,130,014 | +54% |
| 8 | Blacktip Services Incorporated | $1,268,045 | +73% |
| 9 | Estep Construction, Inc. | $1,349,108 | +84% |
| 10 | Signal Technology and Installation Corp. | $1,717,781 | +135% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Leon America Construction | 2. Yoroca Engineering Contractors, LLC | 3. Alexander Design + Build, LLC | 4. American Design Engineering Construction Inc. | 5. Jones Benitez Corporation | 6. Rogar Management & Consulting of Florida LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $80,000 | $100,000 | $152,000 | $175,000 | $120,000 | $50,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $50,000 | $25,000 | $67,600 | $20,000 | $60,000 | $35,000 |
| 0015 | Commercial material for temporary driveway maintenance (0102-3) | CY | 72.90 | $65.00 | $15.00 | $35.00 | $100.00 | $80.00 | $50.00 |
| 0020 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $10,000 | $5,000.00 | $9,100.00 | $5,000.00 | $5,000.00 | $3,000.00 |
| 0025 | Work zone sign (0102-60) | ED | 9,390 | $0.20 | $0.19 | $0.46 | $3.50 | $0.56 | $0.50 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 6,428 | $0.10 | $0.11 | $0.13 | $3.50 | $0.23 | $1.00 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 2,410 | $0.06 | $0.06 | $0.20 | $3.50 | $0.37 | $4.00 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 60 | $5.00 | $11.70 | $13.00 | $30.00 | $10.00 | $10.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 1,352 | $6.00 | $9.90 | $7.00 | $45.00 | $17.00 | $15.00 |
| 0050 | Type III barricade (0102-115) | ED | 500 | $0.60 | $0.29 | $0.78 | $3.50 | $1.00 | $1.00 |
| 0055 | Removable tape, white, 12" crosswalk (0102-913-24) | LF | 202 | $5.66 | $5.00 | $24.00 | $4.00 | $22.00 | $6.00 |
| 0060 | Sediment barrier (0104-10-3) | LF | 3,808 | $2.50 | $5.00 | $3.75 | $6.00 | $2.00 | $3.00 |
| 0065 | Inlet protection system (0104-18) | EACH | 12 | $176.00 | $250.00 | $300.00 | $10.00 | $180.00 | $10.00 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $31,140 | $50,000 | $28,600 | $4,500.00 | $24,000 | $25,000 |
| 0075 | Removal of existing concrete (0110-4-10) | SY | 244 | $40.00 | $20.00 | $36.50 | $8.00 | $24.00 | $60.00 |
| 0080 | Mailbox, F&I single (0110-7-1) | EACH | 11 | $500.00 | $350.00 | $750.00 | $150.00 | $250.00 | $50.00 |
| 0085 | Tree removal (0110-23) | EACH | 4 | $270.00 | $350.00 | $1,500.00 | $150.00 | $2,400.00 | $100.00 |
| 0090 | Regular excavation (0120-1) | CY | 553.40 | $6.00 | $50.00 | $19.50 | $15.00 | $30.00 | $44.00 |
| 0095 | Embankment (0120-6) | CY | 122.80 | $9.00 | $50.00 | $36.40 | $15.00 | $20.00 | $44.00 |
| 0100 | Type B stabilization (0160-4) | SY | 88 | $5.00 | $50.00 | $58.50 | $15.00 | $12.00 | $44.00 |
| 0105 | Optional base, base group 11 (0285-711) | SY | 426 | $30.00 | $30.00 | $58.50 | $118.00 | $100.00 | $44.00 |
| 0110 | Turnout construction- asphalt/driveway base- asphalt material (0286-2) | TN | 96.20 | $180.00 | $120.00 | $280.00 | $285.00 | $200.00 | $300.00 |
| 0115 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 95 | $135.00 | $250.00 | $280.00 | $285.00 | $350.00 | $300.00 |
| 0120 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 8 | $6,000.00 | $10,000 | $9,000.00 | $14,500 | $8,000.00 | $15,000 |
| 0125 | Inlets, DT bot, type F, <10' (0425-1561) | EACH | 2 | $9,000.00 | $10,000 | $10,400 | $14,500 | $10,000 | $15,000 |
| 0130 | Inlets, gutter, type V, <10' (0425-1711) | EACH | 1 | $10,000 | $10,000 | $11,000 | $14,500 | $14,000 | $15,000 |
| 0135 | Manholes, P-7, <10' (0425-2-41) | EACH | 3 | $8,000.00 | $10,000 | $10,000 | $14,500 | $9,000.00 | $15,000 |
| 0140 | Manholes, P-7, partial (0425-2-43) | EACH | 2 | $6,500.00 | $5,000.00 | $7,800.00 | $14,500 | $6,000.00 | $8,800.00 |
| 0145 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 23 | $170.00 | $200.00 | $219.00 | $70.00 | $200.00 | $300.00 |
| 0150 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 90 | $210.00 | $200.00 | $115.00 | $44.00 | $160.00 | $300.00 |
| 0155 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 33 | $110.00 | $200.00 | $170.00 | $52.00 | $240.00 | $300.00 |
| 0160 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 8 | $150.00 | $200.00 | $230.00 | $75.00 | $320.00 | $300.00 |
| 0165 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 27 | $200.00 | $200.00 | $219.00 | $75.00 | $150.00 | $300.00 |
| 0170 | Mitered end section, optional round, 15" CD (0430-982123) | EACH | 2 | $2,500.00 | $1,500.00 | $2,600.00 | $1,500.00 | $3,000.00 | $3,500.00 |
| 0175 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 5 | $3,000.00 | $1,500.00 | $3,700.00 | $1,500.00 | $3,400.00 | $3,500.00 |
| 0180 | Pipe handrail - guiderail, steel (0515-1-1) | LF | 18 | $70.00 | $250.00 | $195.00 | $200.00 | $270.00 | $100.00 |
| 0185 | Concrete curb & gutter, type F (0520-1-10) | LF | 145 | $35.00 | $100.00 | $65.00 | $35.00 | $50.00 | $48.00 |
| 0190 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 2,548 | $58.00 | $61.00 | $75.00 | $65.00 | $90.00 | $119.00 |
| 0195 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 171 | $80.00 | $75.00 | $100.00 | $75.00 | $130.00 | $121.00 |
| 0200 | Detectable warnings (0527-2) | SF | 351 | $30.00 | $20.00 | $36.50 | $30.00 | $30.00 | $21.00 |
| 0205 | Performance turf, sod (0570-1-2) | SY | 5,053 | $4.00 | $4.00 | $5.00 | $6.00 | $4.50 | $7.66 |
| 0210 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 42 | $540.00 | $500.00 | $750.00 | $850.00 | $1,800.00 | $465.00 |
| 0215 | Single column ground sign assembly, remove (0700-1600) | EACH | 14 | $55.00 | $50.00 | $150.00 | $20.00 | $320.00 | $10.00 |
| 0220 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 19 | $105.00 | $55.00 | $125.00 | $20.00 | $170.00 | $4.00 |
| 0225 | Enhanced highway sign solar powered, F&I ground mount, W/2 beacons, 12-20 SF of static sign panels (0700-142122) | EACH | 4 | $12,000 | $15,000 | $11,500 | $9,500.00 | $14,000 | $18,000 |
| 0230 | Object marker, type 1 (0705-10-1) | EACH | 3 | $280.00 | $250.00 | $330.00 | $65.00 | $320.00 | $100.00 |
| 0235 | Raised pavement marker, type B (0706-1-3) | EACH | 24 | $4.50 | $4.00 | $10.00 | $3.00 | $8.00 | $4.00 |
| 0240 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,000.00 | $9,982.00 | $8,500.00 | $2,500.00 | $15,500 | $2,500.00 |
| 0245 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 963 | $3.50 | $3.25 | $8.00 | $6.00 | $5.00 | $3.00 |
| 0250 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 257 | $7.00 | $6.52 | $19.00 | $6.00 | $10.00 | $6.00 |
| 0255 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 811 | $16.00 | $17.25 | $26.00 | $6.50 | $27.00 | $6.00 |
| 0260 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.17 | $5,000.00 | $8,758.00 | $15,000 | $5,500.00 | $14,000 | $15,000 |
| 0265 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.16 | $5,000.00 | $8,757.00 | $15,000 | $5,500.00 | $14,000 | $15,000 |
| 0270 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 171 | $4.20 | $5.00 | $8.00 | $60.00 | $8.00 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.