FDOT contract T2A84 bid tabulation
SR 20 FROM ROWLAND AVE TO S PALM AVE AND FROM SR 19 TO ALABAMA. Let by Florida DOT on October 28, 2026, Putnam, District 2. 7 bids received; low bid $9,234,345 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 28 OCT 2026
- Pay items
- 119
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $9,234,345 | Low |
| 2 | Pigott Asphalt and Sitework LLC | $9,862,608 | +7.0% |
| 3 | Halifax Paving, Inc. | $10,147,264 | +10% |
| 4 | Preferred Materials Inc. | $10,173,460 | +10% |
| 5 | C.W. Roberts Contracting, Inc. | $10,647,468 | +15% |
| 6 | Hubbard Construction Company | $12,282,806 | +33% |
| 7 | Duval Asphalt Products, Inc. | $12,714,781 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. Pigott Asphalt and Sitework LLC | 3. Halifax Paving, Inc. | 4. Preferred Materials Inc. | 5. C.W. Roberts Contracting, Inc. | 6. Hubbard Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization 21000475201, (0101-1) | LS | 1 | $561,654 | $625,000 | $341,820 | $401,523 | $435,000 | $745,986 |
| 0010 | Maintenance of traffic 21000475201, (0102-1) | DA | 1 | $283,417 | $300,000 | $225,000 | $222,919 | $280,000 | $724,435 |
| 0015 | Pedestrian or bicycle special detour 21000475201, (0102-4-1) | SY | 1 | $29,962 | $20,000 | $7,500.00 | $4,532.74 | $7,000.00 | $24,075 |
| 0020 | Traffic control officer (0102-14) | HR | 184 | $109.06 | $250.00 | $150.00 | $100.00 | $87.00 | $94.79 |
| 0025 | Work zone sign (0102-60) | ED | 32,090 | $0.22 | $0.10 | $0.21 | $0.20 | $0.22 | $0.20 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 30,652 | $0.11 | $0.01 | $0.11 | $0.10 | $0.11 | $0.10 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 5,757 | $0.04 | $0.20 | $0.06 | $0.06 | $0.07 | $0.08 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 640 | $5.45 | $5.00 | $5.00 | $4.80 | $5.00 | $5.13 |
| 0045 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 4,544 | $4.91 | $4.33 | $5.00 | $5.00 | $4.25 | $4.45 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 668 | $10.91 | $10.50 | $14.00 | $10.40 | $10.80 | $10.99 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 900 | $9.42 | $0.25 | $8.64 | $8.64 | $9.80 | $9.18 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 900 | $9.42 | $0.25 | $8.64 | $8.64 | $9.80 | $9.18 |
| 0065 | Type III barricade (0102-115) | ED | 1,060 | $0.27 | $0.50 | $0.40 | $0.26 | $0.26 | $0.31 |
| 0070 | Portable regulatory, sign (0102-150-1) | ED | 600 | $5.45 | $1.00 | $5.00 | $4.00 | $4.15 | $5.23 |
| 0075 | Radar speed display unit (0102-150-2) | ED | 600 | $5.45 | $1.00 | $5.00 | $4.00 | $4.15 | $5.23 |
| 0080 | Artificial coverings /rolled erosion control products (0104-1) | SY | 250 | $8.88 | $1.00 | $20.00 | $10.45 | $8.15 | $9.42 |
| 0085 | Sediment barrier (0104-10-3) | LF | 387 | $11.90 | $3.00 | $2.00 | $6.77 | $7.30 | $2.09 |
| 0090 | Inlet protection system (0104-18) | EACH | 176 | $136.32 | $60.00 | $135.00 | $78.23 | $30.50 | $141.31 |
| 0095 | Litter removal (0107-1) | ACRE | 1,489.50 | $49.07 | $1.00 | $26.00 | $55.00 | $26.15 | $27.21 |
| 0100 | Mowing (0107-2) | ACRE | 1,152.43 | $21.81 | $1.00 | $55.00 | $25.00 | $55.50 | $57.57 |
| 0105 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $47,740 | $25,000 | $5,000.00 | $22,324 | $45,000 | $23,496 |
| 0110 | Removal of existing concrete (0110-4-10) | SY | 526 | $34.35 | $40.00 | $50.00 | $37.50 | $42.40 | $39.11 |
| 0115 | Type B stabilization (0160-4) | SY | 440 | $20.56 | $15.00 | $25.00 | $35.00 | $4.90 | $44.93 |
| 0120 | Optional base, base group 09 (0285-709) | SY | 234 | $37.08 | $40.00 | $50.00 | $63.00 | $32.50 | $67.03 |
| 0125 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 245,086 | $1.90 | $2.50 | $2.75 | $1.75 | $1.35 | $3.20 |
| 0130 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 51,220 | $1.95 | $2.00 | $3.50 | $3.69 | $3.80 | $5.99 |
| 0135 | Milling existing asphalt pavement, 3/4" avg depth (0327-70-19) | SY | 34,414 | $1.30 | $1.00 | $3.00 | $1.82 | $3.75 | $2.35 |
| 0140 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 25,683.20 | $123.80 | $135.00 | $145.00 | $144.06 | $142.00 | $150.86 |
| 0145 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 6,344.20 | $171.50 | $195.00 | $180.00 | $200.34 | $227.00 | $213.66 |
| 0150 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 13,939.10 | $127.60 | $139.00 | $145.00 | $150.76 | $176.00 | $170.63 |
| 0155 | Manhole, adjust (0425-5) | EACH | 11 | $1,128.26 | $1,800.00 | $2,000.00 | $1,250.00 | $1,130.00 | $1,857.25 |
| 0160 | Valve boxes, adjust (0425-6) | EACH | 4 | $1,128.26 | $1,200.00 | $2,000.00 | $1,250.00 | $924.00 | $1,731.84 |
| 0165 | Pipe handrail - guiderail, relocate, steel (0515-1-41) | LF | 63 | $27.26 | $22.50 | $20.00 | $65.00 | $23.50 | $21.25 |
| 0170 | Pedestrian / bicycle railing, steel, 42" type 1 (0515-2211) | LF | 20 | $185.39 | $174.08 | $165.00 | $125.00 | $194.10 | $175.34 |
| 0175 | Concrete curb & gutter, type F (0520-1-10) | LF | 401 | $38.17 | $56.00 | $45.00 | $39.50 | $40.00 | $52.34 |
| 0180 | Valley gutter- concrete (0520-3) | LF | 80 | $38.17 | $100.00 | $45.00 | $52.50 | $36.00 | $52.34 |
| 0185 | Concrete traffic separator, special- variable width (0520-70) | SY | 207 | $93.24 | $115.00 | $125.00 | $145.00 | $51.45 | $247.18 |
| 0190 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 72 | $92.69 | $100.00 | $55.00 | $45.00 | $138.90 | $57.85 |
| 0195 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 243 | $93.24 | $120.00 | $75.00 | $65.00 | $122.00 | $89.80 |
| 0200 | Detectable warnings (0527-2) | SF | 282 | $27.03 | $35.00 | $35.00 | $37.50 | $48.00 | $39.11 |
| 0205 | Performance turf, sod (0570-1-2) | SY | 24,992 | $2.73 | $3.00 | $4.00 | $4.69 | $4.15 | $5.75 |
| 0210 | Shoulder drop off soil (0570-13-1) | CY | 3,806.30 | $4.51 | $1.00 | $20.00 | $32.00 | $1.00 | $33.50 |
| 0215 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 4 | $2,185.49 | $2,505.63 | $2,004.05 | $2,004.05 | $2,293.00 | $2,129.42 |
| 0220 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 4 | $2,647.34 | $2,954.00 | $2,427.57 | $2,427.57 | $2,778.00 | $2,579.44 |
| 0225 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 20.81 | $1,199.59 | $1,266.00 | $1,100.00 | $1,099.68 | $1,249.00 | $1,302.26 |
| 0230 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.05 | $1,308.64 | $1,371.50 | $1,200.00 | $1,200.00 | $1,354.00 | $1,411.20 |
| 0235 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 4,818 | $1.36 | $1.32 | $1.50 | $1.50 | $1.29 | $1.36 |
| 0240 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 545 | $1.64 | $1.58 | $1.75 | $1.75 | $1.55 | $1.63 |
| 0245 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 2,539 | $1.74 | $1.85 | $1.60 | $1.60 | $1.80 | $1.90 |
| 0250 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 16.29 | $490.75 | $633.00 | $450.00 | $449.89 | $625.00 | $651.16 |
| 0255 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.88 | $490.75 | $633.00 | $450.00 | $445.90 | $619.25 | $645.39 |
| 0260 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 99 | $81.79 | $68.58 | $75.00 | $75.00 | $67.70 | $70.56 |
| 0265 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 385 | $43.62 | $47.48 | $40.00 | $40.00 | $46.85 | $48.85 |
| 0270 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 15.70 | $1,199.59 | $1,266.00 | $1,100.00 | $1,099.44 | $1,249.50 | $1,301.97 |
| 0275 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 1.27 | $490.75 | $633.00 | $450.00 | $447.51 | $621.50 | $647.71 |
| 0280 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $109,802 | $109,802 | $109,802 | $109,802 | $109,802 | $109,802 |
| 0285 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $674.30 | $674.30 | $674.30 | $674.30 | $674.30 | $674.30 |
| 0290 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 13.93 | $2,181.07 | $1,800.00 | $2,970.00 | $3,450.30 | $3,306.50 | $3,138.19 |
| 0295 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 111 | $486.29 | $527.50 | $445.91 | $445.91 | $476.10 | $473.81 |
| 0300 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 27 | $1,587.17 | $2,162.75 | $1,455.42 | $1,455.42 | $1,554.00 | $1,546.47 |
| 0305 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 9 | $1,937.24 | $2,321.00 | $1,776.21 | $1,776.21 | $1,896.50 | $1,887.33 |
| 0310 | Single column ground sign assembly, remove (0700-1600) | EACH | 70 | $117.78 | $59.08 | $108.00 | $108.00 | $115.30 | $114.76 |
| 0315 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 25 | $473.60 | $226.83 | $434.28 | $434.28 | $463.50 | $461.45 |
| 0320 | Sign panel, furnish & install ground mount, 12-20 SF (0700-3102) | EACH | 8 | $634.41 | $300.68 | $581.75 | $581.75 | $621.10 | $618.14 |
| 0325 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 27 | $117.78 | $36.93 | $108.00 | $108.00 | $115.30 | $114.76 |
| 0330 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 5 | $176.66 | $58.03 | $162.00 | $162.00 | $173.00 | $172.13 |
| 0335 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 46 | $74.01 | $68.58 | $67.87 | $67.87 | $72.45 | $72.12 |
| 0340 | Object marker, type 1 (0705-10-1) | EACH | 27 | $162.88 | $237.38 | $149.35 | $149.35 | $159.45 | $158.69 |
| 0345 | Delineator, flexible tubular (0705-11-1) | EACH | 59 | $168.19 | $110.78 | $154.22 | $154.22 | $164.65 | $163.87 |
| 0350 | Delineator, non-flexible (0705-11-2) | EACH | 12 | $155.59 | $89.25 | $142.67 | $142.67 | $152.30 | $151.60 |
| 0355 | Raised pavement marker, type B (0706-1-3) | EACH | 4,544 | $4.91 | $4.33 | $5.00 | $5.00 | $4.25 | $4.45 |
| 0360 | Painted pavement markings, surface (0710-90) | LS | 1 | $80,676 | $84,303 | $73,979 | $73,979 | $84,000 | $144,312 |
| 0365 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.05 | $5,452.66 | $6,330.00 | $5,000.00 | $5,000.00 | $6,252.00 | $6,513.20 |
| 0370 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,818 | $4.36 | $4.22 | $4.00 | $4.00 | $4.15 | $4.34 |
| 0375 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 435 | $4.63 | $5.28 | $4.25 | $4.25 | $5.20 | $5.43 |
| 0380 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 870 | $6.54 | $6.33 | $6.00 | $6.00 | $6.20 | $6.51 |
| 0385 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.88 | $1,526.75 | $1,477.00 | $1,400.00 | $1,387.24 | $1,445.00 | $1,505.89 |
| 0390 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 12 | $190.84 | $184.63 | $175.00 | $175.00 | $182.00 | $189.97 |
| 0395 | Thermoplastic, standard, arrow (0711-11170) | EACH | 298 | $70.88 | $79.13 | $65.00 | $65.00 | $78.00 | $81.41 |
| 0400 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 110 | $4.63 | $5.28 | $4.25 | $4.25 | $5.20 | $5.43 |
| 0405 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 1.27 | $1,526.75 | $1,055.00 | $1,400.00 | $1,392.27 | $1,036.00 | $1,079.53 |
| 0410 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,669 | $13.09 | $14.77 | $12.00 | $12.00 | $14.50 | $15.20 |
| 0415 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 87 | $158.13 | $200.45 | $145.00 | $145.00 | $198.00 | $206.25 |
| 0420 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 87 | $98.16 | $105.50 | $90.00 | $90.00 | $104.00 | $108.55 |
| 0425 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 9.31 | $5,670.77 | $5,291.88 | $5,600.00 | $5,596.39 | $5,223.00 | $5,441.49 |
| 0430 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 8.43 | $1,744.85 | $1,392.60 | $1,800.00 | $1,799.15 | $1,374.00 | $1,432.22 |
| 0435 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 8.09 | $5,670.77 | $5,064.00 | $5,600.00 | $5,598.62 | $5,000.00 | $5,209.24 |
| 0440 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 9.26 | $4,798.34 | $5,064.00 | $4,600.00 | $4,598.51 | $5,000.00 | $5,208.84 |
| 0445 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.22 | $5,234.56 | $5,570.40 | $4,800.00 | $4,666.67 | $5,349.00 | $5,572.36 |
| 0450 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 7.86 | $1,526.75 | $1,266.00 | $1,500.00 | $1,500.00 | $1,250.00 | $1,302.63 |
| 0455 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 7.61 | $4,798.34 | $5,064.00 | $4,600.00 | $4,596.37 | $4,997.00 | $5,206.42 |
| 0460 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 1,169 | $3.82 | $1.74 | $3.50 | $3.50 | $1.70 | $1.79 |
| 0465 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.20 | $27,590 | $33,760 | $25,300 | $24,401 | $32,158 | $33,503 |
| 0470 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.20 | $16,903 | $12,660 | $15,500 | $14,949 | $12,694 | $12,563 |
| 0475 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.20 | $27,809 | $33,760 | $25,500 | $24,594 | $32,158 | $33,503 |
| 0480 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.20 | $16,903 | $12,660 | $15,500 | $14,949 | $12,694 | $12,563 |
| 0485 | Conduit, furnish & install, open trench (0630-2-11) | LF | 112 | $27.78 | $21.36 | $25.47 | $25.47 | $29.10 | $27.06 |
| 0490 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 467 | $27.84 | $63.04 | $25.53 | $25.53 | $29.20 | $27.13 |
| 0495 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 2 | $4,431.37 | $10,128 | $4,063.49 | $4,063.49 | $4,650.00 | $4,317.70 |
| 0500 | Signal cable- repair/replace/other, furnish & install (0632-7-2) | LF | 90 | $5.26 | $11.24 | $4.82 | $4.82 | $5.50 | $5.12 |
| 0505 | Signal cable, remove- intersection (0632-7-6) | PI | 2 | $942.22 | $1,724.93 | $864.00 | $864.00 | $989.00 | $918.05 |
| 0510 | Span wire assembly, F&I, two point, perpendicular (0634-4151) | PI | 2 | $9,644.07 | $3,555.35 | $8,843.46 | $8,843.46 | $10,119 | $9,396.70 |
| 0515 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 5 | $1,549.54 | $1,329.30 | $1,420.90 | $1,420.90 | $1,626.00 | $1,509.79 |
| 0520 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $3,492.70 | $7,021.03 | $3,202.74 | $3,202.74 | $3,665.00 | $3,403.10 |
| 0525 | Electrical service wire, & install (0639-2-1) | LF | 15 | $6.00 | $8.76 | $5.50 | $5.50 | $6.25 | $5.84 |
| 0530 | Electrical service wire, (0639-2-6) | LF | 50 | $1.18 | $2.06 | $1.08 | $1.08 | $1.22 | $1.15 |
| 0535 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,102.77 | $1,677.45 | $1,928.21 | $1,928.21 | $2,206.25 | $2,048.83 |
| 0540 | Prestressed concrete pole, type P-VIII (0641-2-18) | EACH | 4 | $29,529 | $26,375 | $27,078 | $27,078 | $30,984 | $28,772 |
| 0545 | Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70) | EACH | 6 | $12,249 | $4,035.38 | $11,232 | $11,232 | $12,852 | $11,935 |
| 0550 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $3,617.12 | $2,637.50 | $3,316.84 | $3,316.84 | $3,795.00 | $3,524.34 |
| 0555 | Aluminum signals pole, remove (0646-1-60) | EACH | 6 | $651.89 | $793.36 | $597.78 | $597.78 | $684.00 | $635.18 |
| 0560 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 10 | $980.92 | $891.48 | $899.49 | $899.49 | $1,029.00 | $955.76 |
| 0565 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 5 | $1,903.29 | $875.65 | $1,745.29 | $1,745.29 | $1,987.00 | $1,854.47 |
| 0570 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 8 | $298.24 | $200.45 | $273.78 | $273.78 | $313.00 | $290.91 |
| 0575 | Loop assembly, F&I, type F (0660-2106) | AS | 17 | $1,830.54 | $2,136.38 | $1,678.57 | $1,678.57 | $1,920.00 | $1,783.58 |
| 0580 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 24 | $342.68 | $371.89 | $314.23 | $314.23 | $359.00 | $333.89 |
| 0585 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 12 | $58.89 | $78.07 | $54.00 | $54.00 | $61.50 | $57.38 |
| 0590 | Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202) | EACH | 2 | $1,120.30 | $1,171.05 | $1,027.29 | $1,027.29 | $1,270.00 | $1,091.56 |
| 0595 | Enhanced highway sign AC powered, F&I overhead W/beacon, 31-50 SF of static sign panels (0700-141314) | EACH | 4 | $7,394.64 | $2,505.63 | $6,780.76 | $6,780.76 | $7,759.00 | $7,204.96 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.