FDOT contract T4709 bid tabulation
SR 716 (PORT ST LUCIE BLVD) AND SR 5 (US 1/NW FEDERAL HWY). Let by Florida DOT on January 29, 2025, St Lucie, District 4. 4 bids received; low bid $6,811,256 by Ranger Construction Industries, Inc..
- Owner
- Florida DOT
- Letting
- 29 JAN 2025
- Pay items
- 139
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ranger Construction Industries, Inc. | $6,811,256 | Low |
| 2 | Timothy Rose Contracting, Inc. | $7,298,995 | +7.0% |
| 3 | C.W. Roberts Contracting, Inc. | $7,634,494 | +12% |
| 4 | Ohla USA Inc | $7,850,920 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ranger Construction Industries, Inc. | 2. Timothy Rose Contracting, Inc. | 3. C.W. Roberts Contracting, Inc. | 4. Ohla USA Inc |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $408,000 | $230,718 | $510,000 | $392,500 |
| 0010 | Mobilization (0101-1) | LS | 1 | $272,000 | $233,087 | $385,000 | $392,500 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $390,165 | $227,909 | $213,000 | $424,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $271,190 | $244,216 | $162,000 | $424,000 |
| 0025 | Traffic control officer (0102-14) | HR | 404 | $86.20 | $88.17 | $75.00 | $87.92 |
| 0030 | Work zone sign (0102-60) | ED | 39,000 | $0.25 | $0.24 | $0.25 | $0.20 |
| 0035 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 1,587 | $55.20 | $60.87 | $60.00 | $52.00 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 72,980 | $0.15 | $0.14 | $0.15 | $0.10 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 14,800 | $0.05 | $0.06 | $0.05 | $0.10 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 952 | $6.15 | $6.29 | $7.00 | $7.00 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 1,576 | $11.70 | $11.99 | $12.75 | $10.00 |
| 0060 | Temporary signalization and maintenance, intersection (0102-104) | ED | 2,380 | $17.25 | $31.93 | $17.00 | $25.00 |
| 0065 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 2,380 | $9.20 | $24.83 | $9.00 | $21.00 |
| 0070 | Type III barricade (0102-115) | ED | 952 | $0.35 | $0.38 | $0.50 | $0.20 |
| 0075 | Removable tape, white, 12" crosswalk (0102-913-24) | LF | 3,150 | $5.15 | $11.23 | $5.25 | $6.00 |
| 0080 | Sediment barrier (0104-10-3) | LF | 7,733 | $2.95 | $2.28 | $8.50 | $0.01 |
| 0085 | Inlet protection system (0104-18) | EACH | 124 | $107.90 | $188.09 | $131.75 | $200.00 |
| 0090 | Litter removal (0107-1) | ACRE | 14.51 | $287.40 | $279.16 | $1,000.00 | $80.00 |
| 0095 | Mowing (0107-2) | ACRE | 8.13 | $1,440.00 | $375.89 | $2,000.00 | $200.00 |
| 0100 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $1,310.00 | $59,483 | $4,500.00 | $0.01 |
| 0105 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $875.00 | $17,868 | $4,500.00 | $0.01 |
| 0110 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $89,400 | $294,783 | $90,000 | $300,000 |
| 0115 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $59,690 | $98,643 | $19,000 | $300,000 |
| 0120 | Removal of existing concrete (0110-4-10) | SY | 5,943 | $15.50 | $39.70 | $55.75 | $35.00 |
| 0125 | Tree root and branch pruning (0110-22) | EACH | 1 | $5,750.00 | $5,877.85 | $5,700.00 | $4,000.00 |
| 0130 | Type B stabilization (0160-4) | SY | 832 | $28.30 | $33.75 | $32.00 | $0.01 |
| 0135 | Optional base, base group 09 (0285-709) | SY | 706 | $50.00 | $56.42 | $112.00 | $117.00 |
| 0140 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 1,971 | $7.80 | $6.25 | $7.80 | $9.00 |
| 0145 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 118,018 | $2.50 | $2.98 | $4.00 | $2.80 |
| 0150 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 385.10 | $249.60 | $250.17 | $330.00 | $195.00 |
| 0155 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 9,991.10 | $177.80 | $188.92 | $206.00 | $205.00 |
| 0160 | Miscellaneous asphalt (0339-1) | TN | 6.80 | $382.50 | $777.77 | $1,160.00 | $700.00 |
| 0165 | Plain cement concrete 6" (0350-3-1) | SY | 140 | $93.60 | $161.21 | $266.00 | $73.00 |
| 0170 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 1.20 | $3,370.00 | $3,829.55 | $2,320.00 | $2,500.00 |
| 0175 | Manhole, adjust (0425-5) | EACH | 79 | $100.00 | $917.67 | $930.00 | $950.00 |
| 0180 | Valve boxes, adjust (0425-6) | EACH | 2 | $100.00 | $859.66 | $930.00 | $950.00 |
| 0185 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 304 | $215.90 | $334.46 | $208.00 | $210.00 |
| 0190 | Cleaning & sealing existing pipe joint, 15" storm sewer (0430-821-23) | EACH | 6 | $2,070.00 | $740.19 | $2,800.00 | $950.00 |
| 0195 | Cleaning & sealing existing pipe joint, 18" storm sewer (0430-821-25) | EACH | 6 | $2,180.00 | $468.67 | $3,000.00 | $1,000.00 |
| 0200 | PVC pipe for back of sidewalk, (0430-963-1) | LF | 36 | $121.00 | $95.65 | $92.00 | $95.00 |
| 0205 | Mitered end sect, replace (0430-990) | EACH | 2 | $7,470.00 | $1,502.10 | $3,000.00 | $3,100.00 |
| 0210 | Pipe liner, cured in place, 18" (0431-1118) | LF | 404 | $201.40 | $146.22 | $310.00 | $212.00 |
| 0215 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 138 | $68.10 | $55.25 | $54.00 | $60.00 |
| 0220 | Pedestrian/ bicycle railing, aluminum only,42" type 1 (0515-2311) | LF | 128 | $185.20 | $111.68 | $109.00 | $162.00 |
| 0225 | Concrete curb & gutter, type F (0520-1-10) | LF | 5,505 | $46.40 | $65.11 | $73.00 | $33.00 |
| 0230 | Concrete curb, type D (0520-2-4) | LF | 154 | $33.35 | $28.53 | $56.00 | $30.00 |
| 0235 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 2,479 | $86.20 | $71.79 | $72.00 | $70.00 |
| 0240 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 2,159 | $189.40 | $100.23 | $98.50 | $162.00 |
| 0245 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 3 | $402.50 | $1,211.77 | $463.00 | $45.00 |
| 0250 | Detectable warnings (0527-2) | SF | 1,614 | $50.60 | $40.92 | $58.00 | $45.00 |
| 0255 | Guardrail -roadway, general (0536-1-1) | LF | 228 | $29.65 | $24.69 | $24.00 | $26.00 |
| 0260 | Pipe rail for guardrail (0536-6) | LF | 289 | $25.30 | $24.69 | $24.00 | $22.00 |
| 0265 | Guardrail removal (0536-73) | LF | 221 | $2.85 | $4.82 | $3.50 | $2.50 |
| 0270 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $1,740.00 | $1,904.43 | $1,850.00 | $1,600.00 |
| 0275 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $4,010.00 | $4,643.51 | $4,500.00 | $3,400.00 |
| 0280 | Performance turf, sod (0570-1-2) | SY | 2,263 | $20.05 | $5.48 | $21.00 | $9.00 |
| 0285 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 6.63 | $0.01 | $1,514.21 | $2,000.00 | $1,500.00 |
| 0290 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 24 | $0.01 | $1.62 | $2.30 | $3.00 |
| 0295 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 3.33 | $0.01 | $405.37 | $560.00 | $800.00 |
| 0300 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 1.35 | $0.01 | $405.37 | $790.00 | $800.00 |
| 0305 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 89 | $0.01 | $37.42 | $40.00 | $45.00 |
| 0310 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 4.33 | $0.01 | $1,514.71 | $2,000.00 | $1,500.00 |
| 0315 | Temporary portable access surfaces and curb ramps (0922-102-40) | ED | 10,255 | $0.01 | $1.18 | $2.00 | $0.01 |
| 0320 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0325 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $27,845 | $27,845 | $27,845 | $27,845 |
| 0330 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $22,155 | $22,155 | $22,155 | $22,155 |
| 0335 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 94 | $603.50 | $617.18 | $520.00 | $525.00 |
| 0340 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 51 | $1,720.00 | $1,880.91 | $1,650.00 | $1,500.00 |
| 0345 | Single column ground sign assembly, remove (0700-1600) | EACH | 119 | $57.50 | $29.39 | $57.00 | $50.00 |
| 0350 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 1 | $6,270.00 | $7,993.88 | $4,750.00 | $5,500.00 |
| 0355 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 3 | $7,870.00 | $8,111.43 | $5,400.00 | $6,700.00 |
| 0360 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 1 | $10,900 | $13,519 | $8,700.00 | $9,500.00 |
| 0365 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 5 | $1,350.00 | $1,469.46 | $1,100.00 | $1,100.00 |
| 0370 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 1 | $357.50 | $411.45 | $265.00 | $310.00 |
| 0375 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 1 | $1,050.00 | $822.90 | $2,600.00 | $2,000.00 |
| 0380 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $126.40 | $58.78 | $57.00 | $110.00 |
| 0385 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 19 | $168.90 | $117.56 | $85.00 | $145.00 |
| 0390 | Object marker, type 1 (0705-10-1) | EACH | 16 | $402.50 | $205.72 | $235.00 | $350.00 |
| 0395 | Raised pavement marker, type B (0706-1-3) | EACH | 2,218 | $4.30 | $5.61 | $4.25 | $5.00 |
| 0400 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 25 | $4.60 | $8.73 | $4.50 | $10.00 |
| 0405 | Painted pavement markings, surface (0710-90) | LS | 1 | $32,100 | $15,747 | $32,000 | $25,000 |
| 0410 | Painted pavement markings, surface (0710-90) | LS | 1 | $21,300 | $26,817 | $21,500 | $15,000 |
| 0415 | Thermoplastic, standard, solid, 12" for interchange markings (0711-11103) | GM | 0.13 | $10,900 | $14,489 | $10,000 | $11,500 |
| 0420 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,421 | $3.60 | $2.74 | $3.75 | $5.00 |
| 0425 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 64 | $5.45 | $4.99 | $5.50 | $7.00 |
| 0430 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 1,194 | $7.25 | $7.48 | $7.30 | $9.00 |
| 0435 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 1.35 | $2,870.00 | $2,868.78 | $2,900.00 | $4,400.00 |
| 0440 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 42 | $86.20 | $137.20 | $86.00 | $250.00 |
| 0445 | Thermoplastic, standard, arrow (0711-11170) | EACH | 138 | $64.40 | $112.26 | $65.00 | $90.00 |
| 0450 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 109 | $5.10 | $4.99 | $5.00 | $7.00 |
| 0455 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.35 | $2,810.00 | $2,868.78 | $2,800.00 | $4,300.00 |
| 0460 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,748 | $19.05 | $22.45 | $19.25 | $20.00 |
| 0465 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 36 | $341.50 | $343.01 | $340.00 | $300.00 |
| 0470 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 6.63 | $5,550.00 | $7,733.23 | $5,600.00 | $5,800.00 |
| 0475 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.08 | $6,730.00 | $7,982.69 | $6,800.00 | $5,900.00 |
| 0480 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 8.28 | $1,390.00 | $2,868.78 | $1,400.00 | $4,400.00 |
| 0485 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.07 | $2,490.00 | $3,622.14 | $2,500.00 | $7,100.00 |
| 0490 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 4.33 | $5,200.00 | $7,733.23 | $5,250.00 | $5,800.00 |
| 0495 | Green-colored pavement markings, bike lane (0714-10) | SF | 3,500 | $9.20 | $10.42 | $9.25 | $13.50 |
| 0500 | Conduit, furnish & install, open trench (0630-2-11) | LF | 388 | $22.70 | $29.56 | $23.00 | $25.00 |
| 0505 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 139 | $32.75 | $29.86 | $33.00 | $25.00 |
| 0510 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 65 | $2,440.00 | $1,467.53 | $2,500.00 | $1,200.00 |
| 0515 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 2 | $6,870.00 | $25,304 | $7,000.00 | $21,500 |
| 0520 | Electrical power service, remove underground (0639-1620) | AS | 2 | $832.00 | $1,040.52 | $830.00 | $880.00 |
| 0525 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 2,339 | $2.55 | $3.61 | $2.50 | $3.00 |
| 0530 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 2,329 | $2.85 | $6.62 | $2.90 | $6.00 |
| 0535 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 509 | $0.45 | $1.77 | $0.50 | $1.50 |
| 0540 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 16 | $1,850.00 | $1,773.61 | $1,850.00 | $1,500.00 |
| 0545 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pole top (0715-11213) | EACH | 4 | $1,840.00 | $1,773.61 | $1,870.00 | $1,500.00 |
| 0550 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 12' arm length (0715-61142) | EACH | 1 | $11,200 | $12,448 | $11,350 | $7,800.00 |
| 0555 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 12' arm length (0715-61242) | EACH | 3 | $11,500 | $12,803 | $11,600 | $8,200.00 |
| 0560 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 0' arm length (0715-61400) | EACH | 2 | $13,000 | $14,793 | $13,000 | $9,200.00 |
| 0565 | Light pole complete, F&I, utility conflict pole standard foundation, 30' mounting height, 16' arm length (0715-65166) | EACH | 2 | $12,700 | $13,749 | $12,800 | $8,900.00 |
| 0570 | Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266) | EACH | 1 | $13,200 | $14,340 | $13,400 | $9,500.00 |
| 0575 | Light pole complete, F&I, utility conflict pole standard foundation, 40' mounting height, 16' arm length (0715-65366) | EACH | 1 | $13,700 | $15,579 | $13,900 | $9,800.00 |
| 0580 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 1 | $1,430.00 | $3,405.34 | $1,450.00 | $2,900.00 |
| 0585 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 27 | $1,250.00 | $1,040.52 | $1,250.00 | $900.00 |
| 0590 | Conduit, furnish & install, open trench (0630-2-11) | LF | 276 | $26.45 | $21.28 | $26.75 | $17.00 |
| 0595 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,493 | $37.95 | $41.39 | $38.00 | $34.00 |
| 0600 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 4 | $13,900 | $14,898 | $14,000 | $12,000 |
| 0605 | Signal cable, remove- intersection (0632-7-6) | PI | 4 | $2,820.00 | $4,907.00 | $2,800.00 | $4,000.00 |
| 0610 | Fiber optic cable locator (0633-6) | DA | 476 | $82.80 | $532.08 | $83.00 | $430.00 |
| 0615 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 51 | $2,010.00 | $1,486.74 | $2,000.00 | $1,200.00 |
| 0620 | Aluminum signals pole, (0646-1-11) | EACH | 24 | $3,610.00 | $2,926.46 | $3,600.00 | $2,400.00 |
| 0625 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 4 | $1,430.00 | $2,778.67 | $1,450.00 | $2,300.00 |
| 0630 | Aluminum signals pole, remove (0646-1-60) | EACH | 6 | $665.50 | $555.73 | $670.00 | $450.00 |
| 0635 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 5 | $2,470.00 | $2,069.21 | $2,500.00 | $1,700.00 |
| 0640 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 1 | $332.00 | $354.73 | $330.00 | $285.00 |
| 0645 | Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70) | AS | 6 | $1,210.00 | $1,389.33 | $1,200.00 | $1,100.00 |
| 0650 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- black with reflect border (0650-2102) | EACH | 8 | $584.00 | $945.92 | $590.00 | $765.00 |
| 0655 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 17 | $584.00 | $945.92 | $590.00 | $770.00 |
| 0660 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 20 | $1,230.00 | $1,478.01 | $1,250.00 | $1,200.00 |
| 0665 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 4 | $2,530.00 | $2,542.18 | $2,500.00 | $2,100.00 |
| 0670 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 22 | $82.80 | $307.43 | $83.00 | $250.00 |
| 0675 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 28 | $370.00 | $277.87 | $370.00 | $225.00 |
| 0680 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 22 | $41.65 | $118.25 | $42.00 | $100.00 |
| 0685 | Traffic controller, modify (0671-2-40) | EACH | 4 | $3,680.00 | $1,182.41 | $3,700.00 | $1,000.00 |
| 0690 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 1 | $7,280.00 | $5,019.33 | $7,300.00 | $4,000.00 |
| 0695 | Internally illuminated sign, remove (0700-5-60) | EACH | 1 | $332.00 | $396.11 | $330.00 | $320.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.