FDOT contract T5845 bid tabulation

SR 9/400 (I-95 / I-4) AT SR 400 (I-4 / US 92) INTERCHANGES. Let by Florida DOT on January 29, 2025, Dist/St-Wide, Volusia, District 5. 5 bids received; low bid $2,046,788 by Sice Inc.

Owner
Florida DOT
Letting
29 JAN 2025
Pay items
79
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Sice Inc$2,046,788Low
2Chinchor Electric Inc.$2,200,000+7.0%
3Traffic Control Devices, Inc.$2,339,000+14%
4Highway Safety Devices, Inc.$2,656,095+30%
5New Era Electric Inc$2,860,272+40%
FDOT contract T5845: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sice Inc2. Chinchor Electric Inc.3. Traffic Control Devices, Inc.4. Highway Safety Devices, Inc.5. New Era Electric Inc
0005Mobilization (0101-1)LS1$204,426$132,943$200,000$260,470$187,121
0010Maintenance of traffic (0102-1)DA1$89,773$79,143$63,225$75,000$268,168
0015Traffic control officer (0102-14)HR400$108.30$170.26$120.00$135.00$120.00
0020Work zone sign (0102-60)ED2,355$0.25$0.31$0.25$0.30$0.16
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED5,750$0.13$0.12$0.13$0.15$0.80
0030Arrow board / advance warning arrow panel (0102-76)ED190$6.02$5.49$6.05$7.90$6.50
0035Portable changeable message sign, temporary (0102-99)ED155$11.43$10.98$11.50$19.00$950.00
0040Temporary signalization and maintenance, intersection (0102-104)ED160$25.99$16.48$80.00$50.00$170.00
0045Temporary traffic detection and maintenance, intersection (0102-107-1)ED160$25.99$16.48$80.00$50.00$50.00
0050Type III barricade (0102-115)ED190$0.31$0.31$0.30$0.45$1.50
0055Removal of existing concrete (0110-4-10)SY8$601.68$329.53$270.00$185.00$65.00
0060Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000
0065Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH48$632.38$577.25$620.00$730.00$650.00
0070Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH2$2,645.55$2,414.89$2,785.00$2,550.00$2,887.75
0075Single column ground sign assembly, F&I barrier less than 12 SF (0700-1211)EACH3$2,754.72$2,514.54$3,980.00$4,400.00$2,379.00
0080Single column ground sign assembly, F&I barrier less than 12 SF (0700-1311)EACH1$3,409.87$3,112.57$5,470.00$4,250.00$3,486.55
0085Single column ground sign assembly, relocate (0700-1500)EACH5$481.35$439.38$310.00$450.00$313.15
0090Single column ground sign assembly, remove (0700-1600)EACH14$60.17$54.92$205.00$180.00$89.35
0095Sign panel, furnish & install overhead mount, 51-100 SF (0700-3205)EACH1$5,772.90$5,269.57$4,025.00$4,750.00$5,611.15
0100Retroreflective sign strip- furnish and install, 2' (0700-13-12)EACH52$96.27$87.88$85.00$180.00$110.00
0105Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH24$168.47$153.78$190.00$180.00$140.00
0110Enhanced highway sign AC powered, F&I ground mount, highlighted sign <12 SF (0700-141140)EACH22$6,905.95$9,389.39$9,580.00$10,500$9,500.00
0115Enhanced highway sign solar powered, F&I ground mount, W/eds, UP to 12 SF of static sign panels (0700-142131)EACH1$11,470$11,714$10,665$12,200$16,066
0120Raised pavement marker, type B (0706-1-3)EACH658$24.07$10.98$25.00$31.50$5.50
0125Thermoplastic, standard, message or symbol (0711-11160)EACH1$601.68$549.22$600.25$790.00$450.00
0130Thermoplastic, standard, arrow (0711-11170)EACH48$240.67$1,757.52$240.00$315.00$575.35
0135Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.02$18,051$10,984$18,095$23,700$3,125.00
0140Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF96$60.17$109.84$60.00$79.00$5.20
0145Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH1$18,813$22,906$19,730$23,600$24,481
0150Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH3$9,469.13$16,098$9,935.00$12,300$19,223
0155Vehicle detection system- remove above ground (0660-4-62)EACH3$693.14$1,098.45$750.00$390.00$1,223.55
0160Pedestrian detector, relocate (0665-1-40)EACH2$757.52$384.46$240.00$195.00$322.95
0165Traffic controller assembly, F&I, NEMA, 1 preemption (0670-5111)AS1$42,192$45,869$42,700$53,700$58,007
0170Traffic controller assembly, remove controller with (0670-5600)AS1$2,243.08$3,734.73$935.00$885.00$975.00
0175ITS CCTV camera, F&I, dome enclosure - non-pressurized, high definition (0682-1133)EACH1$5,306.63$6,892.77$8,280.00$8,150.00$6,711.00
0180ITS CCTV camera, remove & disposal (0682-1600)EACH1$693.14$933.68$590.00$575.00$646.25
0185Managed field ethernet switch, furnish & install (0684-1-1)EACH1$2,552.38$6,330.35$3,180.00$3,300.00$6,250.70
0190Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH1$9,113.35$15,020$14,320$7,850.00$13,323
0195Itsfm subsurface documentation- project length (0611-1-1)MI3.62$3,459.69$3,844.57$2,381.94$4,550.00$2,603.50
0200Itsfm location documentation- intersection (0611-2-1)EACH1$2,725.63$2,927.37$1,585.00$3,600.00$2,164.00
0205Itsfm location documentation- ITS site (0611-2-2)EACH6$1,955.48$1,675.13$1,585.00$2,550.00$1,650.00
0210Conduit, furnish & install, open trench (0630-2-11)LF7,408$15.12$25.48$30.00$23.00$27.35
0215Conduit, furnish & install, directional bore (0630-2-12)LF3,023$35.84$34.09$31.00$50.50$57.60
0220Conduit, furnish & install, aboveground (0630-2-14)LF126$60.17$37.77$45.00$52.00$48.25
0225Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$10,845$15,322$10,000$8,550.00$12,503
0230Signal cable, remove- intersection (0632-7-6)PI1$3,119.13$3,295.35$2,900.00$1,750.00$1,910.50
0235Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF12,435$3.91$3.31$3.25$5.30$4.60
0240Fiber optic cable, relocate, underground (0633-1420)LF300$3.61$3.33$3.50$4.70$20.00
0245Fiber optic cable, remove, underground (0633-1620)LF1,140$1.20$1.71$1.50$1.60$1.00
0250Fiber optic connection, install, splice (0633-2-31)EACH296$54.15$46.96$63.00$71.00$55.00
0255Fiber optic connection hardware, F&I, splice (0633-3-11)EACH3$1,263.54$1,482.91$1,470.00$1,650.00$1,554.10
0260Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH25$60.17$75.79$55.00$79.00$56.00
0265Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH4$54.15$43.94$49.00$71.00$37.50
0270Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15)EACH19$1,624.55$1,202.80$1,260.00$2,150.00$2,100.00
0275Fiber optic cable locator (0633-6)DA160$346.57$197.72$225.00$400.00$281.50
0280Multi-conductor cable, furnish & install, cat 6 (0633-8-11)LF15$7.22$6.37$3.75$10.00$4.70
0285Multi-conductor cable, furnish & install, composite (0633-8-12)LF6,119$5.42$7.55$5.00$5.70$8.00
0290Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH79$1,684.72$1,516.82$1,165.00$2,000.00$1,750.00
0295Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH18$2,864.02$2,590.98$3,150.00$3,650.00$2,570.00
0300Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13)EACH7$7,154.03$5,056.22$6,490.00$7,450.00$4,500.00
0305Electrical power service, F&I, underground, meter by contractor (0639-1122)AS3$5,571.00$7,731.62$8,230.00$10,100$4,910.00
0310Electrical power service, remove overhead (0639-1610)AS1$693.14$1,757.52$1,250.00$1,050.00$1,105.20
0315Electrical power service, remove underground (0639-1620)AS1$462.09$1,318.14$960.00$1,050.00$929.00
0320Electrical service wire, & install (0639-2-1)LF8,550$5.91$5.49$7.50$12.00$13.05
0325Electrical service wire, (0639-2-6)LF555$1.20$0.55$1.50$2.00$2.30
0330Electrical service disconnect, F&I, pole mount (0639-3-11)EACH7$1,787.61$2,914.25$2,700.00$2,200.00$2,819.50
0335Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121)EACH11$1,948.56$3,873.13$2,800.00$2,950.00$5,200.00
0340Prestressed concrete pole, type P-II service pole (0641-2-12)EACH10$3,446.64$2,391.22$2,800.00$3,300.00$3,215.00
0345Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH2$2,406.74$1,318.14$380.00$590.00$975.00
0350Vehicle detection system- wrong way for exit ramp, 1 or 2 lanes, AC powered (0660-7-21)EACH6$46,221$43,675$70,790$53,200$53,150
0355Vehicle detection system- wrong way for exit ramp, 3 or more lanes, AC powered (0660-7-22)EACH1$46,221$43,675$70,790$53,200$56,637
0360ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122)EACH6$8,662.20$10,485$7,960.00$12,300$9,340.95
0365ITS cabinet- adjust/modify (0676-2500)EACH2$757.52$3,437.81$2,350.00$760.00$2,533.00
0370ITS cabinet- remove (0676-2600)EACH1$1,039.71$2,196.90$2,350.00$690.00$929.45
0375Media converter, furnish & install (0684-5-1)EACH2$958.18$1,043.53$980.00$1,450.00$1,131.10
0380Managed hub ethernet switch, furnish & install (0684-7-1)EACH6$4,284.36$4,695.87$4,960.00$8,550.00$5,500.00
0385Managed hub ethernet switch, install (0684-7-3)EACH1$563.18$933.68$2,320.00$3,850.00$3,800.00
0390Uninterruptible power supply, furnish and install, online/double conversion (0685-1-12)EACH6$2,598.23$6,117.64$4,980.00$10,900$6,890.40
0395Remote power management rpmu, furnish and install (0685-2-1)EACH7$860.32$688.65$820.00$1,350.00$1,221.50
FDOT contract T5845: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy