RankBidderTotal bidAgainst the low bid
1Anderson Columbia Co., Inc.$14,193,258Low
2Superior Asphalt, Inc.$14,218,0010.0%
3C.W. Roberts Contracting, Inc.$14,649,237+3.0%
4Preferred Materials Inc.$15,464,299+9.0%
5Whitehurst, V. E. & Sons, Inc.$16,159,605+14%
FDOT contract T5847: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Anderson Columbia Co., Inc.2. Superior Asphalt, Inc.3. C.W. Roberts Contracting, Inc.4. Preferred Materials Inc.5. Whitehurst, V. E. & Sons, Inc.
0005Mobilization (0101-1)LS1$536,227$353,000$658,086$623,667$930,270
0010Mobilization (0101-1)LS1$470,555$433,390$609,335$79,062$857,000
0015Maintenance of traffic (0102-1)DA1$153,157$458,525$514,076$426,832$650,850
0020Maintenance of traffic (0102-1)DA1$169,789$488,550$489,597$315,304$682,000
0025Pedestrian or bicycle special detour (0102-4-1)SY1$109,611$19,040$17,000$37,594$30,000
0030Traffic control officer (0102-14)HR5,328$124.74$45.00$90.00$100.00$125.00
0035Work zone sign (0102-60)ED55,960$0.24$0.25$0.25$0.26$0.24
0040Temporary barrier, F&I, anchored (0102-71-15)LF1,005$46.33$48.50$45.00$42.80$45.15
0045Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED145,828$0.11$0.10$0.10$0.12$0.09
0050Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD3,012$0.08$0.10$0.10$0.06$0.18
0055Arrow board / advance warning arrow panel (0102-76)ED3,485$5.94$5.40$5.60$6.68$4.57
0060Temporary crash cushion, redirective option (0102-89-1)LO1$1,425.65$1,295.00$4,200.00$1,200.00$1,128.75
0065Portable changeable message sign, temporary (0102-99)ED2,432$10.69$9.75$10.00$11.34$10.50
0070Temporary signalization and maintenance, intersection (0102-104)ED580$35.58$45.00$22.00$100.00$27.50
0075Temporary traffic detection and maintenance, intersection (0102-107-1)ED580$35.58$1.00$22.00$16.09$17.30
0080Type III barricade (0102-115)ED2,320$0.30$0.28$0.30$0.33$0.30
0085Portable regulatory, sign (0102-150-1)ED1,780$5.35$5.04$5.00$6.07$4.57
0090Radar speed display unit (0102-150-2)ED1,780$5.35$5.04$5.00$6.74$4.57
0095Removable tape, yellow, solid, (0102-913-31)GM1.76$19,603$14,040$13,000$11,500$17,738
0100Sediment barrier (0104-10-3)LF2,743$5.82$1.20$7.50$3.60$2.00
0105Inlet protection system (0104-18)EACH63$178.21$135.00$285.00$140.00$125.00
0110Litter removal (0107-1)ACRE1,215.88$41.58$49.85$25.00$69.19$80.65
0115Mowing (0107-2)ACRE1,157.86$77.22$167.75$70.00$141.90$145.15
0120Clearing & grubbing (0110-1-1)ACRE1$162,416$70,200$239,337$71,128$95,951
0125Clearing & grubbing (0110-1-1)ACRE1$159,505$61,340$190,862$66,128$83,000
0130Removal of existing concrete (0110-4-10)SY337$106.43$25.10$77.00$26.00$58.05
0135Mailbox, F&I single (0110-7-1)EACH7$326.71$346.62$740.00$350.00$300.00
0140Regular excavation (0120-1)CY3,291.70$56.26$34.20$40.50$36.92$20.00
0145Subsoil excavation (0120-4)CY1,337.60$52.17$22.95$77.50$38.51$40.00
0150Embankment (0120-6)CY4,892.70$44.40$31.00$58.00$67.95$25.00
0155Type B stabilization (0160-4)SY4,562$16.00$16.50$16.00$18.61$20.00
0160Optional base, base group 01 (0285-701)SY1,202$11.47$13.50$24.40$15.66$18.95
0165Optional base, base group 06 (0285-706)SY320$27.47$21.35$47.35$38.80$26.90
0170Optional base, base group 09 (0285-709)SY1,987$24.09$24.60$32.00$35.09$29.50
0175Turnout construction- asphalt/driveway base- asphalt material (0286-2)TN593.30$467.69$304.15$343.50$377.84$175.00
0180Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY12,775$4.95$5.80$3.90$5.39$4.20
0185Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY262$11.81$8.05$10.35$22.32$3.85
0190Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11)SY33,245$6.71$5.75$6.70$4.02$3.35
0195Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15)SY48,391$4.70$4.25$3.65$4.49$3.65
0200Milling existing asphalt pavement, 3 1/4" avg depth (0327-70-17)SY82,823$4.33$3.80$3.75$5.24$4.05
0205Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20)SY46,415$4.62$4.70$4.10$5.38$4.40
0210Superpave asphaltic conc, traffic C (0334-1-13)TN35,777.40$140.54$159.95$142.25$161.33$157.60
0215Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25)TN7,979.40$195.35$249.00$214.00$281.24$219.00
0220Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN1,054.70$170.08$194.55$175.00$222.80$166.00
0225Inlets, curb, type P-1, <10' (0425-1311)EACH5$7,722.31$7,020.00$10,725$12,850$13,814
0230Inlets, DT bot, type D, <10' (0425-1541)EACH12$6,653.06$6,050.00$6,250.00$13,950$14,997
0235Inlets, DT bot, type F, <10' (0425-1561)EACH2$6,890.68$6,265.00$6,600.00$13,360$14,362
0240Inlets, gutter, type S, <10' (0425-1701)EACH3$6,771.87$6,155.00$7,200.00$18,250$19,619
0245Manholes, P-8, <10' (0425-2-61)EACH1$6,534.26$5,940.00$16,000$27,944$30,040
0250Manhole, adjust (0425-5)EACH5$1,603.86$1,460.00$1,000.00$1,895.00$2,037.00
0255Pipe culvert, optional material, round, 18"SD (0430-174118)LF67$177.02$128.50$156.50$265.00$285.00
0260Pipe culvert, optional material, round, 24"SD (0430-174124)LF30$211.47$159.85$180.00$315.00$339.00
0265Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF1,464$147.32$101.50$100.00$265.00$285.00
0270Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF8$295.83$236.50$800.00$695.00$748.00
0275Pipe culvert,optional material,other-elip/arch, (0430-175218)LF143$169.89$122.00$140.00$525.00$565.00
0280Mitered end section, optional round, 18" CD (0430-982125)EACH1$2,970.13$2,268.00$3,750.00$3,415.00$3,671.00
0285Mitered end section, optional round, 18" SD (0430-984125)EACH8$3,564.15$2,511.00$3,750.00$2,900.00$3,118.00
0290Mitered end section, optional round, 24" SD (0430-984129)EACH2$3,534.45$2,675.00$4,250.00$3,250.00$3,494.00
0295Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH2$3,534.45$2,675.00$4,675.00$3,175.00$3,413.00
0300Concrete curb & gutter, type E (0520-1-7)LF471$65.18$44.30$44.00$92.00$99.00
0305Concrete curb & gutter, type F (0520-1-10)LF1,041$59.30$55.05$75.00$84.00$90.30
0310Traffic separator concrete- type I, 4' wide (0520-5-11)LF43$203.15$129.60$230.00$180.00$193.50
0315Shoulder gutter- concrete (0520-6)LF560$78.99$46.45$50.00$99.00$106.50
0320Concrete sidewalk and driveways, 4" thick (0522-1)SY360$120.43$83.15$142.00$114.00$122.50
0325Concrete sidewalk and driveways, 6" thick (0522-2)SY267$124.07$95.00$213.50$160.00$172.00
0330Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY188$153.65$114.50$277.50$225.00$242.00
0335Detectable warnings (0527-2)SF465$77.22$23.00$33.50$48.00$51.60
0340Performance turf, sod (0570-1-2)SY71,492$5.97$4.75$4.75$3.17$2.70
0345Conduit, furnish & install, open trench (0630-2-11)LF120$31.01$37.60$38.00$16.54$17.80
0350Conduit, furnish & install, directional bore (0630-2-12)LF137$34.07$49.35$50.00$40.08$43.10
0355Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$2,240.96$1,425.00$1,400.00$1,566.25$1,683.75
0360Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH12$2,907.09$2,555.00$2,600.00$2,605.48$2,800.00
0365Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH12$2,517.54$2,100.00$2,100.00$2,523.19$2,712.50
0370Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH2$9,786.62$7,275.00$7,500.00$7,407.82$7,964.00
0375Traffic monitoring site cabinet, remove existing cabinet (0695-7600)EACH2$1,116.87$1,490.00$1,500.00$1,340.70$1,441.25
0380Raised pavement marker, type B (0706-1-3)EACH4,217$6.12$5.40$4.50$5.50$5.55
0385Painted pavement markings, standard, white, solid, 6" (0710-11101)GM11.41$2,138.49$1,188.00$1,475.00$1,755.00$1,935.00
0390Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF619$2.38$2.15$1.15$2.50$2.15
0395Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF279$3.56$2.70$2.20$3.00$3.23
0400Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM11.44$1,128.65$540.00$725.00$465.00$1,021.25
0405Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM7.79$2,138.49$1,188.00$1,475.00$1,755.00$1,935.00
0410Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM2.01$1,366.25$648.00$722.50$815.00$1,237.00
0415Initial contingency amount, DO not bid (0999-25)LS1$74,000$74,000$74,000$74,000$74,000
0420Initial contingency amount, DO not bid (0999-25)LS1$75,000$75,000$75,000$75,000$75,000
0425Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM18.98$2,494.90$1,242.00$1,560.00$1,750.00$2,365.00
0430Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH56$1,201.23$476.30$490.00$441.00$697.00
0435Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH6$1,777.44$1,910.00$1,975.00$1,766.00$2,615.50
0440Single column ground sign assembly, remove (0700-1600)EACH18$279.22$54.00$55.00$50.00$53.75
0445Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH3$8,250.77$5,860.00$6,000.00$5,426.00$9,264.00
0450Multi-column ground sign assembly, remove (0700-2600)EACH7$1,396.09$1,190.00$1,225.00$1,100.00$210.00
0455Sign panel, relocate, UP to 12 SF (0700-3501)EACH8$459.91$162.00$165.00$150.00$88.15
0460Sign panel, remove, UP to 12 SF (0700-3601)EACH2$139.61$32.40$33.50$30.00$32.25
0465Enhanced highway sign AC powered, remove - ground mount (0700-141902)EACH1$1,675.31$865.00$895.00$800.00$731.00
0470Enhanced highway sign solar powered, F&I ground mount, W/beacon, UP to 12 SF of static sign panels (0700-142111)EACH1$15,856$8,125.00$8,395.00$7,521.00$9,971.00
0475Enhanced highway sign solar powered, F&I ground mount, highlighted sign <12 SF (0700-142140)EACH4$14,739$8,830.00$9,125.00$8,177.00$8,690.00
0480Tubular marker, 36" yellow (0704-1-4)EACH83$267.31$243.00$285.00$225.00$209.00
0485Object marker, type 1 (0705-10-1)EACH1$1,188.05$226.80$235.00$210.00$303.00
0490Raised pavement marker, type B (0706-1-3)EACH5,232$6.24$5.40$4.50$5.50$5.65
0495Painted pavement markings, surface (0710-90)LS1$40,394$37,800$25,000$41,500$36,550
0500Painted pavement markings, surface (0710-90)LS1$40,394$37,800$25,000$41,500$36,550
0505Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,162$5.35$5.40$5.00$4.00$4.85
0510Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF466$6.53$6.50$8.70$6.00$5.91
0515Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF441$10.39$7.55$11.60$10.00$9.41
0520Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.24$3,267.12$4,320.00$1,900.00$3,300.00$2,956.25
0525Thermoplastic, standard, message or symbol (0711-11160)EACH1$386.11$324.00$360.00$195.00$349.40
0530Thermoplastic, standard, arrow (0711-11170)EACH49$130.69$86.40$110.00$150.00$118.25
0535Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF480$6.53$6.50$6.50$6.00$5.91
0540Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM2.04$3,267.13$4,320.00$1,900.00$3,300.00$2,956.25
0545Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101)GM11.51$7,383.72$7,560.00$7,600.00$4,500.00$6,682.00
0550Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102)GM0.19$11,631$9,720.00$9,475.00$22,000$10,525
0555Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131)GM11.44$2,316.69$2,376.00$1,900.00$1,540.00$2,097.00
0560Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201)GM9.66$7,383.72$7,560.00$7,600.00$4,500.00$6,682.00
0565Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.76$6,534.26$7,560.00$5,800.00$3,650.00$5,913.00
0570Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.80$2,079.08$2,376.00$1,450.00$1,300.00$1,882.00
0575Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.92$6,534.26$7,560.00$5,800.00$3,650.00$5,913.00
0580Conduit, furnish & install, open trench (0630-2-11)LF13$15.62$31.00$32.00$16.54$17.80
0585Conduit, furnish & install, directional bore (0630-2-12)LF310$20.96$38.25$39.50$40.08$43.10
0590Conduit, furnish & install, aboveground (0630-2-14)LF60$70.10$79.00$81.50$42.00$45.15
0595Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$1,733.69$2,535.00$2,600.00$1,566.25$1,684.00
0600Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31)EACH5$1,949.26$2,255.00$2,300.00$4,845.51$5,209.00
0605Itsfm location documentation- intersection (0611-2-1)EACH1$3,324.70$1,935.00$2,000.00$2,636.93$2,834.70
0610Conduit, furnish & install, open trench (0630-2-11)LF144$22.86$22.00$23.00$16.54$17.80
0615Conduit, furnish & install, directional bore (0630-2-12)LF310$31.91$38.25$39.50$40.08$43.10
0620Conduit, furnish & install, aboveground (0630-2-14)LF90$70.10$79.00$81.50$42.00$45.15
0625Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$12,109$14,430$14,900$12,193$13,110
0630Span wire assembly, F&I, two point, diagonal (0634-4152)PI1$13,921$5,610.00$5,795.00$7,608.59$8,180.00
0635Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$2,090.15$1,425.00$1,473.00$1,566.25$1,684.00
0640Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$5,464.77$6,695.00$6,900.00$5,188.72$5,578.00
0645Electrical service wire, & install (0639-2-1)LF131$6.91$9.25$9.50$9.90$10.65
0650Electrical service disconnect, F&I, pole mount (0639-3-11)EACH1$2,908.56$2,160.00$2,225.00$2,706.72$2,910.00
0655Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,433.24$3,065.00$3,100.00$2,592.82$2,788.00
0660Prestressed concrete pole, type P-VIII (0641-2-18)EACH2$24,899$36,850$38,000$29,924$32,169
0665Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH2$18,736$15,195$15,700$8,233.43$8,851.00
0670Vehicular traffic signal, furnish & install aluminum, 1 section, 1 way (0650-1-11)AS4$1,906.22$1,750.00$1,800.00$1,116.68$1,200.50
0675Vehicular traffic signal, furnish & install aluminum, 1 section, 2-4 way (0650-1-12)AS2$2,920.65$2,420.00$2,475.00$2,970.00$3,193.00
0680Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH10$1,077.93$705.00$725.00$688.68$740.50
0685Mounting assembly, repair/replace/retro- furnish & install, mast arm mounting assembly (0659-1101)EACH6$9,952.03$740.00$765.00$2,109.52$2,268.00
0690Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH2$23,222$24,085$24,000$14,894$16,011
0695Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH6$14,625$12,170$12,500$7,113.86$7,648.00
0700Traffic controller assembly, relocate controller with cabinet (0670-5500)AS1$8,388.28$10,225$10,000$9,022.99$9,700.00
0705Traffic controller, modify (0671-2-40)EACH1$4,454.96$2,285.00$2,300.00$3,384.30$3,638.00
0710Managed field ethernet switch, furnish & install (0684-1-1)EACH1$6,436.87$5,685.00$5,800.00$5,984.88$6,434.00
0715Managed field ethernet switch, remove- cabinet to remain (0684-1-6)EACH1$377.02$275.00$285.00$270.23$290.50
0720Media converter, furnish & install (0684-5-1)EACH2$2,536.36$1,290.00$1,300.00$1,880.56$2,022.00
0725Remote power management rpmu, furnish and install (0685-2-1)EACH1$977.50$1,770.00$1,800.00$1,197.75$1,288.00
0730Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31)EACH4$4,011.60$2,666.52$2,750.00$4,845.51$5,210.00
FDOT contract T5847: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy