FDOT contract T5867 bid tabulation

SR 423 (LEE RD) FROM W OF KINGSWOOD DR TO E OF ADANSON ST. Let by Florida DOT on September 24, 2025, Orange, District 5. 2 bids received; low bid $3,558,075 by Chinchor Electric Inc..

Owner
Florida DOT
Letting
24 SEP 2025
Pay items
132
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chinchor Electric Inc.$3,558,075Low
2Traffic Control Devices, Inc.$3,756,000+6.0%
FDOT contract T5867: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chinchor Electric Inc.2. Traffic Control Devices, Inc.
0005Mobilization (0101-1)LS1$349,305$375,000
0010Maintenance of traffic (0102-1)DA1$145,860$213,000
0015Traffic control officer (0102-14)HR2,640$165.00$122.00
0020Work zone sign (0102-60)ED11,207$0.25$0.30
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED34,720$0.11$0.15
0030Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD270$0.29$0.10
0035Arrow board / advance warning arrow panel (0102-76)ED359$4.71$8.50
0040Portable changeable message sign, temporary (0102-99)ED449$10.59$14.60
0045Temporary signalization and maintenance, intersection (0102-104)ED679$19.80$89.00
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED680$19.80$1.00
0055Type III barricade (0102-115)ED768$0.41$0.40
0060Sediment barrier (0104-10-3)LF1,013$6.30$9.30
0065Inlet protection system (0104-18)EACH20$204.16$570.00
0070Litter removal (0107-1)ACRE19.60$55.00$82.00
0075Mowing (0107-2)ACRE3.78$82.50$292.00
0080Clearing & grubbing (0110-1-1)ACRE1$77,677$92,250
0085Removal of existing concrete (0110-4-10)SY1,055$41.88$46.50
0090Regular excavation (0120-1)CY106.10$156.00$173.00
0095Embankment (0120-6)CY115.70$152.56$170.00
0100Type B stabilization (0160-4)SY133$114.02$126.00
0105Optional base, base group 15 (0285-715)SY369$137.50$152.00
0110Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY8,997$9.13$10.00
0115Superpave asphaltic conc, traffic E (0334-1-15)TN29.90$408.10$452.00
0120Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88)TN768.80$269.50$300.00
0125Inlets, curb, type P-5, <10' (0425-1351)EACH1$12,287$13,620
0130Inlets, curb, type J-3, <10' (0425-1431)EACH1$29,319$32,500
0135Inlets, curb, type J-3, partial (0425-1435)EACH2$11,670$12,935
0140Inlets, curb, type 8, <10' (0425-1481)EACH3$13,891$15,400
0145Inlets, gutter, type V, J bot, <10' (0425-1713)EACH1$22,540$24,985
0150Manholes, P-7, partial (0425-2-43)EACH1$10,687$11,850
0155Manholes, P-8, partial (0425-2-63)EACH2$10,363$11,490
0160Manholes, J-8, partial (0425-2-93)EACH2$7,053.64$7,820.00
0165Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF31$602.59$668.00
0170Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF62$261.80$290.00
0175Pipe culvert, opt material, round, 42"S/CD (0430-175142)LF8$1,914.00$2,121.00
0180Pipe culvert,optional material,other-elip/arch, (0430-175218)LF19$514.37$570.00
0185Concrete curb & gutter, type F (0520-1-10)LF1,521$62.11$69.00
0190Concrete curb, type D (0520-2-4)LF157$128.05$142.00
0195Valley gutter- concrete (0520-3)LF65$78.25$87.00
0200Traffic separator concrete- type IV, 4' wide (0520-5-41)LF338$90.09$100.00
0205Concrete sidewalk and driveways, 4" thick (0522-1)SY344$93.59$104.00
0210Concrete sidewalk and driveways, 6" thick (0522-2)SY452$138.25$153.00
0215Detectable warnings (0527-2)SF325$37.95$42.00
0220Performance turf, sod (0570-1-2)SY471$5.50$22.50
0225Raised pavement marker, type B (0706-1-3)EACH159$5.50$8.50
0230Painted pavement markings, standard, white, solid, 6" (0710-11101)GM0.32$1,760.00$3,050.00
0235Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF1,603$2.20$2.50
0240Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF340$3.03$4.90
0245Painted pavement markings, standard, white, message or symbol (0710-11160)EACH19$99.00$103.00
0250Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.50$1,870.00$3,050.00
0255Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000
0260Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH7$495.00$660.00
0265Single column ground sign assembly, remove (0700-1600)EACH7$110.00$103.00
0270Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH7$605.00$342.00
0275Sign panel, remove, UP to 12 SF (0700-3601)EACH7$88.00$200.00
0280Tubular marker, 36" yellow (0704-1-4)EACH4$113.30$215.00
0285Raised pavement marker, type B (0706-1-3)EACH190$5.50$8.50
0290Painted pavement markings, standard, yellow, island nose (0710-11290)SF26$27.50$18.30
0295Painted pavement markings, surface (0710-90)LS1$15,400$15,100
0300Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,387$3.30$6.10
0305Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF345$8.80$11.00
0310Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.06$13,200$5,487.00
0315Thermoplastic, standard, arrow (0711-11170)EACH19$99.00$135.00
0320Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF5$8.80$8.50
0325Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.14$12,100$5,490.00
0330Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF1,273$14.03$22.00
0335Thermoplastic, preformed, 24" white with 4" black contrast crosswalk on concrete pavement, 32" (0711-14526)LF228$17.33$36.50
0340Thermoplastic, preformed, 24" white with 4" black contrast stop line on concrete 32" (0711-14527)LF12$17.33$36.50
0345Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528)LF923$8.80$18.30
0350Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.54$13,200$12,200
0355Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.10$9,130.00$5,487.00
0360Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.46$13,200$12,200
0365Thermoplastic, standard-other surfaces, yellow, solid, 8" (0711-16202)GM0.01$68,200$13,412
0370Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF264$3.30$18.30
0375Itsfm subsurface documentation- project length (0611-1-1)MI0.46$3,850.00$4,000.00
0380Itsfm location documentation- intersection (0611-2-1)EACH3$1,760.00$1,600.00
0385Conduit, furnish & install, open trench (0630-2-11)LF973$22.22$22.15
0390Conduit, furnish & install, directional bore (0630-2-12)LF1,153$31.67$48.90
0395Conduit, furnish & install, aboveground (0630-2-14)LF420$65.36$52.00
0400Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI3$12,571$16,080
0405Signal cable, remove- intersection (0632-7-6)PI2$5,500.00$1,462.00
0410Fiber optic connection, install, splice (0633-2-31)EACH24$48.14$63.00
0415Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH2$62.98$58.00
0420Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH24$52.91$47.00
0425Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15)EACH2$1,512.50$1,210.00
0430Fiber optic cable locator (0633-6)DA300$198.00$254.00
0435Multi-conductor cable, furnish & install, cat 6 (0633-8-11)LF3,487$5.83$5.00
0440Span wire assembly, F&I, single point, box or drop box (0634-4143)PI3$13,035$5,700.00
0445Fiberglass insulator, furnish & install (0634-5-1)LF463$18.87$41.30
0450Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH74$1,624.49$1,179.00
0455Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH6$2,538.06$3,165.00
0460Electrical power service, F&I, underground, meter by contractor (0639-1122)AS4$3,952.85$6,615.00
0465Electrical service wire, & install (0639-2-1)LF644$5.55$7.60
0470Prestressed concrete pole, type P-II service pole (0641-2-12)EACH4$3,057.15$2,565.00
0475Prestressed concrete pole, type P-VIII (0641-2-18)EACH12$27,719$27,555
0480Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH2$2,640.00$293.00
0485Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH6$12,760$14,210
0490Aluminum signals pole, (0646-1-11)EACH24$2,824.11$2,536.00
0495Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS30$2,090.81$1,890.00
0500Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS6$2,487.25$2,400.00
0505Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS24$1,054.30$871.00
0510Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS3$110.00$50.00
0515Loop detector inductive, remove- cabinet to remain (0660-1600)EACH15$110.00$47.00
0520Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH3$18,166$21,100
0525Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH12$2,729.90$3,590.00
0530Vehicle detection system- avi, bluetooth, furnish & install, cabinet equipment (0660-6121)EACH3$1,030.76$2,750.00
0535Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment (0660-6122)EACH3$7,508.77$8,545.00
0540Pedestrian detector, furnish & install, accessible (0665-1-12)EACH24$1,672.22$1,660.00
0545Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH1$110.00$49.05
0550Traffic controller assembly, F&I, NEMA W/electronic lock (0670-5170)AS1$45,706$51,100
0555Traffic controller, modify (0671-2-40)EACH2$2,640.00$1,885.00
0560Traffic signal controller cabinet, adjust/modify (0676-1500)EACH2$2,640.00$1,955.00
0565Managed field ethernet switch, remove- cabinet to remain (0684-1-6)EACH2$192.50$943.00
0570Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH3$10,526$12,265
0575Remote power management rpmu, furnish and install (0685-2-1)EACH3$692.62$1,865.00
0580Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21)EACH10$7,416.12$6,385.00
0585Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360)EACH5$7,139.00$5,932.00
0590Itsfm location documentation- ITS site (0611-2-2)EACH1$1,320.00$1,600.00
0595Conduit, furnish & install, directional bore (0630-2-12)LF253$22.86$33.00
0600Conduit, furnish & install, aboveground (0630-2-14)LF5$65.36$41.00
0605Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF883$4.35$3.25
0610Fiber optic cable, remove, overhead (0633-1610)LF286$2.48$2.15
0615Fiber optic cable, remove, underground (0633-1620)LF180$2.02$1.95
0620Fiber optic connection, install, splice (0633-2-31)EACH48$48.13$64.00
0625Fiber optic connection hardware, F&I, splice (0633-3-11)EACH2$1,485.00$1,235.00
0630Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH4$62.98$58.00
0635Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH1$52.91$47.00
0640Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15)EACH1$1,512.50$1,210.00
0645Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$1,624.49$1,180.00
0650Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH3$2,538.06$3,165.00
0655Electrical service wire, & install (0639-2-1)LF29$5.55$7.60
0660ITS CCTV camera, relocate (0682-1400)EACH1$1,650.00$4,000.00
FDOT contract T5867: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of September 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy