FDOT contract T7542 bid tabulation

SR 687 (4TH ST N) FROM SR 694 (GANDY BLVD) TO BIG ISLAND GAP. Let by Florida DOT on June 11, 2025, Pinellas, District 7. 9 bids received; low bid $4,497,500 by Gosalia Concrete Constructors, Inc..

Owner
Florida DOT
Letting
11 JUN 2025
Pay items
97
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Gosalia Concrete Constructors, Inc.$4,497,500Low
2Russell Engineering, Inc.$4,637,401+3.0%
3Kamminga & Roodvoets, Inc.$4,761,578+6.0%
4Watson Civil Construction, Inc.$4,849,866+8.0%
5Sun Civil LLC$5,148,763+14%
6Gibbs & Register, Inc.$5,179,170+15%
7Nelson, David, Construction Co.$5,806,043+29%
8Cone & Graham, Inc.$6,522,350+45%
9Crisdel Group, Inc$6,739,018+50%
FDOT contract T7542: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Gosalia Concrete Constructors, Inc.2. Russell Engineering, Inc.3. Kamminga & Roodvoets, Inc.4. Watson Civil Construction, Inc.5. Sun Civil LLC6. Gibbs & Register, Inc.
0005Mobilization (0101-1)LS1$448,401$455,013$399,000$480,000$453,989$497,000
0010Maintenance of traffic (0102-1)DA1$135,000$661,359$195,000$860,000$119,360$447,000
0015Pedestrian or bicycle special detour (0102-4-1)SY1$133,000$255,013$201,000$97,000$115,350$396,500
0020Traffic control officer (0102-14)HR64$95.00$103.00$85.00$92.00$117.60$95.00
0025Work zone sign (0102-60)ED6,384$0.22$0.23$0.22$0.29$0.27$0.29
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED20,004$0.09$0.25$0.09$0.13$0.12$0.11
0035Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD2,028,818$0.03$0.03$0.03$0.05$0.06$0.04
0040Arrow board / advance warning arrow panel (0102-76)ED84$6.00$6.55$6.00$7.30$7.06$11.00
0045Portable changeable message sign, temporary (0102-99)ED315$11.00$13.00$11.00$13.00$14.11$14.00
0050Temporary signalization and maintenance, intersection (0102-104)ED630$23.99$33.00$30.00$45.00$4.27$26.50
0055Temporary traffic detection and maintenance, intersection (0102-107-1)ED630$23.88$45.00$26.00$65.00$4.27$22.50
0060Type III barricade (0102-115)ED168$0.35$0.36$0.35$0.34$0.41$0.45
0065Sediment barrier (0104-10-3)LF10,776$1.53$3.00$3.00$2.35$2.49$3.00
0070Floating turbidity barrier (0104-11)LF321$17.89$23.00$20.00$9.30$17.37$12.00
0075Inlet protection system (0104-18)EACH24$214.70$303.00$238.00$192.00$196.78$250.00
0080Litter removal (0107-1)ACRE497.99$50.00$23.00$40.00$42.00$39.98$55.00
0085Mowing (0107-2)ACRE497.88$50.00$109.00$125.00$76.00$42.34$80.00
0090Clearing & grubbing (0110-1-1)ACRE1$71,838$323,690$449,100$323,000$306,353$307,500
0095Removal of existing concrete (0110-4-10)SY5,537$25.00$16.00$6.00$26.00$44.39$17.00
0100Tree protection barrier (0110-21)LF475$13.00$23.00$10.00$15.50$6.55$11.00
0105Tree root and branch pruning (0110-22)EACH64$812.01$413.00$400.00$675.00$2,001.93$700.00
0110Regular excavation (0120-1)CY2,358$58.50$23.00$50.50$22.00$26.31$8.50
0115Subsoil excavation (0120-4)CY89.70$175.00$69.00$102.00$123.00$97.62$140.00
0120Embankment (0120-6)CY6,669.80$60.00$23.00$59.00$39.00$60.26$30.00
0125Geosynthetic reinforced foundation over soft soil (0145-2)SY2,780$12.50$7.13$50.00$17.00$9.37$27.00
0130Type B stabilization (0160-4)SY17,561$11.15$11.69$20.25$14.00$27.31$22.00
0135Optional base, base group 01 (0285-701)SY13,844$12.50$27.13$22.25$18.00$31.92$22.00
0140Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY1,519$11.78$38.00$10.00$11.10$17.96$55.00
0145Superpave asphaltic conc, traffic B (0334-1-12)TN1,077$209.92$281.00$204.00$198.00$277.54$300.00
0150Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN125.30$317.06$645.00$307.00$347.00$533.90$1,000.00
0155Inlets, DT bot, type C,<10' (0425-1521)EACH1$6,000.00$7,409.00$4,975.00$5,300.00$6,595.87$6,000.00
0160Inlets, ditch bottom, type D, J bot, <10' (0425-1543)EACH1$7,500.00$7,113.00$9,850.00$7,500.00$12,409$8,000.00
0165Inlets, DT bot, type E, <10' (0425-1551)EACH21$7,400.00$7,903.00$9,150.00$7,000.00$8,964.67$8,000.00
0170Manholes, P-7, <10' (0425-2-41)EACH3$8,000.00$8,555.00$7,500.00$5,900.00$9,016.44$6,500.00
0175Pipe culvert, optional material, round, 18"SD (0430-174118)LF1,681$275.00$103.00$137.00$129.00$221.33$150.00
0180Pipe culvert, optional material, round, 24"SD (0430-174124)LF2,448$305.00$123.00$170.00$163.00$206.33$175.00
0185Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218)LF6$2,000.00$423.00$264.00$507.00$284.15$950.00
0190Pipe culvert, optional material, other shape - ellip/arch, 24"SD (0430-174224)LF12$1,100.00$383.00$305.00$547.00$349.72$600.00
0195Straight concrete endwalls, single, 0 degrees, elliptical (0430-524102)EACH1$7,500.00$5,313.00$9,500.00$4,800.00$5,545.80$7,500.00
0200Pipe filling and plugging- place out of service (0430-830)CY21$700.00$303.00$630.00$630.00$702.69$700.00
0205Mitered end section, optional round, 18" SD (0430-984125)EACH1$3,650.00$2,455.00$3,500.00$2,100.00$3,922.82$4,500.00
0210Mitered end section, optional round, 24" SD (0430-984129)EACH1$3,950.00$2,669.00$7,500.00$2,500.00$4,214.02$5,000.00
0215Concrete curb & gutter, type E (0520-1-7)LF187$82.00$76.00$53.00$80.00$58.62$60.00
0220Concrete curb & gutter, type F (0520-1-10)LF102$85.00$73.00$59.00$72.00$51.23$60.00
0225Concrete curb, type A (0520-2-1)LF35$70.00$87.00$62.00$69.00$59.65$75.00
0230Concrete curb, type B (0520-2-2)LF52$70.00$70.00$55.00$84.00$66.76$60.00
0235Concrete curb, type D (0520-2-4)LF18$70.00$95.00$78.00$125.00$92.08$55.00
0240Concrete sidewalk and driveways, 6" thick (0522-2)SY358$168.00$95.00$94.00$87.00$118.42$90.00
0245Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY58$220.00$127.00$186.00$158.00$129.41$102.00
0250Detectable warnings (0527-2)SF451$45.00$32.13$36.00$31.00$28.22$48.00
0255Performance turf, sod (0570-1-2)SY26,883$5.50$6.69$9.00$7.00$5.08$6.00
0260Painted pavement markings, standard, white, solid, 6" (0710-11101)GM0.01$2,142.86$5,013.00$23,785$4,170.00$1,764.00$8,000.00
0265Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF1,082$4.00$1.90$0.75$2.20$2.35$2.00
0270Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF335$6.00$2.13$1.50$2.35$3.53$2.25
0275Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.01$1,428.57$1,255.00$23,785$1,050.00$1,764.00$2,000.00
0280Initial contingency amount, DO not bid (0999-25)LS1$51,000$51,000$51,000$51,000$51,000$51,000
0285Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH22$432.88$509.00$350.00$438.00$646.80$575.00
0290Single column ground sign assembly, relocate (0700-1500)EACH10$325.43$213.00$200.00$329.00$352.80$225.00
0295Single column ground sign assembly, remove (0700-1600)EACH6$51.66$76.00$150.00$53.00$58.80$80.00
0300Multi-column ground sign assembly, relocate (0700-2500)EACH2$6,715.25$7,555.00$200.00$6,800.00$8,820.00$8,500.00
0305Raised pavement marker, type B (0706-1-3)EACH6$6.00$20.13$7.00$23.40$7.06$22.00
0310Painted pavement markings, surface (0710-90)LS1$10,000$4,680.00$1,600.00$5,000.00$11,760$5,500.00
0315Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF772$8.00$3.13$4.50$3.65$9.41$3.50
0320Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF721$12.00$6.23$7.50$7.25$14.11$7.00
0325Thermoplastic, standard, message or symbol (0711-11160)EACH1$300.00$203.00$600.00$237.00$294.00$225.00
0330Thermoplastic, standard, arrow (0711-11170)EACH1$150.00$85.55$600.00$100.00$117.60$95.00
0335Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.01$7,142.86$8,269.00$15,857$6,900.00$10,584$14,000
0340Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.01$10,000$8,269.00$15,900$9,700.00$10,584$9,000.00
0345Conduit, furnish & install, open trench (0630-2-11)LF40$22.07$23.00$19.25$21.00$48.26$175.00
0350Conduit, furnish & install, directional bore (0630-2-12)LF242$36.00$32.00$28.00$32.00$31.43$50.00
0355Conduit, furnish & install, aboveground (0630-2-14)LF228$38.80$36.00$55.00$37.00$55.41$75.00
0360Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$1,569.66$1,213.00$1,797.00$1,300.00$1,830.55$2,500.00
0365Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF1,108$2.81$2.09$3.25$2.10$2.25$5.50
0370Luminaire & bracket arm- galv steel, furnish & install new luminaire and arm on new/existing pole (0715-5-32)EACH3$2,446.44$2,213.00$7,865.00$2,300.00$2,996.46$4,000.00
0375Load center, relocate, secondary voltage (0715-7-31)EACH1$3,810.24$6,555.00$7,724.00$6,800.00$5,549.47$14,000
0380Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH4$1,583.27$1,555.00$1,274.70$1,600.00$1,201.47$1,600.00
0385Luminaire, remove (0715-11500)EACH4$262.64$580.00$150.00$595.00$164.44$450.00
0390Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH3$815.17$655.00$875.00$672.00$700.87$1,000.00
0395Conduit, furnish & install, open trench (0630-2-11)LF146$25.93$23.00$19.25$21.00$56.75$65.00
0400Conduit, furnish & install, directional bore (0630-2-12)LF201$46.34$32.03$41.50$33.00$54.23$70.00
0405Conduit, furnish & install, aboveground (0630-2-14)LF6$38.80$35.55$55.00$37.00$110.83$250.00
0410Signal cable- repair/replace/other, furnish & install (0632-7-2)LF391$11.46$8.06$20.00$8.25$9.44$25.00
0415Signal cable, remove- outside intersection (0632-7-7)LF450$1.91$1.03$2.00$1.05$1.64$3.00
0420Fiber optic cable locator (0633-6)DA315$273.29$323.00$315.00$400.00$300.80$300.00
0425Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH15$1,564.76$1,213.00$1,797.00$1,300.00$1,451.54$2,500.00
0430Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$5,616.73$6,055.00$5,500.00$6,250.00$4,605.61$8,500.00
0435Electrical service wire, & install (0639-2-1)LF43$14.32$5.09$20.00$5.20$10.30$17.00
0440Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,286.14$1,555.00$2,976.00$1,600.00$2,939.17$1,600.00
0445Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH1$1,017.10$569.00$1,035.00$590.00$986.63$2,300.00
0450Aluminum signals pole, (0646-1-11)EACH8$2,869.94$3,326.00$2,984.00$3,450.00$2,488.57$3,000.00
0455Aluminum signals pole, remove (0646-1-60)EACH8$683.15$955.00$600.00$970.00$493.32$900.00
0460Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$1,063.23$1,055.00$1,276.80$1,100.00$936.83$1,300.00
0465Vehicle detection system- adjust/modify cabinet (0660-4-51)EACH2$1,887.64$2,013.00$1,725.00$2,100.00$1,315.51$1,000.00
0470Vehicle detection system- adjust/modify above ground equipment (0660-4-52)EACH4$1,738.83$2,055.00$1,887.00$2,150.00$1,201.20$3,500.00
0475Pedestrian detector, furnish & install, standard (0665-1-11)EACH8$850.00$455.00$1,020.00$465.00$496.99$400.00
0480Traffic controller, modify (0671-2-40)EACH2$2,100.12$3,055.00$4,500.00$3,200.00$1,058.16$1,300.00
0485Traffic signal controller cabinet, adjust/modify (0676-1500)EACH2$3,078.65$383.00$5,216.00$388.00$1,887.70$6,500.00
FDOT contract T7542: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy