FDOT contract T7542 bid tabulation
SR 687 (4TH ST N) FROM SR 694 (GANDY BLVD) TO BIG ISLAND GAP. Let by Florida DOT on June 11, 2025, Pinellas, District 7. 9 bids received; low bid $4,497,500 by Gosalia Concrete Constructors, Inc..
- Owner
- Florida DOT
- Letting
- 11 JUN 2025
- Pay items
- 97
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gosalia Concrete Constructors, Inc. | $4,497,500 | Low |
| 2 | Russell Engineering, Inc. | $4,637,401 | +3.0% |
| 3 | Kamminga & Roodvoets, Inc. | $4,761,578 | +6.0% |
| 4 | Watson Civil Construction, Inc. | $4,849,866 | +8.0% |
| 5 | Sun Civil LLC | $5,148,763 | +14% |
| 6 | Gibbs & Register, Inc. | $5,179,170 | +15% |
| 7 | Nelson, David, Construction Co. | $5,806,043 | +29% |
| 8 | Cone & Graham, Inc. | $6,522,350 | +45% |
| 9 | Crisdel Group, Inc | $6,739,018 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gosalia Concrete Constructors, Inc. | 2. Russell Engineering, Inc. | 3. Kamminga & Roodvoets, Inc. | 4. Watson Civil Construction, Inc. | 5. Sun Civil LLC | 6. Gibbs & Register, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $448,401 | $455,013 | $399,000 | $480,000 | $453,989 | $497,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $135,000 | $661,359 | $195,000 | $860,000 | $119,360 | $447,000 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $133,000 | $255,013 | $201,000 | $97,000 | $115,350 | $396,500 |
| 0020 | Traffic control officer (0102-14) | HR | 64 | $95.00 | $103.00 | $85.00 | $92.00 | $117.60 | $95.00 |
| 0025 | Work zone sign (0102-60) | ED | 6,384 | $0.22 | $0.23 | $0.22 | $0.29 | $0.27 | $0.29 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 20,004 | $0.09 | $0.25 | $0.09 | $0.13 | $0.12 | $0.11 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 2,028,818 | $0.03 | $0.03 | $0.03 | $0.05 | $0.06 | $0.04 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 84 | $6.00 | $6.55 | $6.00 | $7.30 | $7.06 | $11.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 315 | $11.00 | $13.00 | $11.00 | $13.00 | $14.11 | $14.00 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 630 | $23.99 | $33.00 | $30.00 | $45.00 | $4.27 | $26.50 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 630 | $23.88 | $45.00 | $26.00 | $65.00 | $4.27 | $22.50 |
| 0060 | Type III barricade (0102-115) | ED | 168 | $0.35 | $0.36 | $0.35 | $0.34 | $0.41 | $0.45 |
| 0065 | Sediment barrier (0104-10-3) | LF | 10,776 | $1.53 | $3.00 | $3.00 | $2.35 | $2.49 | $3.00 |
| 0070 | Floating turbidity barrier (0104-11) | LF | 321 | $17.89 | $23.00 | $20.00 | $9.30 | $17.37 | $12.00 |
| 0075 | Inlet protection system (0104-18) | EACH | 24 | $214.70 | $303.00 | $238.00 | $192.00 | $196.78 | $250.00 |
| 0080 | Litter removal (0107-1) | ACRE | 497.99 | $50.00 | $23.00 | $40.00 | $42.00 | $39.98 | $55.00 |
| 0085 | Mowing (0107-2) | ACRE | 497.88 | $50.00 | $109.00 | $125.00 | $76.00 | $42.34 | $80.00 |
| 0090 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $71,838 | $323,690 | $449,100 | $323,000 | $306,353 | $307,500 |
| 0095 | Removal of existing concrete (0110-4-10) | SY | 5,537 | $25.00 | $16.00 | $6.00 | $26.00 | $44.39 | $17.00 |
| 0100 | Tree protection barrier (0110-21) | LF | 475 | $13.00 | $23.00 | $10.00 | $15.50 | $6.55 | $11.00 |
| 0105 | Tree root and branch pruning (0110-22) | EACH | 64 | $812.01 | $413.00 | $400.00 | $675.00 | $2,001.93 | $700.00 |
| 0110 | Regular excavation (0120-1) | CY | 2,358 | $58.50 | $23.00 | $50.50 | $22.00 | $26.31 | $8.50 |
| 0115 | Subsoil excavation (0120-4) | CY | 89.70 | $175.00 | $69.00 | $102.00 | $123.00 | $97.62 | $140.00 |
| 0120 | Embankment (0120-6) | CY | 6,669.80 | $60.00 | $23.00 | $59.00 | $39.00 | $60.26 | $30.00 |
| 0125 | Geosynthetic reinforced foundation over soft soil (0145-2) | SY | 2,780 | $12.50 | $7.13 | $50.00 | $17.00 | $9.37 | $27.00 |
| 0130 | Type B stabilization (0160-4) | SY | 17,561 | $11.15 | $11.69 | $20.25 | $14.00 | $27.31 | $22.00 |
| 0135 | Optional base, base group 01 (0285-701) | SY | 13,844 | $12.50 | $27.13 | $22.25 | $18.00 | $31.92 | $22.00 |
| 0140 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 1,519 | $11.78 | $38.00 | $10.00 | $11.10 | $17.96 | $55.00 |
| 0145 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 1,077 | $209.92 | $281.00 | $204.00 | $198.00 | $277.54 | $300.00 |
| 0150 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 125.30 | $317.06 | $645.00 | $307.00 | $347.00 | $533.90 | $1,000.00 |
| 0155 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $6,000.00 | $7,409.00 | $4,975.00 | $5,300.00 | $6,595.87 | $6,000.00 |
| 0160 | Inlets, ditch bottom, type D, J bot, <10' (0425-1543) | EACH | 1 | $7,500.00 | $7,113.00 | $9,850.00 | $7,500.00 | $12,409 | $8,000.00 |
| 0165 | Inlets, DT bot, type E, <10' (0425-1551) | EACH | 21 | $7,400.00 | $7,903.00 | $9,150.00 | $7,000.00 | $8,964.67 | $8,000.00 |
| 0170 | Manholes, P-7, <10' (0425-2-41) | EACH | 3 | $8,000.00 | $8,555.00 | $7,500.00 | $5,900.00 | $9,016.44 | $6,500.00 |
| 0175 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 1,681 | $275.00 | $103.00 | $137.00 | $129.00 | $221.33 | $150.00 |
| 0180 | Pipe culvert, optional material, round, 24"SD (0430-174124) | LF | 2,448 | $305.00 | $123.00 | $170.00 | $163.00 | $206.33 | $175.00 |
| 0185 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 6 | $2,000.00 | $423.00 | $264.00 | $507.00 | $284.15 | $950.00 |
| 0190 | Pipe culvert, optional material, other shape - ellip/arch, 24"SD (0430-174224) | LF | 12 | $1,100.00 | $383.00 | $305.00 | $547.00 | $349.72 | $600.00 |
| 0195 | Straight concrete endwalls, single, 0 degrees, elliptical (0430-524102) | EACH | 1 | $7,500.00 | $5,313.00 | $9,500.00 | $4,800.00 | $5,545.80 | $7,500.00 |
| 0200 | Pipe filling and plugging- place out of service (0430-830) | CY | 21 | $700.00 | $303.00 | $630.00 | $630.00 | $702.69 | $700.00 |
| 0205 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 1 | $3,650.00 | $2,455.00 | $3,500.00 | $2,100.00 | $3,922.82 | $4,500.00 |
| 0210 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 1 | $3,950.00 | $2,669.00 | $7,500.00 | $2,500.00 | $4,214.02 | $5,000.00 |
| 0215 | Concrete curb & gutter, type E (0520-1-7) | LF | 187 | $82.00 | $76.00 | $53.00 | $80.00 | $58.62 | $60.00 |
| 0220 | Concrete curb & gutter, type F (0520-1-10) | LF | 102 | $85.00 | $73.00 | $59.00 | $72.00 | $51.23 | $60.00 |
| 0225 | Concrete curb, type A (0520-2-1) | LF | 35 | $70.00 | $87.00 | $62.00 | $69.00 | $59.65 | $75.00 |
| 0230 | Concrete curb, type B (0520-2-2) | LF | 52 | $70.00 | $70.00 | $55.00 | $84.00 | $66.76 | $60.00 |
| 0235 | Concrete curb, type D (0520-2-4) | LF | 18 | $70.00 | $95.00 | $78.00 | $125.00 | $92.08 | $55.00 |
| 0240 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 358 | $168.00 | $95.00 | $94.00 | $87.00 | $118.42 | $90.00 |
| 0245 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 58 | $220.00 | $127.00 | $186.00 | $158.00 | $129.41 | $102.00 |
| 0250 | Detectable warnings (0527-2) | SF | 451 | $45.00 | $32.13 | $36.00 | $31.00 | $28.22 | $48.00 |
| 0255 | Performance turf, sod (0570-1-2) | SY | 26,883 | $5.50 | $6.69 | $9.00 | $7.00 | $5.08 | $6.00 |
| 0260 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.01 | $2,142.86 | $5,013.00 | $23,785 | $4,170.00 | $1,764.00 | $8,000.00 |
| 0265 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,082 | $4.00 | $1.90 | $0.75 | $2.20 | $2.35 | $2.00 |
| 0270 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 335 | $6.00 | $2.13 | $1.50 | $2.35 | $3.53 | $2.25 |
| 0275 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.01 | $1,428.57 | $1,255.00 | $23,785 | $1,050.00 | $1,764.00 | $2,000.00 |
| 0280 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $51,000 | $51,000 | $51,000 | $51,000 | $51,000 | $51,000 |
| 0285 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 22 | $432.88 | $509.00 | $350.00 | $438.00 | $646.80 | $575.00 |
| 0290 | Single column ground sign assembly, relocate (0700-1500) | EACH | 10 | $325.43 | $213.00 | $200.00 | $329.00 | $352.80 | $225.00 |
| 0295 | Single column ground sign assembly, remove (0700-1600) | EACH | 6 | $51.66 | $76.00 | $150.00 | $53.00 | $58.80 | $80.00 |
| 0300 | Multi-column ground sign assembly, relocate (0700-2500) | EACH | 2 | $6,715.25 | $7,555.00 | $200.00 | $6,800.00 | $8,820.00 | $8,500.00 |
| 0305 | Raised pavement marker, type B (0706-1-3) | EACH | 6 | $6.00 | $20.13 | $7.00 | $23.40 | $7.06 | $22.00 |
| 0310 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,000 | $4,680.00 | $1,600.00 | $5,000.00 | $11,760 | $5,500.00 |
| 0315 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 772 | $8.00 | $3.13 | $4.50 | $3.65 | $9.41 | $3.50 |
| 0320 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 721 | $12.00 | $6.23 | $7.50 | $7.25 | $14.11 | $7.00 |
| 0325 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 1 | $300.00 | $203.00 | $600.00 | $237.00 | $294.00 | $225.00 |
| 0330 | Thermoplastic, standard, arrow (0711-11170) | EACH | 1 | $150.00 | $85.55 | $600.00 | $100.00 | $117.60 | $95.00 |
| 0335 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.01 | $7,142.86 | $8,269.00 | $15,857 | $6,900.00 | $10,584 | $14,000 |
| 0340 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.01 | $10,000 | $8,269.00 | $15,900 | $9,700.00 | $10,584 | $9,000.00 |
| 0345 | Conduit, furnish & install, open trench (0630-2-11) | LF | 40 | $22.07 | $23.00 | $19.25 | $21.00 | $48.26 | $175.00 |
| 0350 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 242 | $36.00 | $32.00 | $28.00 | $32.00 | $31.43 | $50.00 |
| 0355 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 228 | $38.80 | $36.00 | $55.00 | $37.00 | $55.41 | $75.00 |
| 0360 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 4 | $1,569.66 | $1,213.00 | $1,797.00 | $1,300.00 | $1,830.55 | $2,500.00 |
| 0365 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,108 | $2.81 | $2.09 | $3.25 | $2.10 | $2.25 | $5.50 |
| 0370 | Luminaire & bracket arm- galv steel, furnish & install new luminaire and arm on new/existing pole (0715-5-32) | EACH | 3 | $2,446.44 | $2,213.00 | $7,865.00 | $2,300.00 | $2,996.46 | $4,000.00 |
| 0375 | Load center, relocate, secondary voltage (0715-7-31) | EACH | 1 | $3,810.24 | $6,555.00 | $7,724.00 | $6,800.00 | $5,549.47 | $14,000 |
| 0380 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 4 | $1,583.27 | $1,555.00 | $1,274.70 | $1,600.00 | $1,201.47 | $1,600.00 |
| 0385 | Luminaire, remove (0715-11500) | EACH | 4 | $262.64 | $580.00 | $150.00 | $595.00 | $164.44 | $450.00 |
| 0390 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 3 | $815.17 | $655.00 | $875.00 | $672.00 | $700.87 | $1,000.00 |
| 0395 | Conduit, furnish & install, open trench (0630-2-11) | LF | 146 | $25.93 | $23.00 | $19.25 | $21.00 | $56.75 | $65.00 |
| 0400 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 201 | $46.34 | $32.03 | $41.50 | $33.00 | $54.23 | $70.00 |
| 0405 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 6 | $38.80 | $35.55 | $55.00 | $37.00 | $110.83 | $250.00 |
| 0410 | Signal cable- repair/replace/other, furnish & install (0632-7-2) | LF | 391 | $11.46 | $8.06 | $20.00 | $8.25 | $9.44 | $25.00 |
| 0415 | Signal cable, remove- outside intersection (0632-7-7) | LF | 450 | $1.91 | $1.03 | $2.00 | $1.05 | $1.64 | $3.00 |
| 0420 | Fiber optic cable locator (0633-6) | DA | 315 | $273.29 | $323.00 | $315.00 | $400.00 | $300.80 | $300.00 |
| 0425 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 15 | $1,564.76 | $1,213.00 | $1,797.00 | $1,300.00 | $1,451.54 | $2,500.00 |
| 0430 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $5,616.73 | $6,055.00 | $5,500.00 | $6,250.00 | $4,605.61 | $8,500.00 |
| 0435 | Electrical service wire, & install (0639-2-1) | LF | 43 | $14.32 | $5.09 | $20.00 | $5.20 | $10.30 | $17.00 |
| 0440 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,286.14 | $1,555.00 | $2,976.00 | $1,600.00 | $2,939.17 | $1,600.00 |
| 0445 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $1,017.10 | $569.00 | $1,035.00 | $590.00 | $986.63 | $2,300.00 |
| 0450 | Aluminum signals pole, (0646-1-11) | EACH | 8 | $2,869.94 | $3,326.00 | $2,984.00 | $3,450.00 | $2,488.57 | $3,000.00 |
| 0455 | Aluminum signals pole, remove (0646-1-60) | EACH | 8 | $683.15 | $955.00 | $600.00 | $970.00 | $493.32 | $900.00 |
| 0460 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 8 | $1,063.23 | $1,055.00 | $1,276.80 | $1,100.00 | $936.83 | $1,300.00 |
| 0465 | Vehicle detection system- adjust/modify cabinet (0660-4-51) | EACH | 2 | $1,887.64 | $2,013.00 | $1,725.00 | $2,100.00 | $1,315.51 | $1,000.00 |
| 0470 | Vehicle detection system- adjust/modify above ground equipment (0660-4-52) | EACH | 4 | $1,738.83 | $2,055.00 | $1,887.00 | $2,150.00 | $1,201.20 | $3,500.00 |
| 0475 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 8 | $850.00 | $455.00 | $1,020.00 | $465.00 | $496.99 | $400.00 |
| 0480 | Traffic controller, modify (0671-2-40) | EACH | 2 | $2,100.12 | $3,055.00 | $4,500.00 | $3,200.00 | $1,058.16 | $1,300.00 |
| 0485 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 2 | $3,078.65 | $383.00 | $5,216.00 | $388.00 | $1,887.70 | $6,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.